U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #23
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #23
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 9/1/2017
Reporting Period: 8/19/2017 - 9/1/2017

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
Excavation of contaminated riverbank soils and in-stream sediments is complete in BRSA 4. Removal operations continue in BRSA 6. The staging area is nearly completed in BRSA 9.

2.1.2 Response Actions During Reporting Period

BRSA 4
- Excavation of contaminated soils and sediments was completed, with confirmation results received, in both riverbank grids 44-46 and the adjacent stream tube grids (see Tables 1 & 2);
- Completed transportation and disposal of contaminated soils and sediments for disposal;
- Demobilization of the WWTP, office trailer, equipment and supplies; and
- Backfilling, grading, stabilization and restoration of river banks continues.

BRSA 6
- Excavation of contaminated soils continues with excavation completed and confirmation results received in riverbank grids 6-8. There are 54 total grids in BRSA 6, with each grid consisting of approximately 50 lineal feet of riverbank. There are 4 stream tubes, with each stream tube varying in size. The target clean-up goal in the riverbank soils is 5 mg/kg total PCBs and in-stream sediments is 1mg/kg total PCBs; and
- Completed construction of sheet pile coffer dam systems to facilitate removal of riverbank soils and in-stream sediments.

Estimated excavation depths and confirmation sampling results are found below for riverbank grids in BRSA 4 (Table 1) and adjacent stream tube grids (Table 2) along with results from BRSA 6 (Table 3) and adjacent stream tube grids (Table 4).

BRSA 4

RIVERBANK

GRID

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

44

48

0.065

45

36

0.39

46

36

0.36

Table 1. BRSA 4 Riverbank Grid Confirmatory Sampling Results


BRSA 4

STREAM TUBE GRID*

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

19D-44

6

0.19

19D-45

6

0.074

19D-46

6

0.13

Table 2. BRSA 4 Stream Tube Confirmatory Sampling Results


BRSA 6

RIVERBANK GRID

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

6

12

0.46

7

12

<0.032

8

12

1.00

Table 3. BRSA 6 Riverbank Grid Confirmatory Sampling Results


BRSA 6

STREAM TUBE

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

17D-6

24

<0.039

17D-7

24

0.048

17D-8

24

0.18

Table 4. BRSA 6 Stream Tube Confirmatory Sampling Results

 

Table Notes: Confirmatory sampling takes place immediately following excavation of contaminated soils and/or sediments in accordance with procedures outlined in the FSP and the TM for BRSAs 4, 5, 6 & 9. Both documents can be found in the ‘Documents' Section of the project website. Stream Tube grids are numbered consistent with the riverbank grid they are located adjacent to. A figure showing the location of both (preliminary) riverbank grids and stream tubes can be found on Figure 8 of the BRSA 4, 5, 6 & 9 TM.

BRSA 9
- Continue construction of staging area & stabilization pad;
- Mobilize WWTP, office trailer, supplies and equipment; and
- Began construction of coffer dam system.

OVERALL SITE
- Transport/disposal of approximately 3,285 tons of excavated soils to an EPA-approved landfill facility (see Section 2.1.4).
- Daily particulate monitoring (PM10) around the site perimeter with no sustained exceedance off site of particulates above the action level of 1.5 mg/m3;
- Turbidity control measures and monitoring in Kalamazoo River around the BRSA 3 - 9 excavation area (1 upstream monitor and 2 downstream monitors), with no sustained exceedance of the action level of 50 NTUs above upstream levels;
- Treatment of approximately 116,419 gallons of contact water from contaminated grids and contaminated soils staging pads in on-site WWTPs located in BRSAs 4 & 6 (see Section 2.1.4). Sampling results from the WWTPs continues to confirm non-detect levels for total PCBs in treated water; and
- Monitoring of the temporary WCS.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.

Waste Stream Medium Quantity Total               Manifest #  Treatment Disposal
 Cardboard solid 50 lbs 950 lbs NA recycling Otsego Recycling Center
 Plastic solid 20 lbs 365 lbs NA recycling Otsego Recycling Center
 Steel solid 1620 lbs 10,910 lbs various  recycling Broken Arrow Recycling
 Contaminated soil (< 50 ppm* PCBs) solid 3285 tons (est) 19,842 tons (est) various disposal Republic Ottawa County Farms Landfill, Coopersville, MI
 Contaminated soil
(> 50 ppm* PCBs)
solid 0 tons 103.91 tons     various disposal US Ecology Michigan,
Belleville, MI
 Contact water liquid 116,419 gal           1,024,697 gal  NA on-site WWTP On-site reuse/discharge to Kalamazoo River
*Note: 1 ppm = 1 mg/kg

  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

BRSA 4
- Complete restoration of all excavated riverbank & in-stream sediment removal areas;
- Remove staging area and stabilization pad; and
- Complete transport contaminated soils & sediments for disposal.

BRSA 6
- Continue excavation of contaminated riverbank soils & in-stream sediments;
- Complete installation of sand bag coffer dam systems;
- Treat contact water from contaminated grids & contaminated soils staging pad; and
- Transport contaminated soils & sediments for disposal.

BRSA 9
- Complete construction of staging area and stabilization pad;
- Begin drawdown of Pine Creek impoundment; and
- Establish access and construct coffer dam system to facilitate removal of stream tube(s) at Pine Creek confluence.

SITEWIDE
- Operate dust and turbidity control/monitoring systems; and
- Maintain/monitor temporary WCS.

2.2.1.1 Planned Response Activities

See Sections 2.2.1 & 2.2.1.2

2.2.1.2 Administrative Activities / Next Steps
- A request by AMEC-FW to extend the project completion date from March 31, 2018 to August 31, 2018 was submitted on August 18 and approved by US EPA;
- AMEC-FW continues to hold meetings to resolve outstanding issues and concerns on the draft TM for BRSAs 7 & 8.
- Section 3 of the BRSA 7 & 8 TM was approved to facilitate commencement of a plan to dredge a 'pilot channel' in front of the temporary WCS;
- A meeting was held with the Allegan County Drain Commission on August 21 to discuss plans to draw down Pine Creek to facilitate removal of contaminated in-stream sediments at the confluence of Pine Creek and the Kalamazoo River.

2.2.2 Issues
None

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

A safety meeting is held prior to work start each day. The meeting is led by on-site safety officer(s) from Envirocon & AMEC-FW.

2.5.2 Liaison Officer
- Letters were delivered door to door to all residents in the Pine Creek Drainage District on August 23 providing notice and information related to a planned drawdown of water levels in Pine Creek to support removal operations in BRSA 9 at the confluence of Pine Creek and the Kalamazoo River.
- A picnic for the crew was hosted by a local resident in appreciation of the cleanup work conducted this summer (see photo).
- Access to the command center area was provided to contractors to Michigan Gas Utilities to support installation of a natural gas pipeline through the site.

2.5.3 Information Officer
- A public availability session was held on August 31 for residents living in the Pine Creek Drainage District to provide details and answer questions about a plan to draw down the water level in Pine Creek during the month of September.

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

US EPA - 1
START - 1
Michigan DNR - 1
Michigan DEQ - 1
Envirocon: 35
Milbocker & Sons, Inc.: 3
AMEC-FW: 2
Spicer Group: 1

TOTAL: 45

5. Definition of Terms
  AMEC-FW           AMEC Foster Wheeler
BRSA                  Bank Removal and Stabilization Area
FSP                     Field Sampling Plan    
mg/kg                  milligrams per kilogram
MDEQ                 Michigan Department of Environmental Quality
MDNR                 Michigan Department of Natural Resources
OSC                   On Scene Coordinator
PCBs                  Poly-chlorinated biphenyls
PolRep               Pollution Report
ppm                    parts per million
PRP                    Potentially Responsible Party
START               Superfund Technical Assessment & Response Team (US EPA contractor)
TM                      Technical Memorandum
US EPA              United States Environmental Protection Agency   
WCS                   Water Control Structure
WWTP                Waste Water Treatment Plant     

6. Additional sources of information
 

6.1 Internet location of additional information/report

http://www.epaosc.org/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
The next PolRep will be generated on September 15.

7. Situational Reference Materials
  No information available at this time.


Click here to view Attached Images