U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Otsego Township Dam Area

All POL/SITREP's for this site Otsego Township Dam Area
Otsego Township, MI - EPA Region V
POLREP #49
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Otsego Township Dam Area - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #49
Progress
Otsego Township Dam Area
059B
Otsego Township, MI
Latitude: 42.4601694 Longitude: -85.7199333


To: Douglas Ballotti, EPA
Samuel Borries, EPA
Mike Ribordy, EPA
Jim Saric, EPA
Mark Mills, MDNR
Polly Synk, MDAG
Cyndi Trobeck, City of Otsego
Valincia Darby, U.S. DOI

From: Paul Ruesch, OSC
Date: 7/31/2019
Reporting Period: 8/18/2018 - 7/31/2019

1. Introduction
  1.1 Background
   
Site Number: 059B    Contract Number:  
D.O. Number:      Action Memo Date: 4/6/2016
Response Authority: CERCLA    Response Type: PRP Oversight
Response Lead: PRP    Incident Category: Removal Action
NPL Status: NPL    Operable Unit: 5
Mobilization Date: 8/1/2016    Start Date: 8/1/2016
Demob Date:      Completion Date:  
CERCLIS ID: MID006007306    RCRIS ID:
ERNS No.:    State Notification: EGLE
FPN#:    Reimbursable Account #: 059B

1.1.1 Incident Category     
Time Critical Removal Action - PRP Oversight

1.1.2 Site Description
See PolRep #1

1.1.2.1 Location
See PolRep #1

1.1.2.2 Description of Threat

See PolRep #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See PolRep #1

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative
The final reports (START and PRP) for the project were submitted, reviewed and approved by US EPA. Monitoring and maintenance activities have been conducted quarterly since completion of removal activities and minor repairs were completed.

2.1.2 Response Actions During Reporting Period

- Continued operation & maintenance of surface water run-off and erosion control measures;
- Conducted monitoring & maintenance surveys quarterly (December 2018, February 2019 & May 2019) with checklists and photo logs completed for by START and Wood Group after each inspection;
- Continued treatment for invasive plants in all restored areas;
- Continued operation of the irrigation system (removed in Spring 2019) in BRSAs as needed; and
- Completed repairs identified in the post-construction checklists in each BRSA.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

See PolRep #1

2.1.4 Progress Metrics

  2.2 Planning Section
   

2.2.1 Anticipated Activities
- A final monitoring & maintenance survey will be conducted in August 2019. A final report will be prepared and submitted by Wood Group on the post-construction monitoring & maintenance phase of the project. This report will be reviewed by US EPA.

2.2.1.1 Planned Response Activities

See Section 2.2.1

2.2.1.2 Administrative Activities / Next Steps

The final letter report summarizing air monitoring, split sampling and other activities was received from START on May 24, 2019. The final construction report from Wood Group on behalf of the PRPs was received by US EPA on July 29, 2019 and approved on July 31, 2019. Both documents and posted and available for download on the 'Documents' section of the project website (see Section 6.1).

2.2.2 Issues
The access gates and roadways along the riverbanks in BRSAs 1,3,4,6,8 & 9 are still in place and will remain until the implementation of the remedial phase of the project in adjacent floodplains.

  2.3 Logistics Section
    See PolRep #1

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
   

2.5.1 Safety Officer
Site safety protocols are still in place within work areas. A safety officer is designated for any work crews working within BRSAs.

2.5.2 Liaison Officer
Tours with agency executives/personnel, elected officials, universities, residents, and non-profit organizations continue.

2.5.3 Information Officer
- A final community meeting (presentation available in the 'Documents' section of the website) was held on September 13, 2018;
- An updated Fact Sheet (available in the 'Documents' section of the website) was finalized and distributed in September 2018;
- MDNR lifted the closure order, and held a 'ribbon cutting' ceremony on August 30 to announce the river was open for recreation. The ceremony was attended by politicians, agency executives, contractors and local residents.

3. Participating Entities
 

3.1 Unified Command

3.2 Cooperating Agencies

See PolRep #1

4. Personnel On Site
 

Personnel from USEPA, MDNR, MDEGLE, Envirocon, Wood, Cardo and other subcontractors were present on site off and on during the reporting period.

5. Definition of Terms
  BRSA                 Bank Removal and Stabilization Area
MDEGLE           Michigan Department of Environment, Great Lakes and Energy
MDNR                Michigan Department of Natural Resources 
OSC                   On Scene Coordinator
PolRep               Pollution Report
PRP                    Potentially Responsible Party
START                Superfund Technical Assessment & Response Team (US EPA contractor)
US EPA              United States Environmental Protection Agency

6. Additional sources of information
 

6.1 Internet location of additional information/report

https://response.epa.gov/otsegodam

www.epa.gov/superfund/allied-paper-kalamazoo

6.2 Reporting Schedule
A final PolRep will be issued once the final report on the monitoring & maintenance phase of the project is submitted and approved. This is expected to be later this summer.

7. Situational Reference Materials
  No information available at this time.


Click here to view Attached Images