U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #15
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #15
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 5/12/2017
Reporting Period: 4/29/2017 - 5/12/2017

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
Excavation of contaminated riverbank soils is underway in BRSA 3. Contaminated soils/sediments are being loaded out for transport & disposal at EPA approved landfill facilities. Preparation for excavation activities in BRSA 4 continues.

2.1.2 Response Actions During Reporting Period

The following activities took place during the reporting period:

- Excavation of contaminated soils with confirmation sampling results received from 9 grids in BRSA 3 (see table below for results). There are 17 total grids in BRSA 3, with each grid consisting of approximately 50 lineal feet of riverbank. The target clean-up goal in the riverbank soils is 5 mg/kg total PCBs;

BRSA 3

GRID

 

TOTAL ESTIMATED EXCAVATION DEPTH (in)

 

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

 

1

 

18

 

0.57

 

2

 

18

 

0.59

 

3

 

18

 

0.44

 

4

 

18

 

0.69

 

5

 

18

 

1.20

 

6

 

18

 

0.44

 

7

 

18

 

0.18

 

8

 

18

 

0.043

 

9

 

18

 

ND

 

                                            ND: Non-detect          

Note: Confirmatory sampling takes place immediately following excavation of contaminated soils in accordance with procedures outlined in the Field Sampling Plan and the Technical Memorandum for BRSA 3. Both documents can be found in the ‘Documents' Section of the project website.

- Transport/disposal of approximately 352 tons of excavated soils to an EPA approved landfill facility. An estimated 750 cubic yards of contaminated soils have been excavated from BRSA 3 to date;

- Treatment of contact water from contaminated grids and the contaminated soils staging pad in the on site WWTP. Approximately 9400 gallons were treated during the reporting period. Sampling results continue to confirm non-detect levels for total PCBs in treated water;

- Staging of sand bags and construction of approximately 300 feet of coffer dam in BRSA 4 (see photo);

- Daily particulate monitoring (PM10) around the perimeter of BRSA 3 and BRSA 4 with no sustained exceedance off site of particulates above the action level of 1.5 mg/m3;

- Turbidity control measures and monitoring in Kalamazoo River around the BRSA 3-9 excavation area (1 upstream monitor and 2 downstream monitors) with no sustained exceedance of the action level of 50 NTUs above upstream levels;

- Removal and dismantlement of floating ice boom (see photo) in front of temporary WCS; and

- Monitoring & maintenance of the temporary WCS.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.

Waste Stream Medium Quantity Total               Manifest #  Treatment Disposal
 Cardboard solid 20 lbs 620 lbs NA recycling Otsego Recycling Center
 Plastic solid 10 lbs 200 lbs NA recycling Otsego Recycling Center
 Steel solid 20 lbs 9100 lbs various  recycling Broken Arrow Recycling
 Contaminated soil (< 50 ppm* PCBs) solid 352 tons (est) 7325.91 tons (est) various disposal Republic Ottawa County Farms Landfill, Coopersville, MI
 Contaminated soil
(> 50 ppm* PCBs)
solid 0 tons 103.91 tons     various disposal US Ecology Michigan,
Belleville, MI
 Contact water liquid 9400 gal           312,475 gal  NA on-site WWTP On-site reuse/discharge to Kalamazoo River
*Note: 1 ppm = 1 mg/kg

  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

- Completion of contaminated riverbank soil excavation in remaining grids of BRSA 3;
- Solidification/staging/transport of contaminated sediments & bank soils for disposal;
- Reconstruction & restoration of excavated grids in BRSA 3;
- Treatment of contact water in the on site WWTP;
- Construction of staging area, stabilization pad & wastewater treatment plant (WWTP) in BRSA 4;
- Installation of sand bag coffer dam and sheet piling to prepare for excavation of contaminated sediments in BRSA 4;
- Operation of dust and turbidity control/monitoring systems; and
- Maintenance/monitoring of the temporary WCS.

2.2.1.1 Planned Response Activities

See Sections 2.2.1 & 2.2.1.2

2.2.1.2 Administrative Activities / Next Steps
- AMEC-FW will provide a revised draft TM for BRSAs 4, 6 & 9 incorporating US EPA comments to the BRSAs 6 & 9 sections of the document.
- Planning meetings continue on a draft TM for BRSAs 7 & 8, which will include plans for removal of the temporary WCS.  MDEQ provided feedback on preliminary plans provided by AMEC on the approach in BRSAs 7 & 8 on May 12.
- Planning continues on a draft restoration plan for the spillway area adjacent to the temporary WCS. Project staff are coordinating with electric & gas utility companies as well as the Allegan County Roads Commission in planning efforts.

2.2.2 Issues

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

A safety meeting is held prior to start of work each day. The meeting is led by on-site safety officer(s) representing both Envirocon and AMEC-FW.  A 'safety stand down' was held with the entire work crew on May 10 to reinforce safety policies and procedures.

2.5.2 Liaison Officer

2.5.3 Information Officer
- US EPA continues to meet with residents neighboring the project area to provide updates on construction plans for 2017 and answer questions relating to the project.
- Community Involvement coordinator held sessions on May 10 in Otsego and May 11 in Plainwell. A recommendation was made to hold a public meeting in Otsego to provide an update on progress as well as construction plans for 2017.
- A flyer will be distributed door to door to neighbors in the vicinity of BRSA 4 notifying them of increased noise from upcoming sheet pile installation activities.

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

US EPA - 1
START - 1
Michigan DNR - 1
Michigan DEQ - 1
Envirocon: 24
AMEC-FW: 2
Spicer Group: 1

TOTAL: 31

5. Definition of Terms
  AMEC-FW           AMEC Foster Wheeler
BRSA                  Bank Removal and Stabilization Area
GC                      General Contractor     
mg/kg                  milligrams per kilogram
MDEQ                 Michigan Department of Environmental Quality
MDNR                 Michigan Department of Natural Resources
MDOT                 Michigan Department of Transportation     
OSC                   On Scene Coordinator
PCBs                  Poly-chlorinated biphenyls
PolRep               Pollution Report
ppm                    parts per million
PRP                    Potentially Responsible Party
TM                      Technical Memorandum
US EPA              United States Environmental Protection Agency
WCS                   Water Control Structure
WWTP                Waste Water Treatment Plant     

6. Additional sources of information
 

6.1 Internet location of additional information/report

http://www.epaosc.org/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
The next PolRep will be generated on May 26.

7. Situational Reference Materials
  No information available at this time.


Click here to view Attached Images