U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Minnesota Power Discharge

 
Site Contact:
David Morrison
On-Scene Coordinator

(Morrison.David@epa.gov)

Site Location:
1210 NW 3rd Street
Cohasset, MN 55721
response.epa.gov/MNPower
NRC#: 1404933

July 19-21, 2024: Site Updates

MN Power updated the estimated release volume from approximately 1 million gallons of coal residual slurry water to approximately 5.4 million gallons.

A review and shovel test were performed by an archeological team of the proposed excavation site. Results were reviewed by MP, MPCA, LLBO, and the MN Historical Society and determined excavation would produce no adverse effects. Excavation of source-area soils began Saturday, July 20.

Excavation of the affected soil, subdivided into four zones, zone one being closest to the point of discharge, fanning out along the discharge path towards the edge of Blackwater Creek. Excavation began at zone three working inwards toward zone one. Affected material was excavated down to about six feet below ground surface. Conductivity readings of the soil were intermittently sampled and compared to a baseline sample taken away from the affected area to assess the condition of affected soil.

As of Sunday, July 22, about 256 tons of material was removed from the excavation site.

Water monitoring and sampling efforts continued. Preliminary results of samples taken in Blackwater creek water showed an elevated concentration for sulfate. A sulfate analyzer instrument was requested to provide more immediate concentration levels in the creek.

An ecological survey of the Blackwater Creek was conducted by Barr Industries to assess the condition of the wild rice beds.

July 18, 2024: Site Update

EPA received the first preliminary analytical results for surface water sampling. Preliminary data did not indicate concerns with metals with the exception of elevated boron. Elevated sulfates were found at the point of discharge and diminished further away from the discharge point.

EPA met with representatives from the Leech Lake Tribe to view the potential excavation area to remove affected soils from the spill. A cultural/historical/archeological review is currently underway to determine whether an adverse effect from the excavation is possible. Once the review is complete, EPA and MPCA will work with the Tribe to determine next steps.

July 17, 2024: Site Update

EPA continues to work with the MPCA, the Leech Lake Band of Ojibwe, U.S. Fish and Wildlife Service, Minnesota Department of Natural Resources, U.S. Department of the Interior, and MN Power on response efforts. MN Power continues to conduct surface water monitoring and sampling with EPA and MPCA oversight. EPA is still waiting for sample results to determine next steps for in-water mitigation if needed. Source area mitigation efforts include on-going slurry water collection which has been augmented with additional recovery pits for groundwater collection and planned soil removal.  Protection boom has been placed near the discharge area to prevent Blackwater Creek flow from disturbing potentially contaminated areas until sampling results are received.

 

EPA issued a Notice of Federal Interest to MN Power under the agency’s Superfund and Clean Water Act authorities.

 

July 16, 2024: Site Update
On Tuesday, July 16, Minnesota Power determined that approximately 1 million gallons of coal residual slurry water (otherwise called supernate), from a discontinued coal ash slurry pond was discharged from a return-water reuse pipeline over several days. The discharge flowed overland into the backwaters of Blackwater Creek which feeds into Blackwater Lake, a backwater lake of the Mississippi River near Cohasset. This area is nearby and downstream of the Leech Lake Band of Ojibwe Reservation and within the 1855 Treaty Rights Area.

EPA arrived at the site to begin coordinating with the Minnesota Pollution Control Agency (MPCA), the Leech Lake Band of Ojibwe, the U.S. Fish and Wildlife Service, U.S. DOI, and MN Power. On July 16, all recoverable material from the spill area and pipeline back-drain was collected. Surface water samples were collected to be analyzed for contaminants of concern such as sulfides, metals, total suspended solids, chloride and carbonaceous biochemical oxygen demand, or CBOD.

MN Power installed an earthen berm to contain slurry water near the leak and will recover water that will be sent back to the plant systems. MN Power also installed silt fencing further down the slope to retain any solids as well as installed a line of floating boom across the creek just downstream of the release where it empties into Blackwater Lake.

MN Power will conduct water quality monitoring and sampling with EPA and MPCA oversight. EPA and MPCA are working on a sampling and analyses plan for the incident and reviewed previous analyses of the slurry water. EPA has identified wild rice areas throughout the system and downstream. Mitigation needs will be reassessed as more data is available.

MN Power will continue to conduct hourly visual inspections of the area for any signs of stressed vegetation or wildlife or unusual water quality.