2.1.1 Narrative
The fire
was reported to local officials at 05:35 local time. Both the Salish and
Kootenai Tribes and the Lake County OEM requested assistance from EPA.
2.1.2 Response Actions to Date
EPA OSCs (Nguyen,
Sandoval, and Guy) arrived on-scene at approximately 6:30 pm on April 8 and joined
incident command. On-site were fire
equipment and personnel from the Polson and Ronan fire departments. The on-scene incident commander, Stephen
Stanley (OEM, Lake County), provided an update of the situation and the tactics
being deployed to suppress the fire. A contractor hired by the owner was hauling soil
in from a close borrow area (1/2 mile) for capping operations to smother and
put out the fire. The contractor had
three excavators in the borrow area, two bull dozers and a front end loader at
the fire, and nine dump trucks.
The fire was on the front face of the landfill, which
consisted of a steep surface approximately 50-60 feet high and 1,000 feet
long. Soils were being hauled to the top
face of the landfill above the fire, dumped, and then pushed with a dozer over
the edge. Below, a dozer was pushing
soils into a deep pit below the face in order to build up a berm at the base of
the fire to hold soils being placed from above. EPA offered assistance and equipment as
needed. ERRS arrived with an excavator,
dozer, and water truck. OEM asked EPA to
standby in case any of the local contractor’s equipment broke down.
By 8:00 pm, approximately 95% of the burning face had been capped and extinguished
with soil. Several sites mid-level on
the face were difficult to cover on the steep slope and were still exposed and
flaring. At 10:00 pm the soil hauling
operation was stopped for the night for safety concerns. Several Polson fire trucks
remained on-site to monitor and cool the uncovered hotspots until morning. With a significant area of the burn face covered, emissions
from the site were fairly localized to the pit and surrounding site, with some emissions
leaving off-site towards Highway 93.
On the morning of April 9, crews commenced at 7 am with soil
hauling and capping activities. START
arrived and per OSC direction set up an air monitoring network to monitor
particulate emissions in the work zone and outer perimeter of the site. Michael Durglo, from the Confederated Salish
& Kootenai Tribes of the Flathead Reservation, Natural Resources
Department, was on-site and requested EPA to provide air monitoring data taken at the site. By 10 am, the lower pit area had been filled
and soils were pushed up the slope from the berm to cover the mid-level hot areas. Several exposed small hot spots with visible emissions
remained on the capped face. By 12 pm a
cap was in place over the entire burn site.
No discernable emissions were observable. Both fire departments demobilized soon thereafter. EPA demobilized both ERRS and START. The owner's contractor continued with capping
operations, building up the base of the landfill face and bringing the slope
out with additional soil placement. Total
volume of clayee soil hauled and used for capping was estimated at
6,500 cubic yards. An equivalent amount
or more of material was mobilized from sidewalls of the old quarry and used for
filling in the pit and base of the landfill face.
During the afternoon, significant truck loads of soil were hauled in and staged on top of the landfill to address flare-up of hot spots should they occur over the next several days.
Inpection of the landfill was conducted again at 3 and 7 pm by EPA. Conditions remained stable. The owner was present at the 3 pm inspection and indicated he would be inpecting the site periodically on Sunday. Stephen Stanley (OEM, Lake County), indicated earlier in the day that he would be returning on Monday to inspect site conditions.
EPA will demoblize on the morning of April 10.
2.1.3 Progress Metrics
Fire has been extingquished. Additional soils continue to be placed on the face of the landfill fire area to ensure fire does not re-start.
|