U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Zonolite Road Atlanta GAO144

All POL/SITREP's for this site Zonolite Road Atlanta GAO144
Atlanta, GA - EPA Region IV
POLREP #7
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Zonolite Road Atlanta GAO144 - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region IV

Subject: POLREP #7
Progress
Zonolite Road Atlanta GAO144
B407
Atlanta, GA
Latitude: 33.8063720 Longitude: -84.3417654


To:
From: Kevin Eichinger, OSC
Terry Stilman, OSC
Date: 12/15/2011
Reporting Period: December 1, 2001 through December 14, 2011

1. Introduction
  1.1 Background
   
Site Number: B410    Contract Number:  
D.O. Number:      Action Memo Date: 4/8/2011
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: PRP    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 6/1/2011    Start Date: 6/1/2011
Demob Date:      Completion Date:  
CERCLIS ID:    RCRIS ID:
ERNS No.:    State Notification:
FPN#:    Reimbursable Account #:

1.1.2 Site Description

A removal site evaluation indicating that the Zonolite Road Site be given priority for removal eligibility was completed on March 23, 2011.   The Site, also referenced as the “GAO 144 site” was the former location of a vermiculite expansion (or, exfoliation) plant.  According to the previous owner and operator, the expansion plant operated from 1950 until 1970 and received between 499 and 1,225 tons of vermiculite concentrate from the W.R. Grace vermiculite mine in Libby, Montana. 

 1.1.2.1 Location

The Site is located approximately 4.5 miles northeast of downtown Atlanta, Georgia, in a developed urban area of mixed light-industrial, commercial, and residential use.  The site occupies about 16 acres, some or all of which was the former location of a vermiculite expansion plant.  The Site is bordered to the south by Dalon Road, a landscape services and garden business, and the south fork of Peachtree Creek.  To the west of the Site are Peachtree Creek and several residences.  The Site is bordered to the north by railroad tracks and a complex containing numerous commercial and light industrial businesses.  Residential communities are located to the south beyond the south fork of Peachtree Creek, to the west, and to the north beyond the railroad tracks.  
 

2. Current Activities
  2.1 Operations Section
    2.1.2 Response Actions to Date

Summary - To date, approximately 9,500 tons of material has been removed and sent offsite for disposal. 

December 1, 2011 - Removal operations continued.  37 dump trucks were loaded and sent offsite with approximately 555 tons of material.  Perimeter and personnel air sampling continued.  No asbestos was detected in the perimeter air samples. Two personnel samples from the exclusion zone contained asbestos at 0.00098 fibers/cc.  This level is far below the OSHA PEL for Asbestos (0.1 fibers/cc) and ABS site clean up level of 0.02 fibers/cc.

December 2, 2011 - Removal operations continued.  30 dump trucks were loaded and sent offsite with approximately 450 tons of material.  No asbestos was detected in the perimeter air samples.  One personnel sample from the exclusion zone contained asbestos at 0.00098 fibers/cc.  This level is far below the OSHA PEL for Asbestos (0.1 fibers/cc) and ABS site clean up level of 0.02 fibers/cc.

OSC Terry Stilman and START met with W.R. Grace, DeKalb County, URS, AECOM, and the South Fork Conservancy to discuss site drainage, retention basin and final grading.

December 5, 2011 -  Removal operations continued.  41 dump trucks were loaded and sent offsite with approximately 615 tons of material.  Perimeter and personnel sampling continues. No asbestos was detected in personnel or perimeter air samples.  EPA Environmental Response Team Member, Phil Campagna spent the day on-site and reviewed the site sampling and air monitoring plans.  At his recommendation, the VIPER system was requested.  This system provides real time, remote monitoring of the ambient dust monitors currently in use on the site.

A main hydraulic line ruptured on the excavator at 1530 hours, removal operations were stopped for the day.  The tree shredding/chipping began.  OSC Eichinger met with the property management firm for the adjacent property to discuss using an access road that runs between Zonolite Place and Zonolite Road.  Approval was granted.  The road was improved and drainage systems planned.  The road will be restored to the property management firm specifications at the conclusion of the project.

December 6, 2011 - Removal operations continued.  43 dump trucks were loaded and sent offsite with approximately 645 tons of material.  Perimeter and personnel sampling continues.  No asbestos was detected in the perimeter air samples.  One personnel sample from the exclusion zone contained asbestos at 0.00097 fibers/cc.  This level is far below the OSHA PEL for Asbestos (0.1 fibers/cc) and ABS site clean up level of 0.02 fibers/cc.
 
DeKalb County provided sewer diagrams, no storm or sanitary systems will be impacted by the project.  Tree shredding/chipping continued.

December 7, 2011 - Rainy weather prevented soil removal. Site drainage was addressed and tree shredding/chipping was completed.  Chipped trees will be stored on-site for later use by Dekalb County.  The haul roads were improved.  Results on the material in the abandoned drum was received and reviewed.  Material was non-hazardous and will managed appropriately.  

December 8, 2011
 - Removal operations continued.  16 dump trucks were loaded and sent offsite with approximately 240 tons of material.  A hydraulic line ruptured on the excavator which cut removal operations short for the day.  Perimeter and personnel air sampling continues. No asbestos was detected in the perimeter or the personnel air samples.   The VIPER system was setup and the particulate air monitoring data was sent to the ERT server.  Results of the backfill material was received and reviewed.  The material was approved to be used a back fill.

December 9, 2011 - Removal operations continued.  45 dump trucks were loaded and sent offsite with approximately 675 tons of material.  Perimeter and personnel air sampling continued.  The Northwest perimeter sample contained asbestos at 0.0014 fibers/cc.  This level is far below the ABS site clean up level of 0.02 fibers/cc.  Crews will implement additional controls and modify wetting operations.  

December  10, 2011 - Crews removed the soil and cleaned the existing concrete/blacktop pad in the Southeast corner of the exclusion zone.  Polyethylene sheeting was laid and the clean mulch was located to this area and covered for use by DeKalb County in the future.

December 12, 2011 - Removal operations continued.  48 dump trucks were loaded and sent offsite with approximately 720 tons of material.  Perimeter and personnel air sampling continued.  No asbestos was detected in the perimeter samples.   One personnel sample from the exclusion zone contained asbestos at 0.00097 fibers/cc.  This level is far below the OSHA PEL for Asbestos (0.1 fibers/cc) and ABS site clean up level of 0.02 fibers/cc.

December 13, 2011 - Removal operations continued.  47 dump trucks were loaded and sent offsite with approximately 705 tons of material.  Perimeter and personnel air sampling continued.

December 14, 2011 - Removal operations continued.  50 dump trucks were loaded and sent offsite with approximately 750 tons of material.  Perimeter and personnel air sampling continues.  DeKalb County representatives visited the site to check on the progress and to discuss the status of the site grading plan.  DeKalb County will attempt to deliver the final plan as soon as possible.  The equipment rental company met with the Site Superintendent on-site to discuss recent equipment failures.  Superfund Division Director, Franklin Hill, was provided a site summary and tour.  Technical Services Branch Chief, Glen Adams, Toxicologist Tim Frederick and Geologist Ben Bentkowski, OSC Eichinger and START discussed the confirmation sample plan.  The current plan will need to be modified to account for the additional size of the site, the final grading plan and the South Fork Conservancy's conceptual plan for the park.


  2.2 Planning Section
    2.2.1 Anticipated Activities

Continue with soil removal.

Receive the final grading and site restoration plan.

Finalize and update the confirmation sampling plan.

  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    No information available at this time.

3. Participating Entities
  3.2 Cooperating Agencies

Dekalb County


4. Personnel On Site
  EPA - 6 (Various times, throughout the reporting period)
DeKalb County Natural Resources - 1
AECOM - 3
START - 1
URS - 2
W.R. Grace (Remedium Group) - 1 
One Group Consulting - 2
Winter Environmental - 21

5. Definition of Terms
  ABS - Activity Based Sampling - Collecting of air samples while engaging in dust generation activities that could disturb asbestos fibers and release them into the air.

OSHA - Occupational Safety and Health Administration - an agency of the United States Department of Labor whose mission is to prevent work-related injuries, illnesses, and occupational fatality by issuing and enforcing standards for workplace safety and health.

PCM - Phase Contrast Microscopy - Sample analysis procedure, following NIOSH Analytical Method 7400, used to determine the presence of fibers in air samples.  This procedure does not differentiate between non-hazardous fibers and asbestos fibers.  Used to determine the effectiveness of engineering controls and work practices during the actual removal of the asbestos contaminated material. 

PEL - Permissible Exposure Limit - Legal limit in the United States for worker exposure to a chemical substance or physical agent.

TEM - Transmission Electron Microscopy - Sample analysis procedure, following NIOSH Method 7402, used to determine the presence, type and concentration of asbestos in air samples.

6. Additional sources of information
  No information available at this time.

7. Situational Reference Materials
  No information available at this time.