Walsenburg Asbestos Site

Notices

All Notices [5] rss feed
Categories
Notices  Posted Category
Site Description 3/21/2022 01 Background

 

In August 2018, the City of Walsenburg condemned the residential structure located on Walsen Avenue, Walsenburg, Huerfano County, Colorado (the Site). In September 2018, the structure burned, and portions of the building collapsed. The structure is in a state of severe disrepair due to weathering, a collapsing roof, and missing walls and windows. In March 2019, the City of Walsenburg conducted an evaluation of the Site and determined that the burned structure contained friable asbestos.

On August 3, 2020, the City of Walsenburg and the Colorado Department of Public Health and Environment (CDPHE) contacted the EPA Region 8 Response Program requesting assistance in performing a removal action at the Site. The City of Walsenburg provided the EPA with sampling data, where asbestos (chrysotile) concentrations were measured at concentrations as high as 6 percent.

Based on the OSC’s evaluation of the crumbling building materials and the missing walls and windows, there has been a release of friable asbestos to the environment from the ACM at the Site. The property is in a residential neighborhood with other residences located in close proximity. There are continued incidents of trespassing and adequate barriers are not in place to prevent children or other persons from accessing the Site.  The hazardous materials inspector documented a couple of incidences evidence of trespassing and vandalism in August 2018.

Weather events including wind, rain, and snow will continue to degrade the remaining portions of the structure. This will cause asbestos fibers to continue to be released from the ACM as the material weathers and become friable due to ongoing exposure to the elements. Hence, asbestos fibers may migrate off-Site and pose an asbestos inhalation threat to nearby residents and community members.



Response Objectives 3/21/2022 02 8-15 April 2022

1. Mobilized to the site

2. Keep stakeholders informed.

3. Demolish structure while maintaining control of asbestos on site

4. Properly dispose of asbestos material while maintaining control of asbestos

5. Restore site to grade

6. De-mobilize from site



Response Operations 3/21/2022 02 8-15 April 2022

On 4/8/2022 EPA and ERRS crews mobilized to the site with all the equipment. On 4/9/2022 the property was completely demolished and broken up in small enough pieces while maintaining control of asbestos, to haul to an asbestos approved landfill. This website was developed to keep stake holders and the public informed of this project. 

Six truckloads (approx. 150 cubic yards) of waste was hauled to the landfill on 4/11/2022.

No work was accomplished on 4/12/2022 because if high winds.

Ten truckloads (approx. 250 cubic yards) of waste was hauled to the landfill on 4/13/2022.

Eight truckloads (overall total of 565 cubic yards) of waste was hauled to the landfill on 4/14/2022. Completed removing asbestos waste and hauled it all to approved landfill.

Backfill was started and completed on 4/15/22. Grading was completed on 4/15/22.

EPA and contractors de-mobilized from site on 4/15/22.

 



Planned Activities 3/21/2022 02 8-15 April 2022

Continuing trucking and disposal of the asbestos in the landfill. Completed 4/14/22.

Once asbestos is removed the site will be backed filled and graded. Completed 4/15/22.

EPA and ERRS will de-mobilize from the site once work is complete. Completed 4/15/22.

No new planned activities.



Safety Issues 3/21/2022 02 8-15 April 2022

Active overhead power lines and communication cables near site. Plan to keep close communication with excavator operator to avoid lines. Property demolished without incident.