EPA, Emergency and Rapid Response Services (ERRS)
contractors, and Superfund Technical Assessment and Response Team (START)
contractors mobilized to the Site on Monday, September 21, 2026.
Activities completed during the week of 9/21/2026 include
the following:
- Conducted
oversight on ongoing removal activities, documenting progress with site
photos and field documentation.
- Conducted
daily air sampling for asbestos and air monitoring for particulates at
four locations around the site perimeter.
- Received
and staged equipment and supplies needed for completion of removal
activities.
- Removed
the wrought iron fence and Antiques signage from the north and west side
of the site. Removed fencing and signage given to the Huerfano County staff.
- Conducted
vegetation management, cutting back overgrown vegetation around the site.
- Disconnected
fire damaged communication lines from the site, after conversations with
Century Link.
- Began
demolition of on-site structures.
- Began
to stockpile material for future loadout and transportation/disposal.
- Began
transportation/disposal of asbestos containing material in an approved off
site landfill.
- 8 trucks containing approximately 25 cubic yards of material each were hauled off site
for disposal during the week.
- 200 total cubic yards of Asbestos containing material disposed of so far.
Planned activities during the week of 9/28/2026 include
the following:
- Continue
conducting oversight on ongoing removal activities, documenting progress
with site photos and field documentation.
- Continue
conducting daily air sampling for asbestos and air monitoring for
particulates at four locations around the site perimeter.
- Continue to stockpile
material for future loadout and transportation/disposal.
- Continue
transportation/disposal of asbestos containing material in an approved off
site landfill.