2.1.1 Narrative
An Action Memorandum approving response actions to address the contaminated soil in the residential Eastwick neighborhood was signed July 21, 2016. The RPM conducted several outreach sessions to inform the residents and community groups about the Removal Action. EPA also mailed information to residents of the community. The RPM also gained access from and discussed response actions with residents and property owners to be directly affected by the Removal Action.
The OSC and RPM first convened with ERRS (ER) and START (Weston) contractors on the Site on August 8, 2016 (Mobilization Date). This meeting and subsequent meetings were conducted to assure a proper plan of action and that proper personnel, equipment, and materials could be identified to implement the response action. Between 8/8/2016 and 9/6/2016, the OSC and RPM continued preparation activities inclusive of coordination with residents and contractors and development of air monitoring and other actions to enhance safety in the community during the Removal Action.
2.1.2 Response Actions to Date
ERRS contractors continued to prepare the Site for Removal Actions. Construction of the area to be used for Command Post, equipment staging, material staging was completed. This area is located near the intersection of 83rd Street and Buist. Trees and brush were cut and most have been chipped. Chipping activities continue. The area was leveled, a fabric was laid and the area upon which the Command Post will sit was stoned. EPA and ERRS trailers arrived on 9/12/16. Electric generator was also hooked up the week of 9/12/16.
ERRS completed the accessway from the Command Post area to the area of the landfill upon which the contaminated soil will be staged. The accessway courses immediately behind or near the residential properties subject to the Removal Action in order the facilitate the removal and transportation of the contaminated soil away from the residences. The soil staging area is near the top of the landfill. The initial construction of the access road involved the removal of trees and brush and debris and was completed 9/9/16. Clean stone was placed on the accessway and rolled. This work was completed by 9/20/16. The soil staging area on the landfill was bermed and covered with fabric to manage stormwater. Accessway terminates inside this disposal area. Once soil staging begins, soil will be covered at the end of each work day. Silt fencing and high visibility fencing were installed along the accessway where needed, to manage potential stormwater and minimize potential public access through the adjacent Eastwick Park. Fencing between the accessway and yards was removed on 9/22/16. Large trees in front and back yards of homes to be addressed in near future along Buist Avenue were removed by ERRS.
Dust suppression is being provided by spraying water from a water truck. Water is obtained from a hydrant under permit. Portions of the accessway which had not yet been stoned were also watered over the weekend of 9/10/16.
Soil samples for clean backfill and topsoil were collected by START contractor on 9/16/19 and 9/19/19, respectively, with results being provided within 48 hours from the laboratory. Sample results indicated that both sources were acceptable. There were no exceedances of site-specific soil cleanup levels established in the OU1 Record of Decisions. The backfill and topsoil also meet criteria to be considered to be clean fill under the Pennsylvania Management of Fill policy.
The START contractor conducted air monitoring using Dust Trak units to monitor dust levels upwind and downwind of the work area. Data from the Dust Trak units is being uploaded in real-time to the the EPA ERT VIPER website. Total Dust Action Limits that are protective for residents and workers have been established in the HASP. The VIPER website has been set to provide alerts to EPA and START personnel when dust levels reach certain thresholds prior to hitting Total Dust Action Limits. This will facilitate any additional dust suppression activities. Air monitoring data indicates that dust suppression will be necessary throughout the action. The soil is very fine and dry and easily went airborne when travelled. During residential excavations, dedicated ERRS personnnel will be conducting dust suppression activities.
The EPA Remedial Project Manager (RPM) and START contractor met with the property owner representatives and tenants of the first four yards to be addressed. Inventory was taken of all items to be removed prior to excavation. A restoration plan and the expectations for the work to be performed was developed and agreed to by EPA, property owners and tenants. The RPM has explained to the property owners and tenants the process that will be followed during yard excavation and restoration. Although dust suppression will be ongoing, EPA has recommended that all doors and windows remain closed during excavation to minimize any dust entering the homes and to dampen any loud noises. Excavation of the first yards will start on 9/26/16. Three to four yards will be addressed the first week, depending on the pace of progress. The current plan is to complete restoration of yards within 5 days.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Activity related to identification of PRPs is still ongoing.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|