Loading of debris containing ACM for transportation and disposal continued on June 25, June 26, and was completed on June 27, 2024. As of June 27, 2024 a total of 1,300 cubic yards of ACM has been moved off site.
Backfill activities were conducted on June 27, June 28, and were completed on June 29, 2024.
EPA communicated with City officials on June 29 regarding the completion of field activities and the reopening of 3rd Street in the vicinity of the former Delta Cleaners property.