2.1.1 Narrative
2.1.2 Response Actions to Date
1. 1. Diversion Channel
See Pol/Sitrep #17 for diversion channel description.
The right downstream banks of the channel are being redesigned to allow water to filter through without having soil slough from the embankments. A filtering system similar to the design of the dam will be implemented through all areas that are not reinforced by the mountainside.
Construction of the water dissipator at the end of the channel has begun. OSC received access from adjacent property owner allowing remediation on both sides of the creek bed. The area of Ore Knob Branch 150 downstream of the water dissipator will be dredged to remove tailings that have settled in the creek bed. The branch will be reinforced with rock as an erosion control mechanism. Sediment control measures including berms and rock check dams will be placed downstream before work begins on the branch.
A 1000 ft. fence has been placed along each side of the diversion channel at it deepest points as a safety measure. Warning signs have been placed along this area discouraging trespassing.
2. Site Ponds
See Pol/Sitrep #17 for Site Ponds description.
Pond 2 is still being filled with tailings that are excavated from the dam face and water dissipator. The area is being contoured to allow water to drain to the rear (south) of the tailings impoundment. The other three ponds are all filled and re-vegetated.
3. Tailings Dam
See Pol/Sitrep #17 for Tailings Dam description.
A. Sediment Pond
The sediment pond is periodically cleaned to maintain the maximum amount of freeboard.
B. Starter Dam
The Starter Dam has been completely constructed. The face was re-graded to an approximately 3.5:1 slope and the bottom most portion was excavated to the water table. It was then filled with filter sand covered with a water-permeable liner. Next, the sections were covered with small rock, backfilled, and seeded.
C. Shear Key
The Shear Key has been completely constructed and is functioning as planned.
D. Main Tailings Impoundment
The dam face of the Main Tailings Impoundment has been totally re-sloped. The filter drain is functioning as expected and the slope has been revegetated to prevent erosion.
4. Other/Miscellaneous
A public meeting was held in April to update residents of ongoing and upcoming activities at Ore Knob. Representatives from ERRB and Remedial Branches along with NCDENR and NC Dept. of Public Health were present to answer questions from the public and the press.
EPAs remedial program has conducted well sampling events at homes around the Ore Knob Mine Site. Wells that have levels of contaminants that are of concern are being given bottled water to drink as a precaution. Residents requesting to receive bottled water are receiving it also.
Constant precipitation has greatly hampered Site activities, increasing site costs and extending the project schedule.
Recycling
In an effort to reduce the carbon footprint of the Ore Knob Mine Site, all paper and plastics are being recycled and no construction waste is being generated on-site. All soils, rock and water is recycled for use onsite—thus eliminating transportation and disposal costs.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
PRPs have been identified and enforcement activities are underway.
2.1.4 Progress Metrics to date (approximate)
Product Stream
Quantity (CY)
Soil
141780
Tailings
78195
Rock
30330