U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V
|
Subject:
|
POLREP #23
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333
|
To:
|
Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI
|
From:
|
Paul Ruesch, OSC
|
Date:
|
9/1/2017
|
Reporting Period:
|
8/19/2017 - 9/1/2017
|
1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
059B |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
4/6/2016 |
Response Authority: |
CERCLA |
|
Response Type: |
PRP Oversight |
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
NPL Status: |
NPL |
|
Operable Unit: |
5 |
Mobilization Date: |
8/1/2016 |
|
Start Date: |
8/1/2016 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
MID006007306 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
DEQ |
FPN#: |
|
|
Reimbursable Account #: |
059B |
1.1.1 Incident Category
Time Critical Removal Action - PRP Oversight
1.1.2 Site Description
See PolRep #1
1.1.2.1 Location
See PolRep #1
1.1.2.2 Description of Threat
See PolRep #1
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See PolRep #1
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
Excavation of contaminated riverbank soils and in-stream sediments is complete in BRSA 4. Removal operations continue in BRSA 6. The staging area is nearly completed in BRSA 9.
2.1.2 Response Actions During Reporting Period
BRSA 4
- Excavation of contaminated soils and sediments was completed, with confirmation results received, in both riverbank grids 44-46 and the adjacent stream tube grids (see Tables 1 & 2);
- Completed transportation and disposal of contaminated soils and sediments for disposal;
- Demobilization of the WWTP, office trailer, equipment and supplies; and
- Backfilling, grading, stabilization and restoration of river banks continues.
BRSA 6
- Excavation of contaminated soils continues with excavation completed and confirmation results received in riverbank grids 6-8. There are 54 total grids in BRSA 6, with each grid consisting of approximately 50 lineal feet of riverbank. There are 4 stream tubes, with each stream tube varying in size. The target clean-up goal in the riverbank soils is 5 mg/kg total PCBs and in-stream sediments is 1mg/kg total PCBs; and
- Completed construction of sheet pile coffer dam systems to facilitate removal of riverbank soils and in-stream sediments.
Estimated excavation depths and confirmation sampling results are found below for riverbank grids in BRSA 4 (Table 1) and adjacent stream tube grids (Table 2) along with results from BRSA 6 (Table 3) and adjacent stream tube grids (Table 4).
BRSA 4
RIVERBANK
GRID
|
TOTAL ESTIMATED EXCAVATION DEPTH (in)
|
FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)
|
44
|
48
|
0.065
|
45
|
36
|
0.39
|
46
|
36
|
0.36
|
Table 1. BRSA 4
Riverbank Grid Confirmatory Sampling Results
|
BRSA 4
STREAM TUBE GRID*
|
TOTAL ESTIMATED EXCAVATION DEPTH (in)
|
FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)
|
19D-44
|
6
|
0.19
|
19D-45
|
6
|
0.074
|
19D-46
|
6
|
0.13
|
Table 2. BRSA 4
Stream Tube Confirmatory Sampling Results
|
BRSA 6
RIVERBANK GRID
|
TOTAL ESTIMATED EXCAVATION DEPTH (in)
|
FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)
|
6
|
12
|
0.46
|
7
|
12
|
<0.032
|
8
|
12
|
1.00
|
Table 3. BRSA 6 Riverbank
Grid Confirmatory Sampling Results
|
BRSA 6
STREAM TUBE
|
TOTAL ESTIMATED EXCAVATION DEPTH (in)
|
FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)
|
17D-6
|
24
|
<0.039
|
17D-7
|
24
|
0.048
|
17D-8
|
24
|
0.18
|
Table 4. BRSA 6
Stream Tube Confirmatory Sampling Results
|
Table Notes: Confirmatory sampling takes place immediately following excavation of contaminated soils and/or sediments in accordance with procedures outlined in the FSP and the TM for BRSAs 4, 5, 6 & 9. Both documents can be found in the ‘Documents' Section of the project website. Stream Tube grids are numbered consistent with the riverbank grid they are located adjacent to. A figure showing the location of both (preliminary) riverbank grids and stream tubes can be found on Figure 8 of the BRSA 4, 5, 6 & 9 TM.
BRSA 9
- Continue construction of staging area & stabilization pad;
- Mobilize WWTP, office trailer, supplies and equipment; and
- Began construction of coffer dam system.
OVERALL SITE
- Transport/disposal of approximately 3,285 tons of excavated soils to an EPA-approved landfill facility (see Section 2.1.4).
-
Daily particulate monitoring (PM10) around the site perimeter with no sustained exceedance off site of particulates above the action level of 1.5 mg/m3;
- Turbidity control measures and monitoring in Kalamazoo River around the BRSA 3 - 9 excavation area (1 upstream monitor and 2 downstream monitors), with no sustained exceedance of the action level of 50 NTUs above upstream levels;
- Treatment of approximately 116,419 gallons of contact water from contaminated grids and contaminated soils staging pads in on-site WWTPs located in BRSAs 4 & 6 (see Section 2.1.4). Sampling results from the WWTPs continues to confirm non-detect levels for total PCBs in treated water; and
- Monitoring of the temporary WCS.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
See PolRep #1
2.1.4 Progress Metrics
Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.
Waste Stream |
Medium |
Quantity |
Total |
Manifest # |
Treatment |
Disposal |
Cardboard |
solid |
50 lbs |
950 lbs |
NA |
recycling |
Otsego Recycling Center
|
Plastic |
solid |
20 lbs |
365 lbs |
NA |
recycling |
Otsego Recycling Center |
Steel |
solid |
1620 lbs |
10,910 lbs |
various |
recycling |
Broken Arrow Recycling |
Contaminated soil (< 50 ppm* PCBs) |
solid |
3285 tons (est) |
19,842 tons (est) |
various |
disposal |
Republic Ottawa County Farms Landfill, Coopersville, MI |
Contaminated soil
(> 50 ppm* PCBs) |
solid |
0 tons |
103.91 tons |
various |
disposal |
US Ecology Michigan,
Belleville, MI |
Contact water |
liquid |
116,419 gal |
1,024,697 gal |
NA |
on-site WWTP |
On-site reuse/discharge to Kalamazoo River |
*Note: 1 ppm = 1 mg/kg
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:
BRSA 4
- Complete restoration of all excavated riverbank & in-stream sediment removal areas;
- Remove staging area and stabilization pad; and
- Complete transport contaminated soils & sediments for disposal.
BRSA 6
- Continue excavation of contaminated riverbank soils & in-stream sediments;
- Complete installation of sand bag coffer dam systems;
- Treat contact water from contaminated grids & contaminated soils staging pad; and
- Transport contaminated soils & sediments for disposal.
BRSA 9
- Complete construction of staging area and stabilization pad;
- Begin drawdown of Pine Creek impoundment; and
- Establish access and construct coffer dam system to facilitate removal of stream tube(s) at Pine Creek confluence.
SITEWIDE
- Operate
dust and turbidity control/monitoring systems; and
- Maintain/monitor temporary WCS.
2.2.1.1 Planned Response Activities
See Sections 2.2.1 & 2.2.1.2
2.2.1.2 Administrative Activities / Next Steps
- A request by AMEC-FW to extend the project completion date from March 31, 2018 to August 31, 2018 was submitted on August 18 and approved by US EPA;
- AMEC-FW continues to hold meetings to resolve outstanding issues and concerns on the draft TM for BRSAs 7 & 8.
- Section 3 of the BRSA 7 & 8 TM was approved to facilitate commencement of a plan to dredge a 'pilot channel' in front of the temporary WCS;
- A meeting was held with the Allegan County Drain Commission on August 21 to discuss plans to draw down Pine Creek to facilitate removal of contaminated in-stream sediments at the confluence of Pine Creek and the Kalamazoo River.
2.2.2 Issues
None
|
|
2.3 Logistics Section
|
|
|
See PolRep #1
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
2.5.1 Safety Officer
A safety meeting is held prior to work start each day. The meeting is led by on-site safety officer(s) from Envirocon & AMEC-FW.
2.5.2 Liaison Officer
- Letters were delivered door to door to all residents in the Pine Creek Drainage District on August 23 providing notice and information related to a planned drawdown of water levels in Pine Creek to support removal operations in BRSA 9 at the confluence of Pine Creek and the Kalamazoo River.
- A picnic for the crew was hosted by a local resident in appreciation of the cleanup work conducted this summer (see photo).
- Access to the command center area was provided to contractors to Michigan Gas Utilities to support installation of a natural gas pipeline through the site.
2.5.3 Information Officer
- A public availability session was held on August 31 for residents living in the Pine Creek Drainage District to provide details and answer questions about a plan to draw down the water level in Pine Creek during the month of September.
|
3. Participating Entities
|
|
3.1 Unified Command
3.2 Cooperating Agencies
See PolRep #1
|
4. Personnel On Site
|
|
On average, the following personnel were present on site during the reporting period:
US EPA - 1
START - 1
Michigan DNR - 1
Michigan DEQ - 1
Envirocon: 35
Milbocker & Sons, Inc.: 3
AMEC-FW: 2
Spicer Group: 1
TOTAL: 45
|
5. Definition of Terms
|
|
AMEC-FW AMEC Foster Wheeler
BRSA Bank Removal and Stabilization Area
FSP Field Sampling Plan
mg/kg milligrams per kilogram
MDEQ Michigan Department of Environmental Quality
MDNR Michigan Department of Natural Resources
OSC On Scene Coordinator
PCBs Poly-chlorinated biphenyls
PolRep Pollution Report
ppm parts per million
PRP Potentially Responsible Party
START Superfund Technical Assessment & Response Team (US EPA contractor)
TM Technical Memorandum
US EPA United States Environmental Protection Agency
WCS Water Control Structure
WWTP Waste Water Treatment Plant
|
6. Additional sources of information
|
|
6.1 Internet location of additional information/report
http://www.epaosc.org/otsegodam
www.epa.gov/superfund/allied-paper-kalamazoo
6.2 Reporting Schedule
The next PolRep will be generated on September 15.
|
7. Situational Reference Materials
|
|
No information available at this time.
|
|
|