2.1.1 Narrative
The
removal action involves the removal of contaminated soils up to two feet below
ground surface found on site. Hazardous substances will be profiled, packaged,
and transported to off-site disposal facilities that are in compliance with the
EPA Offsite Rule. All waste streams will be profiled and disposed of
appropriately. Contaminated soil will be excavated and backfilled.
The property will be graded and stabilized.
2.1.2 Response Actions to Date
During
the period of 11 January – 16 January 2016, 12 grid excavations were completed to
a depth of 6 – 12 inches below ground surface; excavated grids are located on the
north portion of the site. Twelve confirmation samples were collected and shipped
to ALS Environmental Labs, located in Houston, Tx for analysis of Lead
contamination. One of the twelve confirmation sample results were above the Lead action level
of 800 mg/kg, the associated grid will be excavated an additional 6 inches and
re-sampled for Lead contamination. An
estimated 540 tons of excavated soil has been transported to Maloy Landfill
located at Campbell, TX. Air monitoring instruments were
deployed daily to monitor for particulates in the air during excavation
activities.
During
the period of 18 January – 23 January 2016, 7 grid excavations were completed
to a depth of 6 – 12 inches below ground surface; excavated grids are located
towards the center of the site. Eight confirmation samples were collected and shipped
to ALS Environmental Labs for analysis of Lead contamination and Hexavalent Chromium
contamination. Two of the seven samples
results were above the Lead action level of 800 mg/kg, the associated grids
will be excavated an additional 6 inches and re-sampled for Lead contamination.
All 7 confirmation samples were below the Hexavalent Chromium action level of 650 mg/kg. An estimated 850 tons of excavated soil has
been transported to Maloy Landfill. Air monitoring
instruments were deployed daily to monitor for particulates in the air during
excavation activities.
On
01/21/16, during the excavation of grid B07, a drum was discovered around 12
inches below ground surface. Excavation activities were stopped as directed by
EPA OSC. EPA will conduct a additional geophysical survey of the site now that structures/obstacles have been removed from the initial survey area.
To date, an estimated 1,700 tons of excavated soil has been transported of site to Maloy Landfill.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
The Site PRPs formed a steering committee, the Chemical Recycling Incorporated Steering Committee and has elected not to perform the Removal Action.
2.1.4 Progress Metrics
Disposal
metrics for the reporting period are below.
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
Non- Haz Lead |
Soil |
~540 tons |
1913085 - 1913111 |
None |
Maloy Landfill |
Non- Haz Lead |
Soil |
~1,160 tons |
1913112 - 1913115
2945011 - 2945039
|
None |
Maloy Landfill |
|
|
|
|
|
|
|