U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

J.H. Baxter - Time Critical Removal Action

 
Site Contact:
Randy Nattis
On Scene Coordinator

(nattis.randy@epa.gov)

Site Location:
85 Baxter St
Eugene, OR 97402
response.epa.gov/JHBaxter

Site updates

This operational update covers only Section 2—response actions and planning information. For all other static information, please refer to Operational Period #1 in the document section of this website.

 

 

Operational Period 4: October 5 –October 11, 2026
Excavation continued within Zone 3, with approximately 1,288 cubic yards of contaminated material removed during the reporting week, bringing the cumulative excavation total to approximately 2,485 cubic yards. Oil continued to seep from exposed soils and accumulate in extraction pits and pooled groundwater. Work included continued NAPL and impacted-groundwater recovery, backfilling of the northern portion of the excavation, and beginning demolition of the former Shop Annex to provide access to contaminated soils.

EPA

  • Continued oversight of excavation, material segregation, liquid recovery, and backfill activities within Zone 3.
  • Evaluated field conditions as excavation exposed continued oil seepage from excavation sidewalls and oil-saturated soils near the former Shop Annex and pump house.
  • Continued evaluating the extent of contamination around former fuel-transfer infrastructure. Field observations identified piping connecting the pump house and tank farm as a potential source of oil contamination.
  • Advanced removal activities into areas requiring demolition of the former Shop Annex to access contaminated soils beneath and adjacent to the structure.

 

ERRS

  • Excavated approximately 1,288 cubic yards of contaminated material within Zone 3, bringing the cumulative excavation total for the current removal effort to approximately 2,485 cubic yards.
  • Removed overlying material identified as clean soil before excavating underlying contaminated material.
  • Segregated and staged excavated soils according to contamination density. Expanded contaminated-soil staging capacity beneath the west drip-pad cover and continued using covered staging space within the west-side barn.
  • Continued recovering oil and impacted groundwater from extraction pits and pooled areas within the excavation.
  • Pumped approximately 3,500 gallons of impacted groundwater. Recovered liquids passed through an oil-water separator, with water routed to a weir tank for accumulation before transfer to onsite frac tanks.
  • Backfilled an existing test pit following oil-recovery efforts and excavated another test pit closer to the southern end of the excavation on October 8. Floating oil (NAPL) was identified.
  • Continued excavation near the Shop Annex and pump house, exposing a storm drain surrounded by oil-saturated soils.
  • Placed a demarcation barrier in a portion of the Zone 3 excavation in preparation for backfill. Began gravel backfilling in the northern portion of the excavation.
  • Began demolition of the former Shop Annex to provide access to contaminated soils. Demolition remained in progress.
  • Staged removed metal for recycling.

 

START

  • Conducted daily air monitoring for volatile organic compounds and particulates at AM03, AM07, AM08, AM10, and AM11.
  • Supported oversight of excavation and segregation of removed soils into appropriate waste streams.
  • Documented excavation progress, oil seepage, test-pit conditions, demolition, and backfill activities through photographic records and excavation mapping.
  • Updated excavation and water-management quantity logs.

 

USCG Pacific Strike Team

  • Two USCG personnel were reported onsite during the operational period. Specific activities were not detailed in the START weekly summary.

2.1.3 Progress Metrics



Materials Management

Operational Period 4

Cumulative*

Contaminated material excavated

1,288 cubic yards

2,485 cubic yards

Impacted water recovered and managed onsite

3,500 gallons

8,100 gallons

*Cumulative quantities reflect the excavation and water-recovery effort beginning in September 2026. Water quantities do not represent a separately measured volume of recovered NAPL.

Excavation and backfill by day

 

 

2.2 Planning Section

 

 

2.2.1 Anticipated Activities:
Operational Period 4: October 12–18, 2026

  • Continue excavation within Zone 3, adjusting excavation sequencing and backfill timing based on subsurface conditions and liquid-recovery needs.
  • Continue recovering NAPL and impacted groundwater from extraction pits and pooled areas, modifying recovery arrangements as excavation progresses.
  • Continue managing recovered liquids through the oil-water separator and onsite tank system.
  • Begin collecting water samples from the extraction pits and soil samples along excavation boundaries.
  • Begin air sampling within the material-storage and soil-stockpile areas, within the excavation area, and along the site fence-line perimeter.
  • Continue Shop Annex demolition as needed to provide access to contaminated soils beneath and adjacent to the structure.
  • Evaluate exposed drainage and former fuel-transfer piping to guide excavation and management of associated contaminated material.
  • Continue placing demarcation barriers and backfilling selected excavated areas.
  • Continue managing contaminated-soil staging capacity and segregating materials into appropriate waste streams.
  • Continue routine air monitoring and field documentation to support excavation and material-management decisions.

 

2.2.2 Next Steps / Long-Term Planning

EPA will evaluate continued NAPL accumulation and groundwater recovery to determine whether additional or modified recovery systems are warranted during the removal action. Excavation observations will inform excavation limits and management of contaminated material around former structures, drainage features, and fuel-transfer piping.

 

EPA will direct test pits throughout the west size of zone 3 to identify contaminated soils and evaluate groundwater and NAPL impacts.

 




A Map is available for viewing GIS information.