Stark Ceramics

All POL/SITREP's for this site Stark Ceramics
East Canton, OH - EPA Region V
POLREP #7
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Stark Ceramics - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V

Subject: POLREP #7
Stark Ceramics
C596
East Canton, OH
Latitude: 40.7799980 Longitude: -81.2960310


To:
From: Tricia Edwards, OSC
Date: 10/20/2014
Reporting Period: 10/4/2014 to 10/17/2014

1. Introduction
  1.1 Background
   
Site Number: C596    Contract Number:  
D.O. Number: 0148    Action Memo Date: 5/23/2014
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: EPA    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 7/14/2014    Start Date: 7/14/2014
Demob Date:      Completion Date:  
CERCLIS ID: OHN000510945    RCRIS ID:
ERNS No.:    State Notification: Yes
FPN#:    Reimbursable Account #:

1.1.1 Incident Category

CERCLA Incident Category:  Inactive Production Facility

1.1.2 Site Description

See POLREP #1

1.1.2.1 Location

See POLREP #1

1.1.2.2 Description of Threat

See POLREP #1

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

See POLREP #1


2. Current Activities
  2.1 Operations Section
    2.1.1 Narrative

For the period from October 4-17, 2014 EPA continued shipping of waste material off site.

2.1.2 Response Actions to Date

On Monday, October 6, 2014, no ACWM transported to the landfill for disposal today. ERRS crew continued the removal and relocation of non-friable ACWM from the east perimeter of the asbestos exclusion zone to the truck load-out area. ERRS continued load-out of hazardous solids from the Covered Shed. 8 loads (~200 tons) of hazardous solids was transported off site for treatment at the EQ Treatment Facility in Canton, Ohio. START continued perimeter air monitoring and air sampling around the perimeter of the asbestos exclusion zone. START continued air monitoring around the perimeter of the Covered Shed.

 

Tricia Edwards (US EPA OSC) and Ginny Narsete (UE EPA CIC) attended a City Council meeting to present the status of the removal activities on Site.

 

On Tuesday, October 7, 2014, 17 loads (~347 tons) of non-friable ACWM was transported off site for disposal at the American Landfill in Waynesburg, Ohio. ERRS continued load-out of hazardous solids from the Covered Shed. 8 loads (~207 tons) of hazardous solids was transported off site for treatment at the EQ Treatment Facility in Canton, Ohio. ERRS consolidated the color dye powders from the fiber drums into lined Gaylord boxes for subsequent transportation and disposal. START continued perimeter air monitoring and air sampling around the perimeter of the asbestos exclusion zone. START continued air monitoring around the perimeter of the Covered Shed.

 

On Wednesday, October 8, 2014, 16 loads (~328 tons) of non-friable ACWM was transported off site for disposal at the American Landfill in Waynesburg, Ohio. ERRS continued load-out of hazardous solids from the Covered Shed. 8 loads (~212 tons) of hazardous solids was transported off site for treatment at the EQ Treatment Facility in Canton, Ohio. START continued perimeter air monitoring and air sampling. Last day perimeter asbestos air samples were collected around the perimeter of the asbestos exclusion zone. START continued air monitoring around the perimeter of the Covered Shed.

 

On Thursday, October 9, 2014, 11 loads (~226 tons) of non-friable ACWM was transported off site for disposal at the American Landfill in Waynesburg, Ohio. Last load of ACWM was transported off site today. A total of 169 loads (~3,491 tons) of non-friable ACWM was transported off site for disposal . ERRS continued load-out of hazardous solids from the Covered Shed. 10 loads (~269 tons) of hazardous solids was transported off site for treatment at the EQ Treatment Facility in Canton, Ohio. Asbestos exclusion barrier tape and signage was removed. START began the final visual inspection of the former asbestos exclusion zone. START continued air monitoring around the perimeter of the Covered Shed. USCG personnel demobilized from Site today.

 

On Friday, October 10, 2014, no hazardous solids were transported to the landfill for disposal today.

ERRS prepared the site for extended holiday weekend. Demobilization for the Columbus Day Holiday.

 

No work scheduled for Saturday or Sunday.

 

On Monday, October 13, 2014. No work today. Columbus Day Holiday.

 

On Tuesday, October 14, 2014, the EPA, ERRS and START remobilized back to the Site from the Columbus Day Holiday. ERRS wetting and staging the hazardous solids in the Covered Shed for loading trucks tomorrow. ERRS loaded roll-off boxes with scrap metal generated during the asbestos removal activities.

 

On Wednesday, October 15, 2014, 10 loads (~273 tons) of hazardous solids was transported off site for treatment at the EQ Treatment Facility in Canton, Ohio. START collected bulk samples of suspect ACM within the partially demolished kiln building. START continued final visual inspection of the former asbestos exclusion zone and continued perimeter air monitoring around the Covered Shed.

 

On Thursday, October 16, 2014, 10 loads (~267 tons) of hazardous solids was transported off site for treatment at the EQ Treatment Facility in Canton, Ohio. ERRS processed scrap metal generated during the asbestos removal activities for subsequent recycling. ERRS conducted localized clean-up of suspect ACM within the partially demolished Kiln Building. START continued the final visual inspection of the former asbestos exclusion zone and continued perimeter air monitoring around the Covered Shed. A representative from the Canton City Health District arrived on site to conduct a site inspection.

 

On Friday, October 17, 2014, 8 loads (~216 tons) of hazardous solids was transported off site for treatment at the EQ Treatment Facility in Canton, Ohio. Three loads (~19 tons) of scrap metal were transported off site for recycling at the PSC Metals, Inc. facility in Canton, Ohio. Scrap metal transported off site for recycling. ERRS continued to demobilize equipment and resources from the Site that are no longer required. START continued the final visual inspection of the former asbestos exclusion zone and continued perimeter air monitoring and air sampling.



2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

The PRP has been identified and appropriate enforcement actiivities have been initiated by the local and State authorities.

2.1.4 Progress Metrics

Waste Stream Medium Quantity Manifest # Treatment Disposal
 ACWM  Solid  7,438.95 tons  2718108-2738037    Friable ACM
 ACWM  Solid  3,491 tons  NA    Non-friable ACM
 Hazardous Solids  Solid  1,740 tons    Stabilzation  Hazardous Solid
 Crushed Containers  Solid  60 yards / 7.2 tons  NA    Solid Waste
 Empty Propane Cylinders  Solid  39 Cylinders  NA  Recycle  AmeriGas


  2.2 Planning Section
    2.2.1 Anticipated Activities

2.2.1.1 Planned Response Activities

Remove remaining ACWM discovered during the ongoing visual inspection of the asbestos exclusion zone
Continue visual inspection of the asbestos exclusion zone
Properly dispose of hazardous materials contained in drums or other containers
Load, transport, and dispose of heavy metal contaminated material from Covered Shed

2.2.1.2 Next Steps

Final visual inspection of the ACWM area after removal activities completed
Heavy metal contaminated material is believed to be from old lagoons on site
Transportation and disposal of the lab-packed and over-packed containerized waste.


2.2.2 Issues




  2.3 Logistics Section
    The site is in a remote area and the nearest water source is over 1,200 feet away.   Additional hose was procurred in order for the site to have a constant supply of water.


  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    2.5.1 Safety Officer


Daily Safety meetings are being held before the start for all work shifts.


2.5.2 Liaison Officer

NA

2.5.3 Information Officer

A Community Involvement Coordinator has been assigned to the site.

3. Participating Entities
  3.1 Unified Command

3.2 Cooperating Agencies

Ohio EPA
Canton Health Department
Canton Fire Department

4. Personnel On Site
  1- EPA
9 - ERRS
1 - START

5. Definition of Terms
  No information available at this time.

6. Additional sources of information
  No information available at this time.

7. Situational Reference Materials
  No information available at this time.