Ironwood Manufactured Gas Plant Site

All POL/SITREP's for this site Ironwood Manufactured Gas Plant Site
Ironwood, MI - EPA Region V
POLREP #3
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Ironwood Manufactured Gas Plant Site - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #3
Progress
Ironwood Manufactured Gas Plant Site
B5ZC
Ironwood, MI
Latitude: 46.4516240 Longitude: -90.1780130


To:
From: Kathy Halbur & Jacob Hassan, OSC
Date: 9/20/2012
Reporting Period: 9/10/2012-9/2012

1. Introduction
  1.1 Background
   
Site Number: B5ZC    Contract Number: EP-S5-08-04
D.O. Number: 0051    Action Memo Date: 8/9/2012
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 8/20/2012    Start Date: 8/22/2012
Demob Date:      Completion Date:  
CERCLIS ID: MIN000510500    RCRIS ID:
ERNS No.:    State Notification:
FPN#:    Reimbursable Account #:

1.1.1 Incident Category

Time-Critical

1.1.2 Site Description

The Ironwood Manufactured Gas Plant (MGP) Site is the location of a former coal gasification plant. Reportedly, the plant was constructed in 1911 and operated using a carbureted water gas (CWG) process.  A review of Sanborn maps indicates that the processes at the Site were consistent with typical CWG processes for the era. These processes generally included a first step in which coke or coal was heated in a closed vessel or retort into which steam was injected. A flammable gas mixture of methane and carbon monoxide was produced. In some cases petroleum products may have been applied to the heated mixture increasing the flammability of the resultant gas mixture. During these processes, a dense, oily liquid known as coal tar would condense out of the gas at various stages during its production, purification and distribution, and the coal tar would need to be either recycled in the process, sold, or otherwise disposed of. 

The plant continued operations and distribution of manufactured gas until the late 1950's when natural gas pipelines and service became more readily available in the area. By 1956 the plant was for sale and based on accounts of the Wisconsin Public Service Commission, by 1961 had discontinued service to Hurley, including the removal of meters following abandonment.

Interviews conducted by the Michigan Department of Environmental Quality (MDEQ) with local residents indicate that the buildings at the Site were removed prior to the gasometers (gas storage tanks). Based on the historical accounts, the surface structures at the Site were demolished and removed during the 1970's and the 1980's.  Following removal of the surface structures, the Site was reportedly used by the City of Ironwood for the storage of inoperable equipment and debris.

1.1.2.1 Location

The Site does not have a physical address but is located on the northwest corner of Hemlock Street and West Ayer Street in Ironwood, Gogebic County, Michigan

1.1.2.2 Description of Threat

The Site contains MGP waste material, such as coal tar and other process waste, that are the source of hazardous substances that have migrated and are migrating into soil, groundwater, surface water, and sediments of the Montreal River.  Contaminants of concern identified in soil, groundwater, surface water, and sediment include volatile organic compounds (VOCs), semivolatile organic compounds (SVOCs), polyaromatic hydrocarbons (PAHs) and inorganic contaminants.

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

During bridge construction at West Norrie Street in 2010, construction crews identified visually contaminated soils suspected to be from the former Ironwood Manufactured Gas Plant site located approximately 700' upstream. MDEQ developed a Site Inspection Work Plan in 2010 to characterize conditions in the subsurface at the Site as well as in the surface water and sediment in the adjacent Montreal River.  The Site Inspection activities performed by the MDEQ were implemented with the intent of evaluating groundwater, surface water, and soil exposure pathways.

The results of the MDEQ’s Site Inspection indicated the presence of uncontrolled hazardous substances at the Site.  Gross tar and MGP process waste contamination was discovered in the surface and subsurface soil primarily located in the historical operating area of the Site, which contained VOC's, SVOC's, and inorganic contaminant concentrations exceeding the MDEQ Part 201 Residential Direct Contact Criteria (RDCC) and Groundwater Surface-water Interface (GSI).  Based on these findings, MDEQ requested assistance from USEPA.

USEPA conducted a site reconnaissance visit on November 19, 2010 to evaluate site conditions and to gather logistical information to assist in the development of a supplement site assessment plan.

A Supplemental Site Assessment was conducted during the week of April 9, 2012.  The Supplemental Site Assessment demonstrated that coal tar and other MGP waste remain buried at the Site in a visually discreet layer and that contaminants from this buried waste (volatile and semi-volatile organic compounds and inorganic compounds) are migrating into the groundwater and surface water (Montreal River). 

    

2. Current Activities
  2.1 Operations Section
    2.1.1 Response Actions to Date

See Previous Polreps for details regarding activities during previous reporting periods.

Significant Site Activities for this reporting period (9/10/12 - 9/20/12): 

  • Completed vegetation removal and chipping
  • Completed excavation of contaminated material along river bank
  • Commenced excavation in former process areas and continued backfilling excavated areas
  • Discovered two additional buried vats of waste (three identified to date)
  • Completed stabilization and removal of material in coal tar vats
  • Continued to haul MGP waste to the landfill (7,250 Tons to date)
  • Continued air monitoring efforts and dust control measures
  • Continued to work with the City of Ironwood on Restoration Plan
  • Continued community office hours

2.1.2 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

The City of Ironwood is the former owner and operator of the Ironwood Gas Works and is the only PRP for this Site.  The City does not have the ability to conduct the clean-up, but is assisting by contributing in-kind services. 

2.1.3 Progress Metrics 

Waste Stream Medium Quantity Manifest # Treatment Disposal
 Coal Tar Soil Soil 7,250 tons
(145 loads)
T75386 -
T75531
Landfill K&W Landfill, Ontonagon, MI


  2.2 Planning Section
    2.2.1 Anticipated Activities

USEPA will hold community office hours every Thursday evening from 5pm to 6 pm in the Engineering Room on the second floor of the City of Ironwood's Memorial Building, 213 S. Marquette Street

2.2.1.1 Planned Response Activities & Next Steps

The following activities are planned for the next reporting period:

  • Continue excavation of contaminated material and backfilling
  • Continue to transport and dispose of MGP waste
  • Relocate the on-site haul road
  • Continue air monitoring efforts and dust control measures
  • Finalize the Site Restoration Plan
  • Begin Site restoration (grading of excavated areas)
  • Continue community office hours

Site activities will be shut down from September 21-25, 2012 to allow the City to pave Ayer and Hemlock Streets and to provide the crew a short break.  Security will be on-site around the clock while operations are shut down. 

2.2.2 Issues

The City streets adjacent to the Site (Hemlock & Ayer Streets) are still under construction as part of the City's sewer and water line replacement project.  Paving is scheduled during the Site shut down period.  If paving does not occur as scheduled, delays associated with transportation and disposal, as well as additional cost will be realized.

Inclement weather has resulted in some down time.

  2.3 Logistics Section
    The following equipment was used during the reporting period:

1 - 1/2 ton pickup truck
3 - 3/4 ton pickup trucks
2 - excavators (including HoRam attachment)
1 - front end loader
1 - bull dozer
1 - wood chipper
1 - water truck (dust control)
1 - skid steer with broom attachment (street sweeper)
1 - 21,000 gallon frac tank
1 - 12' x 60' office trailer
1 - 10' cargo trailer
1 - portable satellite unit
4 - DataRams with Viper
1 - Multi-Rae

The chipper was demobilized during this reporting period. The frac tank will be demobilized during the next reporting period (river bank excavation completed and no groundwater recharging occurring).

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer

Kathy Halbur, OSC
Jacob Hassan, OSC

3. Participating Entities
  3.2 Cooperating Agencies

City of Ironwood
Gogebic County Soil and Erosion Control District
Michigan Department of Community Health
Michigan Department of Environmental Quality
Western Upper Peninsula Health Department
Wisconsin Department of Health Services
Wisconsin Department of Natural Resources

4. Personnel On Site
 

During this reporting period:

U.S. EPA: 2 (Halbur, Hassan)
START (Weston): 2
ERRS (LATA-Kemron & CMC): 8


5. Definition of Terms
  ATV - All terrain vehicle
BGS - Below Ground Surface
CWG - carburated water gas
ERRS - Emergency and Rapid Response Services
GSI - groundwater surface-water interface
MDEQ - Michigan Department of Environmental Quality
MDNR - Michigan Department of Natural Resources
MGP - Manufactured Gas Plant
OSC - On Scene Coordinator
PAH - polyaromatic hydrocarbons
PRP - Potentially Responsible Party
RDCC - Residential Direct Contact Criteria
START - Superfund Technical Assessment and Response Team
SVOC - semivolatile organic compounds
USCG - United States Coast Guard
USEPA - United States Environmental Protection Agency
VOC - volatile organic compounds
WDNR - Wisconsin Department of Natural Resources
WUPHD - Western Upper Peninsula Health Department



6. Additional sources of information
  6.1 Internet location of additional information/report

Please see the following websites for project updates:

www.epa.gov/region5/cleanup/ironwood

www.epaosc.org/ironwoodmgp


6.2 Reporting Schedule

Please see the following websites for project updates:

www.epa.gov/region5/cleanup/ironwood

www.epaosc.org/ironwoodmgp


Progress Polreps will be issued as significant activities occur.

7. Situational Reference Materials
 
 R5 Priorities Summary
This is an Integrated River Assessment.  The numbers should overlap. Miles of river systems cleaned and/or restored  <1
Cubic yards of contaminated sediments removed and/or capped 150
Gallons of oil/water recovered  0
Acres of soil/sediment cleaned up in floodplains and riverbanks  2
Stand Alone Assessment Acres Protected  4
Number of contaminated residential yards cleaned up  0
Human Health Exposures Avoided 100
Number of workers on site 11
Contaminant(s) of Concern
Contaminant(s) of Concern Coal tar, VOCs, SVOCs, inorganic materials, PM