Narrative:
Week's Activities Overview
Over the week beginning the September
23rd, 2013 work focused primarily on the following activities:
- Continued clearing of the land surrounding mercury knob and 1.5 acre
where cover will be installed.
- Completion of excavation,
backfilling and grading of the mercury knob waste pile.
- Completion of backfilling and grading of the battery pile area and the
two rear asbestos pile areas.
- Continuing to improve access paths to hillside waste piles
- Initiated removal of hillside waste piles
- Finalized design for smelter ruins contamination advisory signage
Soil Monitoring:
Throughout the site, after excavation of predesignated waste piles,
remaining soil will be screened with the XRF to determine the
amount of lead, copper, and arsenic remaining in the soil, if any. If
levels of metals in remaining soil exceeds the residential direct contact
criteria (RDCC), soil will be demarkated before backfilling.
This week, the XRF was used to screen the mercury knob waste pile area during
excavation to delineate the area that needed to be excavated and help determine
the depth of contamination. After
excavation, screening showed that copper, arsenic and lead in remaining soil in
the mercury knob pile area (in the hole) were below the residential direct
contact criteria.
The XRF was used to screen the easternmost hillside waste pile on
terrace 3 during excavation to delineate the area that needed to be excavated
and help determine the depth of contamination. After excavation, screening showed that copper, arsenic and lead in
remaining soil in the easternmost hillside waste pile (in the hole) were below the residential
direct contact criteria.
The XRF was also used to better delineate the
boundaries of the hillside waste piles on site, to determine which areas exceed
site specific criteria, and establish excavation boundaries.
Air Monitoring and Sampling:
Every day that excavation and loading of contaminated soils is ongoing air
monitoring will be conducted to ensure public and worker safety. This work
(and therefore air monitoring and sampling) began on 9/16/13.
Chemical hazards due to fugitive emissions from
removal activities are anticipated to be low since the crew will employ
administrative and engineering controls (i.e.; barricades, warning signs, and
suppression measures) to minimize fugitive emissions and particulates (dust)
that migrate off-site.
Meteorological data will be obtained daily from
the NWS website that provides current weather conditions at the Houghton County
Airport (Airport Code: KCMX) and documented in the site logbook.
Perimeter Air Monitoring:
Datarams (DR4) are deployed along three of the perimeter boundaries
where off-site receptors are most at risk to exposure from fugitive emissions.
The smelter facilities were built into the northwest facing hillside, therefore
monitors have been placed along the north, east, and west site boundaries.
Real-time particulate data will be transmitted back to the site
command post where it will be monitored continuously.
A website has been established to view the current and past perimeter air
monitoring data for the site. To view the data go to the web
address: viper.ert.org. You have to create a login on your first visit to
the site. Once you have logged in, go to the R05 Michigan Smelter
Deployment to view site data.
The perimeter action level for particulate has been set at 500 micrograms per
cubic meter (μg/m3). Should a DR4 unit detect sustained particulate
concentrations greater than 500 μg/m3, the source of emmisions will be
investigated, and administrative and/or engineering controls will be initiated
to reduce the particulate emissions.
During the
week of September 23, 2013, two unsustained exceedances of the action level were
recorded. One exceedance of 500 ug/m3 was detected on September 23, 2013.
However, upon investigation, it was found that the exceedance was unrelated to
site activities. A nearby landowner was mowing, generating a dust cloud that
blew onto the site. The exclusion zone action level was not exceeded at that
time. Another exceedance of 500 ug/m3 was also detected on September 27,
2013. This exceedance appears to have been generated by wind during backfilling
the easternmost hillside waste pile excavation area. The exceedance quickly
subsided and engineering controls were applied
to mitigate the particulate concentrations.
Exclusion Zone Air Monitoring and Sampling:
Monitoring:
Personal DR (PDR) particulate air monitors are deployed daily in the exclusion
zone during active excavation and capping activities. The particulate monitors
data-log instantaneous and time weighted average (TWA) particulate
concentrations during operations.
The concentrations of contaminants identified in the removal assessment
analytical results were used to establish a site-specific action level of 95
μg/m3 for total particulates for the exclusion zone. The crew will implement
appropriate engineering control measures if an exceedance of the established
action level is sustained for more than 60 seconds. Action level exceedances
will be managed by setting the monitor to alarm at the established action level
to notify on-site personnel.
During the
week of September 23, 2013, one exceedance of 95 ug/m3 was detected in the
exclusion zone on September 25, 2013. Levels reached 112 µg/m3 over a two minute
period but were not sustained. Another
exceedance of 95 ug/m3 was also detected on September 27, 2013. This exceedance
appears to have been generated by wind during backfilling of the easternmost hillside
waste pile excavation area with clean fill. The exceedance quickly subsided. Engineering
controls were applied
to mitigate the particulate concentrations.
Sampling:
Integrated air sampling for personnel exposure characterization was performed
by ERRS for inorganic contaminants and asbestos in the breathing zone. ERRS
collected samples from personnel with the greatest potential for exposure
within the exclusion zone for each job classification over for a full shift
(minimum of seven hours) over the first three days of intrusive activities. If
the exposure assessment reveals employee exposures to be below the action
level, further exposure determination will be discontinued. If there is a
change of equipment, process, control, or a new task has been initiated that
may potentially result in an employee being exposed at or above the action
level, additional air monitoring shall be conducted. Should the sample results
indicate exposures over the OSHA permissible exposure limits and site-specific
action levels, engineering controls will be adjusted and an additional three days
of air sampling will be conducted.
These samples were
collected on the day of intrusive work in the mercury knob area during the week
of September 23, 2013.
Results that have been received back to date show no detections of lead or
arsenic.
Asbestos Assessment Results
Lab
results from the comprehensive site asbestos survey were received this week. A
total of 21 bulk samples of suspected asbestos containing materials (ACM) were
collected from the foundations and former operating areas of the smelter during
the asbestos survey.
Seven
suspect ACMs were identified and sampled including:
1.
Asphalt
roofing material;
2.
Shingle
roofing material;
3.
Two
different types of brick mortar;
4.
Rectangle
fire brick;
5.
Rounded
fire brick; and,
6.
An
unidentifiable fibrous material, suspected to be degraded thermal system
insulation (TSI).
The following suspect ACMs tested
positive for asbestos (greater than 1 percent asbestos).
- Suspect TSI (samples
MISM-ASB-FM-01-091813, MISM-ASB-FM-02-091813, and MISM-ASB-FM-03-091813); and,
- Asphaltic roofing material (sample
MISM-ASB-LR-01-091813).
Each
of the suspect ACMs were sampled at three different locations across the site.
Based
on sampling results roofing material, was classified as Category I non-friable ACM.
The suspected TSI will be removed as ACM classified as a regulated asbestos
containing material (RACM).
Specific activities completed each day are described in further detail
below.
Activities on 9/23/13
- Completed installation of topsoil and
establishment of final grade with backfill over battery pile area, two rear
asbestos pile areas and haul road cover area for final restoration
- Initiated excavation of the waste pile known
locally as mercury knob waste pile in level C PPE, and staged waste for
disposal. Sampling and screening results of the waste pile do not indicate that
elemental mercury is a contaminant of concern; however, concentrations of
exceed site specific and residential direct contact criteria for arsenic.
- Particulate air monitors deployed in the
vicinity of the work measured particulate concentrations ranging from 0.12 µg/m3 to
46.91 µg/m3. Exceedances of site action levels were not
recorded.
- Perimeter air monitoring was initiated along the north and east site
boundaries. Exceedances of site action levels along the site perimeter were not
recorded.
Activities on 9/24/13
- Continued excavation of the mercury knob waste
pile in level C PPE, and staged waste for disposal. The excavation
averaged approximately one foot in depth and covered an area of approximately
5,000 square feet. Excavated soil is stockpiled in an area of the Site scheduled
for cap placement.
- Used XRF to delineate hillside hot spots that
exceed site specific metals criteria. Rough excavation limits were
initially established based on historical screening and sampling data and
maps.
- Implemented dust control measures
- Particulate air monitors deployed in the
vicinity of the work measured particulate concentrations ranging from 0.02 µg/m3 to
84.33 µg/m3. Exceedances of Site action levels were not recorded.
- Particulate air monitors along the Site perimeter did not record any
exceedances of Site action levels. Excavation work was conducted in Level C
personal protective equipment.
Activities on 9/25/13
- Completed excavation of the mercury knob waste
pile in level C PPE, and staged waste for disposal.
- Begun backfilling mercury knob excavation
area. The floor and limits of the excavation were screened with an XRF to
verify cleanup prior to the placement of backfill.
- Implemented dust control measures
- Finalized design of contamination
advisory signage for smelter ruins. As the removal project cannot remove
all metal contamination from within the actual smelter ruins, perimeter of
ruins will be posted with signage to advise of the presence of some
contaminated soil that exceeds residential direct contact criteria.
-Particulate air monitors deployed in the
vicinity of the work measured particulate concentrations ranging from 0.03 µg/m3 to
112.08 µg/m3. Maximum readings in the exclusion exceeded the action
level of 95 µg/m3. Exceedances were not sustained and were recorded
over an interval of 2 minutes.
- Particulate air monitors along the site perimeter did not record any
exceedances of Site action levels.
Activities on 9/26/13
- Completed backfilling mercury knob excavation
area with clean sand. Topsoil was placed over backfill sand and graded.
- Implemented dust control measures
- Particulate air monitors deployed in the
vicinity of the work measured particulate concentrations ranging from 0.16 µg/m3 to
24.49 µg/m3.
- Particulate air monitors along the site perimeter did not record any
exceedances of site action levels.
Activities on 9/27/13
- Initiated and completed excavation of eastern
most hillside waste pile, located
on Terrace 3, uphill from the Command Post. The waste deposit was excavated by
hand and waste material was transferred to an area of the site scheduled for
cap placement to await disposal. Excavation work was conducted in Level C
personal protective equipment. The floor and limits of the excavation were
screened with an XRF to verify cleanup prior to the placement of backfill.
- Initiated backfilling easternmost hillside
waste pile. Clean
sand backfill was placed in the hillside excavation to match the existing grade.
- Implemented dust control measures
- During the
placement of backfill in the excavated areas, exclusion zone and a perimeter
air monitor exceeded action levels for dust.
- Particulate air
monitors deployed in the vicinity of the work measured particulate
concentrations ranging from 0.02 µg/m3 to 5,750.93 µg/m3.
Exceedances were not sustained and were recorded over an interval of 10
minutes. Similarly, the downhill perimeter dust monitor exceeded perimeter
action levels. Visible dust was not observed and engineering controls were
applied to mitigate the particulate concentrations.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties
(PRPs)
A general notice letter was issued
to the Copper Range Company on November 5, 2012. A response was
received from indicating that they were unsure about their liability and do not
have the financial resources to conduct the removal action at the site.
Investigation is ongoing.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|