|
|
Site Number: |
01HA |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
8/8/2013 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
6/23/2015 |
|
Start Date: |
4/13/2015 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
NHN000105965 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time-Critical
Removal Action
1.1.2 Site Description
1.1.2.1 Location
The Former Synergy Site is adjacent to the north and eastern bank of the Sugar River near the center of the City of Claremont on the western side of the intersection of North Street and State Route 11. The approximate latitude and longitude is N 43º22’28” and W 72º20’15”, respectively.
Please refer to SITREP/POLREP 1 for additional details.
1.1.2.2 Description of Threat
This
site is the location of a defunct manufactured gas plant (MGP) which was
heavily impacted by an oily waste product (coal tar).
Visual
observation, field instrumentation, and laboratory data indicate that
approximately two-thirds of the site was impacted by coal tar. Constituents of the product include
semi-volatile organic compounds (carcinogenic and non-carcinogenic polynuclear aromatic
hydrocarbons [PAHs]) and to a lesser degree, volatile organics and inorganics.
Please refer to SITREP/POLREP 1 for
additional details.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
Please refer to SITREP/POLREP 1 for additional
details.
|
|
|
2.1.1 Narrative
Due
to a long history of bankruptcies, acquisitions, and mergers, AmeriGas Propane,
L.P. (AmeriGas) is the respondent for the site.
Over the past few years, numerous discussions between EPA, AmeriGas, the
City of Claremont, and the New Hampshire Department of Environmental Services
(NHDES) have led to a cost sharing approach via an Administrative Order on
Consent (AOC). A contractor for AmeriGas
has concluded the majority of the field work which has been overseen by a
consultant (GEI) for AmeriGas, and On-Scene Coordinator Gary Lipson for the EPA. The property in question will be deeded to
the City of Claremont to be used at their discretion. The cost share involves EPA spending up to a
bottom-line expenditure with AmeriGas responsible for any costs incurred above
that amount.
Removal
activities included demolition of the above ground structures, in-situ
stabilization of some deeper contaminated soil/sediment, removal of coal-tar
saturated soil down to bedrock, removal of contaminated near-shore sediments
along the Sugar River, temporary rerouting of a subsurface sewer pipe and
replacement of a section of that pipe, and backfilling/landscaping of the
property.
Please
refer to SITREP/POLREP 1 for additional details.
2.1.2 Response Actions to Date
Please refer to SITREPs/POLREPs 1 & 2 for
additional details.
August 14 – August 21, 2015:
-
GEI and Enviro-Air Technologies, Inc. (EAT), the field contractor for
AmeriGas, broke through the concrete pad which supported Gas Holder No. 2, the
second of three on-site gas holders.
Free product was observed beneath the pad, so demolition and removal of the pad began along
with removal of the visible coal tar waste;
-
The replacement sewer line was completed and the sewer bypass was shut
down;
-
Contaminated soil
continued to be excavated and transported off-site for disposal. Approximately
6,000 tons of soil have been disposed of to date;
-
Clean back-fill has been
brought to the site and spreading and rough grading began.
August 24 – August 28, 2015:
-
Excavation from all designated excavation areas has been completed with
the exception of the base of Gas Holder No. 3.
Approximately 8,000 tons of soil have been disposed of to date;
-
Backfilling has been ongoing. Approximately
5,500 tons of backfill have been installed and compacted;
-
A
meeting with state and local officials was held to discuss possible options to
memorialize the history of the site and the city. Historical documentation of the site is
required by the Historical Preservation Act and memorialized via a Memorandum
of Understanding previously created between EPA and the State Historical
Preservation Office (SHPO).
August 30 – September 4, 2015:
-
Excavation has been completed. Approximately 9,000 tons of soil have been
shipped offsite for disposal;
-
Backfilling has continued. Approximately 7,800 tons have been installed
and compacted;
-
Three test trenches were cut into the concrete pad for Gas Holder
No.3. No free or residual product was
observed, so after consultation with NH DES and EPA, the remaining pad was left
in place and covered with clean fill. dual product was observed, so after
consultation with NH DES and EPA, the remaining pad was left in place and
covered with clean fill.
-
By mid-September, backfilling had been completed and the topsoil was
graded to match the final design plans;
-
Grass seed and straw were installed along with the beginnings of
plantings for eventual riverbank restoration;
-
A chain link fence was installed around most of the restored area to
allow for growth of the fresh plantings;
-
The crew demobilized by the end of September although additional
plantings were placed in November.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Please refer to SITREP/POLREP 1 for additional
details.
|
|
|
2.2.1 Anticipated Activities
The cleanup contractor will return in the
spring to complete restoration activities. This includes additional plantings
for both shoreline and wetland applications.
Since
the site is part of the Claremont Historic District and qualifies under the
federal Historic Preservation Act, EPA has been working with the SHPO to
document the historic nature of the site. This included full documentation of
the site structures prior to their demolition, a report on the site history,
and its history in context to the City of Claremont. EPA has been working with the SHPO, the city,
and EPA’s contractors to design
and eventually construct a lasting monument at the site that will depict the
contribution that the original MGP made to the city and its well documented
textile history. The monument is expected to be completed by the
end of April, 2016.
|