U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #27
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #27
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 10/27/2017
Reporting Period: 10/14/2017 - 10/27/2017

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
Restoration with native plantings continues in BRSAs 3 & 4. Removal operations are near completion in BRSAs 6 & 9.  Hydraulic dredging of a pilot channel to support removal and restoration operations continues in BRSAs 7 & 8, with heavy rain and high water levels (see photos) preventing progress.

2.1.2 Response Actions During Reporting Period
BRSAs 3 & 4
- Completed planting native trees and shrubs along river banks, with the exception of live willow stakes.

BRSA 6
- Excavation of contaminated soils continues in Grid 54, which requires additional excavation to meet the target clean-up goal. There are 54 total grids in BRSA 6, with each grid consisting of approximately 50 lineal feet of riverbank. There were 4 stream tubes, with each stream tube varying in size. The target clean-up goal in the riverbank soils is 5 mg/kg total PCBs and in-stream sediments is 1mg/kg total PCBs;
- Restoration of riverbanks along excavated grids; and
- Continued transportation and disposal of contaminated soils and sediments.

BRSAs 7 & 8
- Hydraulic dredging continues to construct a 'pilot channel' in front of the temporary WCS;
- Removed or added stop logs at temporary WCS, with concurrence from MDEQ & MDNR, to lower or raise water levels, allowing better access for construction;
- Clearing of trees along access roads;
- Construction of access roads along riverbanks; and
- Maintenance and monitoring of turbidity curtain downstream of temporary WCS and old auxiliary spillway to control downstream turbidity (cloudiness in water caused by sand/dirt/clay particles) which may result from hydraulic dredging operations.

BRSA 9

- Excavation continues in remaining grids though progress was impeded by elevated water levels. (see photos). There are 38 total river bank grids in BRSA 9, with each grid consisting of approximately 50 lineal feet of riverbank; and
- Continued transportation and disposal of contaminated soils and sediments.

OVERALL SITE
- Transport/disposal of approximately 1131 tons of excavated soils to an EPA-approved landfill facility (see Section 2.1.4).
- Daily particulate monitoring (PM10) around the site perimeter with no sustained exceedance off site of particulates above the action level of 1.5 mg/m3;
- Turbidity control measures and monitoring in the Kalamazoo River downstream of project area (1 upstream monitor and 2 downstream monitors), with no sustained exceedance of the action level of 50 NTUs; 
- Treatment of approximately 137,890 gallons of contact water from contaminated grids and contaminated soils staging pads in on-site WWTPs located in BRSAs 6 & 9 (see Section 2.1.4). Sampling results from the WWTP in BRSA 6 indicated an exceedance in the permissible discharge limit for PCBs (ND) of 0.29 ppm. The system was shut down for maintenance and change out of activated carbon vessel(s). Discharged water was being collected in storage tanks at the time and was not discharged to the Kalamazoo River. Sampling results from the WWTP in BRSA 9 continued to show non-detect levels for PCBs in the treated discharge; and
- Monitoring of the temporary WCS. Stop logs continue to be added or removed depending on the operational and navigational needs of the hydraulic dredging rig constructing the pilot channel.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.

Waste Stream Medium Quantity Total               Manifest #  Treatment Disposal
 Cardboard solid 0 lbs 1060 lbs NA recycling Otsego Recycling Center
 Plastic solid 0 lbs 425 lbs NA recycling Otsego Recycling Center
 Steel solid 0 lbs 12,240 lbs various  recycling Broken Arrow Recycling
 Contaminated soil (< 50 ppm* PCBs) solid 1131 tons (est) 30,283 tons est) various disposal Republic Ottawa County Farms Landfill, Coopersville, MI
 Contaminated soil
(> 50 ppm* PCBs)
solid 0 tons 103.91 tons     various disposal US Ecology Michigan,
Belleville, MI
 Contact water liquid 137,890 gal           1,520,676 gal  NA on-site WWTP On-site reuse/discharge to Kalamazoo River
*Note: 1 ppm = 1 mg/kg

  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

BRSAs 3 & 4
- Re-plant native plantings impacted by elevated water levels.

BRSA 6
- Continue backfilling & restoration of excavated riverbank grids;
- Treat contact water from contaminated grids & contaminated soils staging pad;
- Perform maintenance, cleaning and activated carbon change out in WWTP;
- Begin removal of sheet pile coffer dams; and
- Complete transport contaminated soils & sediments for disposal.

BRSAs 7 & 8
- Continue hydraulic dredging of pilot channel;
- Continue tree-clearing as needed for access to river banks;
- Continue drawdown of water levels by adding or removing stop logs from temporary WCS;
- Continue monitoring & maintenance of dredging spoils fill area; and
- Continue access road construction along river banks.

BRSA 9
- Continue backfilling & restoration of excavated riverbank grids;
- Complete excavation of contaminated soils & sediments;
- Treat contact water from contaminated grids & contaminated soils staging pad; and
- Transport contaminated soils & sediments for disposal.

SITEWIDE
- Operate dust and turbidity control/monitoring systems; and
- Maintain/monitor temporary WCS.

2.2.1.1 Planned Response Activities

See Sections 2.2.1 & 2.2.1.2

2.2.1.2 Administrative Activities / Next Steps
- US EPA will discuss proposed plans to remove of the temporary WCS and restore the area with the PRPs and agencies on November 7.
- Wood Group submitted final draft TM for BRSAs 7 & 8 to US EPA for final review on October 27.

2.2.2 Issues

Excessive rainfall events resulted in high water levels which inundated all work areas (see photos), slowing or completely stopping work progress for several days during the operational period. Repairs and maintenance will need to be performed along river banks prior to re-starting work.

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

A safety meeting is held prior to work start each day by on-site safety officer(s) from Envirocon & Wood Group.

2.5.2 Liaison Officer

2.5.3 Information Officer

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

US EPA - 0
START - 1
MDNR - 1
MDEQ - 1
Envirocon - 44
White Lake Dock & Dredge, Inc. - 3
Milbocker & Sons Construction, Inc. - 0
SWAT - 2
Toads Tree Service - 2
Wood Group - 3
Spicer Group - 1

TOTAL: 58

5. Definition of Terms
  BRSA                  Bank Removal and Stabilization Area
FSP                     Field Sampling Plan    
mg/kg                  milligrams per kilogram
MDEQ                 Michigan Department of Environmental Quality
MDNR                 Michigan Department of Natural Resources
ND                      Non-Detect
OSC                   On Scene Coordinator
PCBs                  Poly-chlorinated biphenyls
PolRep               Pollution Report
ppm                    parts per million
PRP                    Potentially Responsible Party
START               Superfund Technical Assessment & Response Team (US EPA contractor)
TM                      Technical Memorandum
US EPA              United States Environmental Protection Agency   
WCS                   Water Control Structure
WWTP                Waste Water Treatment Plant     

6. Additional sources of information
 

6.1 Internet location of additional information/report

http://www.epaosc.org/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
The next PolRep will be generated on November 10.

7. Situational Reference Materials
  No information available at this time.


Click here to view Attached Images