Preliminary Assessment/ Site Investigation is completed.
Surface soil samples collected on 04 April, 2011.
Subsurface soil samples and ground water samples collected 17 and 18 May, 2011
Additional surface soils were collected on July 13, 2011.
Action Memo signed on 11 August, 2011 securing funds and defining the actions proposed to remedy the situation.
Exacavation began on 12 October, 2011 and was completed on 18 October, 2011.
Transportation and disposal of contaminated soils began on 19 December, 2011 and was completed on 20 December 2011.
All field activities completed on 21 December, 2011. All personnel and equipment were demobilized on 21December, 2011.