2.1.1 Narrative
During this reporting period (September 28-October 3, 2015), the following tasks have
been completed:
4765 H Mitchell Rd
- A total of 406 cy of topsoil
was backfilled, leveled, and compacted in DU 201G.
- A fence was re-installed
around DU 201G to keep animals out of the garden.
4765 A Mitchell Rd
- Excavation from 0-6" lift was completed and in
situ screening with the XRF was conducted at DU 39.
- Performed confirmation
soil sampling at 16 locations at 6” bgs at DU 39.
- A total of 105 cy of excavated
material was transported to Stevens County Landfill.
- A total of 756 cy of topsoil
was delivered to the site to be used as backfill.
- Geotextile was placed around trees in DUs
35 and 35PA.
· Unknown Property Address, End of Mitchell Road
- A total of 20 cy of topsoil
was backfilled around the trees in DU 49.
- A total of 40 cy pit run backfilled
into DU 49.
4765 C Mitchell Road
- Geotextile fabric was
placed around trees in all DUs (203, DEA-A, DEA-B, DEA-C).
- Backfill material was changed
to only topsoil instead of gravel below topsoil in all property DUs due to
material availability.
- All DUs were backfilled
with imported topsoil.
4765 K Mitchell Rd
- Completed final pre-excavation
site walk with homeowner to finalize DU boundaries, review scope of work, and
locate potential areas of sensitivity.
- Completed 0-6” lift at DU
HIC-A.
4765 Q Mitchell Road
- DUs HUB and 194 were
backfilled with topsoil. A total of 155 cy was placed at DU HUB and 170 cy at
DU 194.
- A total of 6,000 ft2 of sod was installed
after topsoil backfill was completed in DU HUB. A Sod Maintenance Plan was delivered
to the homeowner.
- DU 194 will be hydroseeded with a native grass mixture
at a later date.
4361 K Highway 25 North
- A total of 180 cy of gravel
and 111 cy of pit run was delivered to DU 319M for backfill; the gravel will be
placed on top of the pit run.
4291 Highway 25 North
- The
excavation from 0-6” bgs was completed at DU 40, and the area was screened
in-situ with the XRF. Confirmation soil sampling was performed at 20 locations.
- A total of 240 cy of soil was transported to the
Stevens County Landfill.
- The car port was
supported with concrete blocks to allow hand excavation beneath the structure
to a total depth of 6” bgs. The concrete blocks will be left in place to
provide support.
4765 F Mitchell Rd
- Confirmation soil
sampling in 25 locations at 6” bgs at DU KNI-AB.
- Confirmation soil
sampling in 8 locations at 6” bgs at DU KNI-C.
- Confirmation soil
sampling in 6 locations at 6” bgs at DU KNI-D.
4361 A Highway 25 North
- Confirmation soil
sampling consisted of 35 locations at 6” bgs at DU 151.
- Per homeowner request,
the driveway was rerouted on the property.
4110 Deep Lake Boundary Rd
- Subsurface utilities were
located and BMPs were installed.
- Excavation to 6” bgs was
performed at DUs 218 and ROY from October 1-3. The area was screened with the
XRF.
- Confirmation soil sampling
in 13 locations at 6” bgs at DU 218.
- Confirmation soil
sampling in 6 locations at 6” bgs DU ROY.
- A total of 270 cy of excavated
soil was transported to the Stevens County Landfill.
Parcel Number 151-H 195
- Performed the final
pre-excavation site walk with Debra Wulff (BIA), Patti Bailey (CCT), and Don
Hurst (CCT) to finalize excavation boundaries, review scope of work, and locate
potential areas of sensitivity. The two DUs are TA195-A and TA195-B.
Central Soil Stockpile (located at the Command Post)
- A total of 240 cy transported
to Stevens County Landfill.
- A total of 482 cy of
imported topsoil and 60 cy of imported gravel was delivered to the Command Post
stockpile.
2.1.2 Response Actions to Date
Refer to POLREP 1.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
On
August 11, an Administrative Settlement Agreement and Order on Consent (ASAOC)
for Removal Action (Docket No. CERCLA-10-2015-1040) was signed by EPA, Teck
Metals Limited, and Teck American Incorporated. The ASAOC provides the
terms of the agreement under which Teck will conduct the removal action under
oversight by EPA.
2.1.4 Progress Metrics
As of October 3, 2015:
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
Soil |
Solid |
5,998 tons |
varies |
NA |
Landfill |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.2.1 Anticipated Activities
2.2.1.1 Planned Response Activities
During
this removal action, contaminated soil will be excavated and removed from 14
residential properties and 1 tribal allotment. Soil will be excavated in
6" lifts to a maximum depth of 12" total depth (24" total depth
in garden areas). The excavation will be backfilled with the material of
the property owner's choice. The excavated soil will be transported and
disposed at an appropriate landfill.
2.2.1.2 Next Steps
Excavation, sampling, and/or backfilling will continue
at the properties described in Section 2.1. In the next reporting period,
October 4-10, excavation is scheduled to begin at the following properties:
- ·
Parcel Number 151-H 195
2.2.2 Issues
|