U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #30
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #30
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 12/8/2017
Reporting Period: 11/25/2017 - 12/8/2017

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: DEQ
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
Removal operations continue along with riverbank restoration in BRSA 9. Construction of access roads in BRSA 8 was completed. Removal operations are underway in BRSA 7. Winterization of WWTPs in BRSA 6 & 9, which will treat contact water from BRSAs 7 & 8, respectively, is complete (see photos).

2.1.2 Response Actions During Reporting Period

BRSA 6
- Restoration continues along riverbanks;
- Winterization of WWTP (see photo); and
- Removal of sheet piling containment areas.

BRSA 7
- Excavation of contaminated soils and sediments is underway with confirmation results received in riverbank grids and stream tube grids shown in the tables below. There are 63 total river bank grids in BRSA 7, with each grid consisting of approximately 50 feet of riverbank. There are 3 stream tubes, with each varying in size. The target clean-up goal in riverbank soils is 5 mg/kg total PCBs and in-stream sediments is 1mg/kg total PCBs;
- Commenced transportation and disposal of contaminated soils and sediments (utilizing the staging pad in BRSA 6);
- Continued maintenance of stream tube protection measures to prevent erosion; and
- Field sampling was conducted within several grids (19-26 and 52-63) to confirm the need for remediation excavation in areas with high banks and coarse sediments.

Estimated excavation depths and confirmation sampling results are found below for riverbank grids and stream tubes in BRSA 7 (Tables 1 & 2).

BRSA 7

RIVERBANK GRID

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

1*

36*

1.1*

2

48

1.3

3

48

0.35

4

48

< 0.071

5

48

< 0.067

Table 1. BRSA 7 Riverbank Grid Confirmatory Sampling Results

*Note: Result shown is for Grid #54 of BRSA 6, which was extended to encompass Grid #1 of BRSA 7 for logistical purposes.

BRSA 7

STREAM TUBE

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

11E-1*

18*

< 0.075*

Table 2. BRSA 7 Stream Tube Confirmatory Sampling Results

 *Note: Result shown is for stream tube #11E, grid #54 of BRSA 6, which was extended to encompass stream tube #11E, grid #1 of BRSA 7 for logistical purposes.

General Table Notes: Confirmatory sampling takes place immediately following excavation of contaminated soils and/or sediments in accordance with procedures outlined in the FSP and the TM for BRSAs 7 & 8. Both documents can be found in the ‘Documents' Section of the project website. Stream tube grids are numbered consistent with the riverbank grid they are located adjacent to. A figure showing the location of both (preliminary) riverbank grids and stream tubes can be found on Figure 1-7 of the BRSA 7 & 8 TM.

BRSA 8

- Completed construction of access roads along riverbanks; and
- Continued maintenance of stream tube protection measures to prevent erosion.

BRSA 9
- Excavation of contaminated soils continues with confirmation results received in riverbank grids and stream tube grids shown in the tables below. There are 38 total river bank grids in BRSA 9, with each grid consisting of approximately 50 lineal feet of riverbank. There are 3 stream tubes, with each stream tube varying in size. The target clean-up goal in the riverbank soils is 5 mg/kg total PCBs and in-stream sediments is 1mg/kg total PCBs;
- Winterization of WWTP (see photo); and
- Continued transportation and disposal of contaminated soils & sediments.

Estimated excavation depths and confirmation sampling results are found below for riverbank grids and stream tubes in BRSA 9 (Tables 3 & 4).

BRSA 9

RIVERBANK GRID

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

31

12

TBD

32

12

TBD

33

12

1.1

Table 3. BRSA 9 Riverbank Grid Confirmatory Sampling Results


BRSA 9

STREAM TUBE

TOTAL ESTIMATED EXCAVATION DEPTH (in)

FINAL
CONFIRMATION TOTAL PCBs RESULT (mg/kg)

12A-31

TBD

TBD

12A-32

TBD

TBD

11A-33

12

0.94

Table 4. BRSA 9 Stream Tube Confirmatory Sampling Results


Table Notes: Confirmatory sampling takes place immediately following excavation of contaminated soils and/or sediments in accordance with procedures outlined in the FSP and the TM for BRSAs 4, 5, 6 & 9. Both documents can be found in the ‘Documents' Section of the project website. Stream Tube grids are numbered consistent with the riverbank grid they are located adjacent to. A figure showing the location of both (preliminary) riverbank grids and stream tubes can be found on Figure 3-3 of the BRSA 4, 5, 6 & 9 TM.

OVERALL SITE
- Transport/disposal of approximately 1,578 tons of excavated soils to an EPA-approved landfill facility (see Section 2.1.4).
- Daily particulate monitoring (PM10) around the site perimeter with no sustained exceedance off site of particulates above the action level of 1.5 mg/m3. New locations were secured for upwind and downwind monitors as removal work gets underway in BRSAs 7 & 8;
- Turbidity control measures and monitoring in the Kalamazoo River downstream of project area (1 upstream monitor and 2 downstream monitors), with no sustained exceedance of the action level of 50 NTUs; 
- Treatment of approximately 15,000 gallons of contact water from contaminated grids and contaminated soils staging pads in on-site WWTPs located in BRSAs 6 & 9 (see Section 2.1.4). The WWTP in BRSA 6 is now treating contact water from BRSA 7 removal operations. The WWTP in BRSA 9 will treat contact waster from BRSA 8 removal operations. Both WWTPs have been winterized (see photos). Sampling results from the WWTPs in BRSAs 6 & 9 continue to show non-detect levels for PCBs in the treated discharge; and
- Monitoring of the temporary WCS. All stop logs remain removed from the structure.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

 

See PolRep #1

2.1.4 Progress Metrics

Both quantities during the reporting period ('Quantity' column) and totals to date ('Total' column) are included in the table.

Waste Stream Medium Quantity Total               Manifest #  Treatment Disposal
 Cardboard solid 50 lbs 1150 lbs NA recycling Otsego Recycling Center
 Plastic solid 20 lbs 505 lbs NA recycling Otsego Recycling Center
 Steel solid 3,880 lbs 25,600 lbs various  recycling Broken Arrow Recycling
 Contaminated soil (< 50 ppm* PCBs) solid 1,578 tons (est) 32,330 tons(est) various disposal Republic Ottawa County Farms Landfill, Coopersville, MI
 Contaminated soil
(> 50 ppm* PCBs)
solid 0 tons 103.91 tons     various disposal US Ecology Michigan,
Belleville, MI
 Contact water liquid 15,000 gal           1,696,016 gal  NA on-site WWTP On-site reuse/discharge to Kalamazoo River
*Note: 1 ppm = 1 mg/kg

  2.2 Planning Section
   

2.2.1 Anticipated Activities
During the next reporting period, the following activities are expected to occur:

BRSA 6
- Continue restoration of excavated riverbank grids; and
- Continue staging pad and WWTP operations to support removal operations in BRSA 7.

BRSA 7
- Continue access road construction along riverbanks;
- Continue excavation of contaminated riverbank soils and in-stream sediments;
- Treat contact water from contaminated grids, stream tubes and staging pad (located in BRSA 6); and
- Transport contaminated soils & sediments for disposal.

BRSA 8
- Begin excavation of contaminated riverbank soils and in-stream sediments;
- Treat contact water from contaminated grids, stream tubes and staging pad (located in BRSA 9); and
- Transport contaminated soils & sediments for disposal.

BRSA 9
- Complete excavation of remaining riverbank grids and stream tubes;
- Complete backfilling & restoration of excavated riverbank grids;
- Treat contact water from contaminated grids & contaminated soils staging pad; 
- Continue staging pad and WWTP operations to support removal operations in BRSA 8; and
- Transport contaminated soils & sediments for disposal.

SITEWIDE
- Operate dust and turbidity control/monitoring systems; and
- Maintain/monitor temporary WCS.

2.2.1.1 Planned Response Activities

See Sections 2.2.1 & 2.2.1.2

2.2.1.2 Administrative Activities / Next Steps
- Planning discussions continue with respect to removal of the temporary WCS and restoration of the area.

2.2.2 Issues
- Cold weather and high winds causes minor delays in work progress during the reporting period.

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer

A safety meeting is held prior to work start each day by on-site safety officer(s) from Envirocon & AMEC-FW.

2.5.2 Liaison Officer

2.5.3 Information Officer

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

On average, the following personnel were present on site during the reporting period: 

US EPA - 1
START - 1
MDNR - 1
MDEQ - 1
Envirocon - 44
Milbocker & Sons, Inc. - 3
AMEC-FW - 3
Spicer Group - 1

TOTAL: 55

5. Definition of Terms
  AMEC-FW          AMEC Foster Wheeler     
BRSA                  Bank Removal and Stabilization Area
FSP                     Field Sampling Plan    
mg/kg                  milligrams per kilogram
MDEQ                 Michigan Department of Environmental Quality
MDNR                 Michigan Department of Natural Resources
ND                      Non-Detect
OSC                   On Scene Coordinator
PCBs                  Poly-chlorinated biphenyls
PolRep               Pollution Report
ppm                    parts per million
PRP                    Potentially Responsible Party
START               Superfund Technical Assessment & Response Team (US EPA contractor)
TM                      Technical Memorandum
UAO                    Unilateral Administrative Order
US EPA              United States Environmental Protection Agency   
WCS                   Water Control Structure
WWTP                Waste Water Treatment Plant     

6. Additional sources of information
 

6.1 Internet location of additional information/report

http://www.epaosc.org/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
The next PolRep will be generated on December 22.

7. Situational Reference Materials
  No information available at this time.


Click here to view Attached Images