U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #3
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #3
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 9/14/2016
Reporting Period: 9/1/2016 - 9/14/2016

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative

Contractors finalized preparations for contaminated sediment and bank soil excavation in BRSA 1, which will begin this week. Excavation in Cell 1 of BRSA 1 will primarily involve bank soils.

2.1.2 Response Actions to Date

The following activities took place during the reporting period:

- Complete construction & testing of WWTP in the BRSA 1 forward staging area;

- Start-up of particulate (dust) monitoring system in BRSA 1;

- Installation and start-up of turbidity monitoring in Kalamazoo River around BRSA 1 excavation area (1 upstream monitor and 2 downstream monitors);

- Completion of the BRSA 1 staging area, including the contaminated sediments staging area, support areas, and riverbank access roads;

- Installation of water management infrastructure (sediment curtain, coffer dam, HDPE pipe) to support excavation activities in BRSA 1;

- Completion of mussel survey/relocation; and

- Continuation of bathymetric/hydrographic/overbank surveying activities. 

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

Waste Stream Medium Quantity Manifest # Treatment Disposal
 
     
           
           


  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

- Excavation of contaminated sediments and bank soils in BRSA 1;

- Solidification/staging/transport of contaminated sediments & bank soils for disposal at approved landfill facilities;

- Reconstruction/restoration of excavated areas in BRSA 1;

- Operation of dust & turbidity monitoring systems in BRSA 1; and

- Completion of bathymetric/hydrographic/overbank surveying activities.

2.2.1.1 Planned Response Activities

See Section 2.2.1

2.2.1.2 Next Steps
See Section 2.2.1

2.2.2 Issues

None

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

See PolRep #1

2.5.2 Liaison Officer

Diane Russell (US EPA) continues in the role of CIC.  

2.5.3 Information Officer

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

US EPA - 1

Michigan DNR - 1

START (US EPA contractor) - 2

Envirocon (general contractor): 16

ProAct (WWTP contractor): 2

AMEC-FW (project consultant): 3

Spicer Group (surveyors): 3

Environmental Solutions & Innovations, Inc. (mussel survey/relocation sub-contractor): 2

TOTAL: 30

5. Definition of Terms
 

GC                     General Contractor

AMEC-FW         AMEC Foster Wheeler

BRSA                Bank Removal and Stabilization Area

CIC                   Community Involvement Coordinator

HDPE                High Density Polyethylene

Michigan DNR  Michigan Department of Natural Resources

OSC                  On Scene Coordinator

PolRep              Pollution Report

PRP                  Potentially Responsible Party 

US EPA             United States Environmental Protection Agency

WWTP               Waste Water Treatment Plant

 

6. Additional sources of information
 

6.1 Internet location of additional information/report

http://www.epaosc.org/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule

PolReps are generated every two weeks during active field activities.

7. Situational Reference Materials
  No information available at this time.