2.1.2 Response Actions to DateSummary - To date, approximately 14,120 tons of material has been removed and sent offsite for disposal to the Waste Management Landfill in Ball Ground, Georgia. OSCs Eichenger, Stilman and START on-site conducting oversite.
Air sample data was received for December 27th and 28th, 2011. No asbestos was detected in the perimeter or personnel air samples taken on December 28th. No asbestos removal work occurred on December 27th, so no air sampling occurred.
December 29, 2011 - Removal operations continued. 51 dump trucks were loaded and sent offsite with approximately 765 tons of material. Perimeter and personnel air sampling continued. One personnel sample contained asbestos at 0.00099 fibers/cc. This level is far below the ABS site cleanup level of 0.02 fibers/cc. No asbestos was detected in the perimeter samples.
December 30, 2011 - Removal operations continued. 50 dump trucks were loaded and sent offsite with approximately 750 tons of material. Perimeter and personnel air sampling continued. One personnel sample contained asbestos at 0.00098 fibers/cc. This level is far below the ABS site cleanup level of 0.02 fibers/cc. No asbestos was detected in the perimeter samples.
January 2, 2012 - No work occurred due to the holiday.
January 3, 2012 - Removal operations continued. 48 dump trucks were loaded and sent offsite with approximately 720 tons of material. Perimeter and personnel air sampling continued. One personnel sample contained asbestos at 0.00096 fibers/cc. This level is far below the ABS site cleanup level of 0.02 fibers/cc. No asbestos was detected in the perimeter samples.
January 4, 2012 - Removal operations continued. 49 dump trucks were loaded and sent offsite with approximately 735 tons of material. No asbestos was detected in personnel or perimeter air samples. URS collected a 5-point composite of soil from beneath the southern concrete pad and one additional grab sample from an exposed portion of the pad; submitted the samples for bulk TEM analysis. DeKalb County delivered diagrams for the grading and proposed utilization of the excavated area.
January 5, 2012 - Removal operations continued. 51 dump trucks were loaded and sent offsite with approximately 765 tons of material. Perimeter and personnel sampling continues. No asbestos was detected in personnel or perimeter air samples. One Group collected eight grab soil samples for bulk TEM analysis from the wooded area and small berms to the NE of the site, south of the pathway leading to the commercial buildings and storm water drainage culvert. Additional suspect material where the base of the excavation and northern and southern concrete pads meet (sidewall) was found.
January 6, 2012 - Removal operations continued. 12 dump trucks were loaded and sent offsite with approximately 180 tons of material. Perimeter and personnel air sampling continued. One personnel sample contained asbestos at 0.00194 fibers/cc. This level is far below the ABS site cleanup level of 0.02 fibers/cc. No asbestos was detected in the perimeter samples.
Contractors moved scaffolding and scrapped the north and south concrete pads. URS and One Group collected/submitted 3 samples of material different in color (red, dark brown and brown) along the sidewall of the north and south pad; and collected 2 additional samples from the sidewall of shiny “vermiculite-like” material requested by EPA with 24 TAT (Monday) to MAS. START L. Meadows collected 2 samples from the same vein along the sidewall of the north and south pad with 72 TAT (Thursday) samples will arrive at BATTA Environmental Associates on Monday.
January 9, 2012 - Removal operations continued. 48 dump trucks were loaded and sent offsite with approximately 720 tons of material. Perimeter and personnel sampling continues. No asbestos was detected in personnel or perimeter air samples.
January 10, 2012 - Removal operations continued. 9 dump trucks were loaded and sent offsite with approximately 135 tons of material. Perimeter and personnel sampling continues. No asbestos was detected in personnel or perimeter air samples. Contractors began staging backfill material on-site.
January 11, 2012 - Removal operations were suspended due to the heavy rains and damage to the haul roads.
January 12, 2012 - Removal operations continued. 9 dump trucks were loaded and sent offsite with approximately 135 tons of material. Perimeter and personnel sampling continues. No asbestos was detected in personnel or perimeter air samples.
Contractor began preparation to pump the storm water/ groundwater from the base of the excavation pit. Preliminary results for the 8 bulk samples from the berms located between the NW corner of the silt fencing and the trailer were non-detect. START collected 2 sidewall samples from the north pad (ATV-SW-01) and south pad (ATV-SW-02), which one sidewall sample, from the north pad contained Libby Amphibole at 0.41%. Based on the sampling results additional contaminated soil (above 0.25% Libby Amphibole) and a portion of the concrete pad will be removed.
Air monitoring was late setting up; after contractor moved asbestos containing material. Limited number of material was moved though OSC Eichinger requested that air monitoring always be in place prior to removal of asbestos containing material.
OSC Eichinger and START Meadows observed poor housekeeping operations between clean fill dirt and ACM soil being staged. Suggestions of segregation, scrapping, and removal of final material were forwarded to Grace and Winter representatives.
January 13, 2012 - Removal operations continued. The main extent of the waste pile has been removed from site. Crews began removing and restoring the stream bank that runs around the perimeter of the site. 19 dump trucks were loaded and sent offsite with approximately 285 tons of material. Perimeter and personnel sampling continues. No asbestos was detected in personnel or perimeter air samples.
OSC Eichinger coordinated and hosted a site meeting to discuss site status, bulk and ABS sampling, concrete pad delineation, and additional grading proposals. Representatives from EPA, START, DeKalb County, the South Fork Conservancy, W.R. Grace, and W.R. Grace's contractors attended. Based on decisions made at the meeting, a final grading plan will be developed.
January 16, 2012 - Limited crews on-site due to the Martin Luther King Holiday. Crews continued pumping water from the excavation. Perimeter and personnel sampling continues. START and URS collected 16 individual grab aliquots and 4 composite samples for standard turn.
January 17, 2012 - No removal operations occurred. Crews worked on constructing new haul roads to excavate the stream bank. The rain slowed down operations and the excavation is in ground water.
January 18, 2012 - No removal operations occurred. Crews continued to construct the haul roads. Perimeter and personnel sampling continues. START and URS collected bulk soil samples from under the southern pads at a depth of 3 feet.