2.1.1 Narrative
March 18th thru March 22nd, 2013
On March 18th, rainfall began at approximately 0845. The crew had enough time to dismantle a small
section of fence at 1723 Read and removed some overgrown shrubbery in between
the fence before rainfall began.
On 3/19/13, the ERRS crew began dismantling the remaining
fencing along the 1723/1725 Read property line.
The back half of the fence belongs to 1725 Read, and the front half of
the fence, which was very dilapidated and could not be saved, belongs to 1723
Read. The crew rolled up the fencing
belonging to 1725 Read to save for later installation once removal work was
completed. After receiving permission
from the property owner to remove the brick sidewalk (very high concentrations
of lead in soil between the brick pavers), ERRS began popping the bricks with
shovels until the Ditch Witch mini excavator and loader arrived on site. Once the two pieces of equipment arrived
(0845), the remaining brick pavers/sidewalk was removed. Contaminated soil between 1723 and 1721 Read
was removed down to clay, approximately one foot. Once the material was pulled out from between
the two homes, the equipment was no longer needed. ERRS decontaminated the equipment, and the
equipment was returned to the rental company.
ERRS utilized the larger excavator and skidsteer to continue removal
efforts. For operational purposes, the
two front yards of 1723 and 1725 Read were removed first, and then material was
pulled from the shared side yards of the two properties. ERRS crew made their
way to the back yard of 1725 Read and ended operations for the day.
On 3/20/13, ERRS began removing contaminated soil from
the back yard of 1723 Read. Once material was removed, START collected post
removal soil samples from the front and back yard of 1723, as the front and
back yard of 1725 Read was not 100% complete at this point. ERRS backfilled
these areas with clay and topsoil, then graded and tamped the areas.
On 3/21/13, the ERRS crew began removal at the front yard
(left side of sidewalk and side yard) of 1725 Read. Some areas of contamination at this yard were
as high as ~600 ppm Pb in the front, and areas along the concrete wall (far
left) were over ~1,000 ppm for Pb. 5,065
ppm Pb was the highest concentration observed along the left side yard of the
home. ERRS continued to pull
contaminated soil along the side yard to the back of the property. Removal was completed at approximately
1130. Sod was also delivered at this
time. START collected post soil samples
from the front and back yard of 1725 Read. There were not enough loads of clay
and topsoil remaining at the Staging Area to complete backfill of this area, so
the ERRS PM purchased several loads of both clay and topsoil to complete the
property. ERRS backfilled the yard with
clay and topsoil and graded the area. Once grading was complete, the area was
tamped. A load of crush-n-run was placed at the back yard of 1723 Read as a
parking pad to replace the previously existing parking area.
On 3/22/13, the ERRS crew placed sod at 1725 and 1723
Read. After today, the site will be shut
down for a week in observance of the Easter holiday. Work will commence on Monday, April 1, 2013.
Residents living at 1727 Read have been notified of our return.
March
25 thru March 29th, 2013
This week was a planned shutdown week for spring break
and Easter holiday as well as time for the federal continuing resolution (CR)
to be passed through the House, Senate and President Obama.
March
31 thru April 6, 2013
Rainfall on 4/1/13, 4/4/13 and 4/5/13- limited to no work
at the site.
On April 1st, the ERRS crew cut down a section of fence from
the front yard of the 1727 Read Avenue property. Due to rainfall at the site,
efforts ceased at approximately 1000 hours.
On 4/2/13, the ERRS crew began removal efforts at the
back yard of 1725 Read. A small section
of yard where two evergreen trees were located remained to be addressed. The ERRS crew removed the trees and
contaminated soil in this location along the alley way. Once the area was backfilled with clay and
topsoil, the evergreen trees were placed back in the ground. The soil was tamped and a small strip of
gravel was placed adjacent to the alleyway in an effort to widen the alley
where traffic was driving onto the yard.
The crew also removed contaminated soil from 1727 Read. The side yard and front yard were completed
on this day. The area was backfilled
with clay, topsoil and the soil was tamped.
On 4/3/13, the crew continued efforts at 1727 Read by
removing contaminated soil from the remaining side yard and back yard of the property. During removal efforts, a severely broken
sewer line was observed at the back of the structure along the foundation. The site plumber was contacted and repaired
the pipe the same day. The removal areas
addressed were backfilled with clay and covered with straw, for topsoil to be
placed the next work day. START also
screened the property located at 1729 Read Avenue. Due to the size of the lot,
several areas were screened. Among the
areas screened at the property, the very front of the property approximately
ten feet from the road had exceedances for lead, and the back third of the
property had exceedances for lead. The
ERRS crew utilized spray paint to spray the areas where removal will take
place. The center of the parcel did not
have exceedances for lead or arsenic.
On 4/4/13, there was heavy rainfall at the site. The ERRS crew ensured items at the Staging
Area were secured and operations ceased for the day. START visited the local NRCS field office to
inquire about historical aerial images. START will have an opportunity to
review these items next week
START contractors continue to assist
with technical support, daily operations, post-excavation confirmation sampling
using X-ray fluorescence spectroscopy (Xrf) and air sampling during excavation
and staging of contaminated soils.
The OSC continues to coordinate clean up efforts and assessments with Tenn Dept
of Environmental Conservation (TDEC) and Tenn Dept of Health as well as
Hamilton County health officials. TDEC and the OSC plan to update Chattanooga
City Council during February 2013. A specific date has not been set by City
Council.
The OSC, Tenn Dept of Health and
Tenn Dept of Environmental Conservation (TDEC) are currently preparing an
assessment strategy for Chattanooga City Council addressing future lead
assessments in the downtown area.
2.1.2 Response Actions to Date
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|