Notice of Shipment
The EPA site team will be shipping the solidified TENORM contaminated solids beginning 6/23/2026 through 6/25/2026. Trucks carrying this waste will be following an approved trucking route, and will be properly placarded and labeled. Community members may noticed increased truck traffic, with a yellow class 7 radioactive materials placard during this time. The site team takes great care to ensure that these loads are handled properly and safely.
Site Update: Week of 6/8/26
EPA and its contractors are continuing
cleanup work at the Fairmont Brine site. Recent work includes:
- Drying sludges that
were partially amended with a drying agent in Fall of 2025 and staged
on-site in 9.5 cubic yard bags. Sludges were amended with a
milled perlite product for additional drying prior to
re-packaging for disposal
- All dried materials are placed
in a 9.5 cubic yard bag and staged on-site for disposal. Materials are
staged in a labeled radioactive materials area.
- To date, 101 bags of
material have been packaged totaling
approximately 639 tons.
- All sludge material from the
frac tanks, concrete basin, and the fire damaged tank have now been dried
and packaged for disposal.
- Disposal of staged material is
scheduled to occur between June and July 2026.
- Frac tanks are being cut
on-site into shippable sizes.
- Frac tank pieces will be
screened for radiation and free released if able to do so. Frac tank
pieces that cannot be decontaminated will be shipped off-site as
radiologically contaminated debris.
Perimeter and work zone air monitoring for
dust and radiation is on-going during site operations. No exceedances have
been observed to date. Total waste handled under the current Action
Memorandum can be found in the table below:
|
Waste Stream
|
Waste Quantity Shipped
|
Estimated Waste Remaining On-Site
|
|
TENORM Solids
|
331 tons
|
500 tons
|
|
RCRA + TENORM Liquids
|
46,200 gallons
|
0 gallons
|
|
TENORM Liquids
|
72,179 gallons
|
0 gallons
|
|
Drum Waste
(DOT/RCRA Corrosive & Non-Corrosive
Materials)
|
2,000 lbs
|
0 lbs
|
|
Decontamination Water (Generated through
on-site operations)
|
16,500 gallons
|
NA
|
|
TENORM Contaminated Debris over 50
pCi/g
|
33.39 tons
|
>10 tons
|
Waste stream descriptions:
- TENORM Solids – material such
as contaminated soil, filter cake, and dried sludges
- RCRA + TENORM liquids – liquids
that exhibited RCRA hazardous waste characteristics and had elevated
levels of TENORM. (Liquids within the frac tanks)
- TENORM liquids – Liquids that
did not exhibit RCRA characteristics but contained elevated
TENORM.
- Drum wastes – drums of
chemicals left onsite from prior operations
- Decontamination water – water
generated and collected from decontamination operations
- TENORM contaminated debris over
50 pCi/g – site debris (trash, piping, wood, plastic sheeting etc)
that was contaminated and had a concentration of TENORM over 50
pCi/g.
Previous site updates have
been archived and made publicly available under the “Documents” tab. The most
recent document can be found here: Archived Site Updates 6/11/2026.
Monthly Community Call
EPA and our state and local partners host a community
call the 2nd Wednesday of each month at 2 pm. The community
calls are open to the public. Please submit any questions or comments to Angela
Ithier and John
Brakeall by 5 pm on the 2nd Monday of each month. The
call will be canceled if EPA does not receive any questions or comments. Ground rules (PDF) for the calls can be viewed online.
Calls for the remainder of the 2026 calendar year:
- Wednesday, July 8, 2026
- Wednesday, August 12, 2026
- Wednesday, September 9, 2026
- Wednesday, October 14, 2026
- Wednesday, November 18, 2026 (3rd Wednesday because of Veterans Day holiday)
- Wednesday, December 9, 2026
Join using Microsoft Teams
Call-in option:
- Dial: (202) 991-0477
- Enter conference ID: 157 924 883#
Fairmont Brine Community Involvement Plan (CIP)
EPA has finalized a Community Involvement Plan (PDF) for the site. The CIP describes how EPA will involve the community and address local needs during the Superfund removal process. EPA and the community will work together by using the tools described in this plan.
Active public involvement is crucial to the success of any project. EPA’s community involvement activities at the site are designed to inform the public of all cleanup activities and include the community in the decision-making process.
Click here to review the CIP.
Site
Overview:
The Fairmont Brine site is located at 168 AFR
Drive in Fairmont, West Virginia. The Brine processing facility was constructed
between 2009 and 2010 by the AOP Clearwater LLC. The plant was acquired
by Fairmont Brine Processing (FBP) in 2012. FBP began pre-treatment
operations at the site in 2013 and fully
operated the plant in fall of 2014. FBP ceased operations at the
site in March 2018.
The plant accepted flowback and produced fluids , known as "Brine" from the
hydraulic fracturing process used to extract natural gas. FBP used chemical and carbon filter media,
multiple-effect evaporation, and crystallization to treat and process the brine
they received. This produced sodium chloride, calcium chloride, and distilled
water. By-products created from the process include sludge
and filter cake material. Produced fluids from fracking operations
can contain Technically Enhanced Naturally Occurring Radioactive Materials,
known as "TENORM". Click
here to learn more about TENORM.
On May 30, 2023, there was a fire and subsequent explosion
at the site damaging an above ground storage tank and the upper process
building. Following the fire, elevated readings of TENORM radiation were
found in several areas of the site. Click here
for general information about radiation sources and doses.