Posted
Category
Site Description
5/25/2022
00 Background
The Crow Agency Tribal Office building (Site) consists of a single-level building of approximately 30,000 square feet that was built in five separate sections from the 1930s to 1970s. The main branch wing of the office building suffered a fire in 2019 which led to the entire office space being vacated. The office space lies in the center proper of the Crow Agency township and is surrounded by residential homes. The tribe made a request for EPA assistance for building demolition and removal of ACM and non-ACM building debris and waste.
Removal Objectives
5/24/2022
00 Background
The EPA Removal Program is conducting a CERCLA cleanup to protect human health and the environment at the Crow Agency Reservation. The main objectives consist of the following:
Demolition of the main office wing containing Asbestos Containing Material (ACM) and transportation to a landfill in Miles City for proper disposal.
Remove any residual ACM in separate wings of office space. ACM-contaminated debris will be transported and disposed at the Miles City landfill.
Demolition of remaining building wings not containing ACM and transportation to a C & D landfill for disposal.
Maintain safety for working crews and local residents by properly securing area and using best engineering practices to control ACM, noise and any potential airborne dust.
Operational Goals
5/28/2022
01 May 23 - 28
Proposed weekly activities from 5/23 - 5/28/22 include the following:
Equipment, resources, and personnel mobilization and set up,
Coordinate w/local tribal contacts to secure electricity, water, blue-stake, night and Sunday security, and awareness to tribal residents on the commencement of activities,
Coordinate w/transportation subcontractors to secure roll-off containers and drivers,
Set up and secure perimeter zones including exclusion zones beginning with primary ACM building, and dental wing of office space,
Air monitoring station set-up along perimeter of demolition activities. First 3-4 days, collect background data prior to the onset of the removal action,
Begin identification & removal of dental wing ceiling tile ACM, proper cleaning of inside area,
Commence demolition on the primary burned out portion of the office building containing ACM. Proper segregation of larger pieces of metal material for later decon & recycling. Segregation of all other ACM for load out activities to begin on 5/31/22.
Operational Accomplishments
5/28/2022
01 May 23 - 28
Accomplishments for Operational period 5/23 - 5/28/22 are highlighted below:
All equipment, resources and personnel present and accounted for. One large excavator delivered w/malfunctioning thumb. Technician will be on-site to make repairs. This is not affecting operations at this time,
All local utilities secured including further advisement on the commencement of activities to area residents,
Transportation drivers secured. Roll off boxes lacking 3 containers,
Site perimeter secured including exclusion zones. Night watchmen also secured by the Tribe,
Air monitoring stations all functioning normally
Dental wing ceiling tile removal and segregation underway,
Demolition activities on primary burned out building commenced late afternoon 5/27.
Operational Goals
5/30/2022
02 May 30 - June 4
Proposed weekly activities comprise the following for May 30 - June 4, 2022:
Continue work on north dental wing, remove ceiling tile & debris, hepa-vac carpets for segregation purposes,
Begin demolition on dental wing later in week in preparation for C & D waste transport,
Secure proper liners for roll off containers,
Continue demolition on main burned out office space containing ACM waste, separation of metal for decon and recycling,
Begin load out of ACM waste into roll off containers for transport to landfill,
Continue coordination w/tribal officials and local residential outreach.
Operational Accomplishments 5/30 - 6/4/22
6/6/2022
May 30 - June 4, 2022
Accomplishments for operational period 5/30 - 6/4/22
North Dental wing demolition complete. Debris and metal pile separation.
Demolition on the main burned out west wing of building containing ACM continues. Debris piles of construction material staged for load out. Metal debris separated, cleaned and staged.
Total number of roll offs (ACM) taken to landfill (13) consisting approx. 150 tons total.
East Wing building ACM marked and located for removal & cleanup. Task completed and ACM removed and staged in main ACM debris pile.
Continue coordination w/tribal officials and local residential outreach.
Operational Goals June 6 - June 11, 2022
6/6/2022
June 6 - June 11, 2022
Proposed weekly activities comprise the following for June 6 - June 11, 2022:
Continue demolition along north-east portion of building containing C & D debris waste. Separation of metal material will continue for recycling.
Break up cement foundation/footings/walls in basement area (Dental wing).
Secure local transport of C & D contractor to Hardin landfill.
Continue demolition on main burnt out office space containing ACM waste, separation and decon of metal for recycling. Load out will continue weather permitting
Continue with air monitoring along perimeter of construction area & personal sampling of individuals in exclusion zones.
On-going coordination w/tribal officials and local residential outreach.
Operational Accomplishments June 6 - June 11, 2022
6/11/2022
Site Update
Accomplishments for operational period 6/6 - 6/11/22
Demolition along north-east portion of building containing C & D debris waste completed on 6/9/22. Separation of metal will continue for recycling.
Break up cement foundation/footings/walls in basement area (Dental wing) continues as needed & as debris is loaded out.
Republic local transport of C & D waste secured and transport to Hardin landfill commenced on 6/9/22. Total tonnage removed in two days 145.12 tons.
Demolition continues on main burnt out office space (east wing) containing ACM waste, separation of metal & waste material. Load out begin late in week due to Miles City landfill closed from inclement weather. Total tonnage removed for the week (only two days) is 133.25 tons.
Continue with air monitoring along perimeter of construction area & personal sampling of individuals in exclusion zones. Results loaded to OSC website.
On-going coordination w/tribal officials and local residential outreach.
Secured contract w/Republic to remove & recycle metals on site.
Secured Ingraham transporter of ACM waste to Miles City. Transportation begins on Monday 6/13/22.
Operational Accomplishments June 13-June 18, 2022
6/16/2022
Site Update
Accomplishments for operational period 6/13 - 6/18/22
Demolition of walls and roof of East Addition (all C&D waste).
Load-out of ACM waste was conducted on Monday-Friday by MP Environmental and Ingraham trucking. Miles City landfill accepts a maximum of 6 loads per day. Loads are typically 15 tons each or slightly higher.
Load-out of C&D waste was conducted by Republic trucking, with waste delivered to the nearby Hardin landfill.
Air monitoring data was reviewed by the OSC, who determined that dust suppression activities were effective. Real-time air monitoring was ended and visual methods will be used for the remainder of on-site work.
A sufficient quantity of representative data was obtained for air sampling on personnel inside the exclusion zone. Air sampling for personnel was concluded.
Operational Goals June 20 to June 25, 2022
6/16/2022
Operational Goals 6/20-6/25
Proposed weekly activities comprise the following for June 20 - June 25, 2022:
Continue load-out of ACM
Continue load-out of C&D
Begin load-out of metal for recycling
Determine if Republic may haul a limited number of ACM loads to Hardin landfill
Evaluate potential sources of backfill material, secure & sample for later use
Secure transportation vendor for recycling of metal material
Operational Accomplishments June 20 - 25, 2022
6/25/2022
Site Update
Accomplishments for operational period 6/20 - 6/25/22
Break up of cement basement floor & walls,
Separation & consolidation of metal debris for recycling,
Load out of C&D material total 128 tons,
Load out of ACM debris total 374 tons,
Secured backfill vendor for next week delivery,
Secured pick up of metal debris for next week pick up
Operational Goals for week June 27 - July 1, 2022
6/25/2022
Site Update
Proposed weekly activities comprise the following activities:
Continue load out & transport of ACM and C&D waste debris,
Begin load out of metal for transport & recycling,
Begin transport of backfill material to site for placement & grading,
Continue break up of cement walls and basement floor slabs.
Operational Accomplishments July 5 - July 9, 2022
7/8/2022
Site Update
Accomplishments operational period July 5 - July 9, 2022
Continue filling bins with ACM waste and transportation to landfill;
Continue filling bins with C&D waste material and transportation to landfill;
Transportation of metal to recycling vendor
Initiated backfilling basements with clean fill.
Operational Accomplishments July 11-16, 2022
7/18/2022
Site Update
Accomplishments operational period July 11-16, 2022
Completed filling bins with ACM waste. Transportation of bins to landfill should be complete week of July 18, 2022.
Completed filling bins with C&D waste material. Transportation of bins to landfill should be complete week of July 18, 2022.
Completed removal of metal for recycling.
Continued backfilling basements with clean fill.