|
|
2.1.1 Narrative
During this time period, the ERRS contractor continued excavation and installation of the interceptor trench on CPA land. The START contractor collected samples of excavated soils.
2.1.2 Response Actions to Date
MONDAY June 16, 2014: Personnel on-site: EPA – 2, USCG – 1, START – 1, ERRS – 8.
The shipment of supplies and equipment from Hawthorne left Guam on a Cabras Marine vessel, due to arrive at the port of Rota early on June 17. In preparation for the arrival of Hawthorne mechanics, ERRS built a temporary containment structure and drained the hydraulic system of the CAT330. START received data indicating that stockpile 8 was below TPH action levels, and stockpile 7 was above the TPH action levels. ERRS began filling cubic yard boxes with contaminated soil from stockpile 7 and loading them into shipping containers. The first full container of contaminated soil was labeled and sealed for transport. ERRS also reinforced pallets to handle cubic yard boxes of soil, which weigh approximately 5000 lbs. Pallets available on-island are not strong enough for this weight and must be reinforced with plywood to safely carry boxes of soil. Sump pipe segments for risers 3, 4, and 5 were cut and capped to be ready for installation.
TUESDAY June 17, 2014: Personnel on-site: EPA – 1, USCG – 1, START – 1, ERRS – 8.
OSC Musante demobilized from site. The Cabras Marine vessel from Guam arrived, but the hydraulic hammer was not aboard, as it was too heavy for the boat with the additional supplies needed, including a compressor, hydraulic oil, and the mechanic’ tools. The hammer will be shipped on its own on to arrive June 18. The Hawthorne mechanic and their Guam operations manager arrived on site and the mechanic purged the CAT330 hydraulic system, which had been contaminated with water while the hammer was operated below groundwater during trenching. The first container of contaminated soil was transported off-site to be staged for shipping. ERRS continued filling cubic yard boxes with contaminated soil from stockpile 7 and began loading the boxes into containers 2 and 3. START received analytical data indicating stockpiles 9 and 10 are below TPH action levels.
WEDNESDAY June 18, 2014: Personnel on-site: EPA – 1, USCG – 1, START – 1, ERRS – 8.
The hydraulic hammer arrived from Guam and was transported to the site. The non-operational hammer was loaded on to the Cabras Marine vessel and transported back to Guam to be repaired and held as a back-up in case the new one fails. The Hawthorne mechanic installed and tested the new hammer. ERRS resumed trenching and completed most of the excavation of trench segment #6. ERRS also completed loading cubic yard boxes of soil from stockpile 7 into containers and containers 2 and 3 were shipped off-site for staging.
THURSDAY June 19, 2014: Personnel on-site: EPA – 1, USCG – 2, START – 1, ERRS – 8.
ERRS backfilled and removed shoring from box #5, completed excavation of segment #6 and installed shoring box #6. ERRS also began digging overburden from trench segment #7. USCG Weil arrived on site from Guam. OSC met with CNMI Historic Preservation Office (HPO) staff to discuss the presence of pre-World War II Japanese tunnels at the southwestern end of the power plant site. The tunnels are reported to have a foot or so of water in them, with oil on the surface. If this is so, the tunnels may represent a preferential pathway for subsurface flow of oil and should be investigated.
FRIDAY June 20, 2014: Personnel on-site: EPA – 1, USCG – 2, START – 1, ERRS – 8.
ERRS backfilled shoring box #6, completed excavation of trench segment #7 and installed shoring box #7. The surface of the groundwater in segment #7 showed a black, oily layer, consistent with its proximity to MW-5, where free product has been observed. START sampled stockpiles, 11, 12 and 13 and shipped samples. In consultation with SEARCH archaeologist and HPO, ERRS conducted exploratory digging to locate the Japanese tunnels. At approximately 2-3 feet below ground surface, a flat concrete surface was found, which extended to at least 10 feet by 8 feet and appeared to possibly be hollow underneath. No means of entry was found and exploratory digging will continue on June 21.
SATURDAY June 21, 2014: Personnel on-site: EPA – 1, USCG – 2, START – 1, ERRS – 8.
ERRS placed sump 3 in shoring box #7, completed excavation of trench segment #8 and installed shoring box #8. Segment #8 showed heavy black spotting and streaking, comparable to segment #7. ERRS, with SEARCH oversight, completed investigation of the area where the Japanese tunnels were believed to be. No evidence of the tunnels was found, and SEARCH concluded that the tunnels were now likely covered by the secondary containment structures for the power plant fuel tanks. Further conversation with HPO staff suggested oil was not present in the tunnels in significant quantities, making it unlikely these tunnels are serving as a preferential pathway for subsurface oil transport. No additional investigation of this area will be conducted.
SUNDAY June 22, 2014: DAY OFF
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Responsible party (CNMI CUC) has been providing assistance, logistical support and supplies, including diesel fuel for heavy equipment.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|