Ecusta Mill

Notices

All Notices [19] rss feed
Categories
Notices  Posted Category
Demolition and Remedial Progress Report for 4/13 to 4/17/09 4/23/2009
• Shaw and DH Griffin cleared buildings 64,86 and 110 for demolition.
• DH Griffin shipped scrap metal to DH Griffins Greensboro office for recycling.
• DH Griffin continued shipping non hazardous materials to Republic Landfill. Fly ash loadout was completed.
• DH Griffin continued shipping lead impacted brick and concrete to Republic Landfill.
• DH Griffin shipped construction debris to WCA Landfill for disposal.
• DH Griffin continued demolition of buildings 43,62,64,86,110.
• DH Griffin continued crushing operations in the north and south ends of the site.
• DH Griffin continued demolition of building slabs 11,15,51.
• DH Griffin continued perimeter dust monitoring.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw collected samples from crush material for lead analysis. Analytical results are all
below regulatory guidelines.
• Shaw performed daily monitoring of building 89 soil stockpiles. The highest PID readings were 10.2 ppm for the week.
*TN continue oversite duties for EPA.


Demolition and Remedial Progress Report for 4/6 to 4/10/09 4/16/2009
• Shaw continued sampling crushed concrete/brick debris.
• DH Griffin shipped 36 loads of scrap metal weighing 858 tons to DH Griffins Greensboro office for recycling.
• DH Griffin continued shipping non hazardous materials (fly ash) to Republic Landfill, 23 loads weighing 453 tons were shipped.
• DH Griffin continued demolition of buildings 15,43,62.
• DH Griffin continued crushing operations in the north and south ends of the site.
• DH Griffin continued demolition of building slabs 11,15.
• DH Griffin continued perimeter dust monitoring. No dust issues or exceedences were noted.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw collected samples from crush material for lead analysis. Analytical results are all below regulatory guidelines.
• JD Galloway excavated the PAH hot spot locations at building 75 and 106. Shaw collected samples from the excavated areas which included the east wall of 75 and all
four walls of the hotspot at 106.
• Shaw performed daily monitoring of building 89 soil stockpiles. The highest PID readings were 23 ppm for the week.
*TN continue oversite and Polrep prep for EPA


Demolition and Remedial Progress Report for 3/30 to 4/3/09 4/13/2009
• Shaw continued sampling crushed concrete/brick debris.
• DH Griffin shipped 47 loads of scrap metal weighing 815 tons to DH Griffins Greensboro office for recycling.
• DH Griffin continued shipping non hazardous materials (fly ash) to Republic Landfill, 38 loads weighing 754 tons were shipped.
• DH Griffin continued shipping lead impacted brick to Republic landfill, one load weighing 18 tons were shipped.
• DH Griffin continued demolition of buildings 15,31,51.
• DH Griffin continued crushing operations in the north and south ends of the site.
• DH Griffin continued demolition of building slabs 73.
• DH Griffin continued perimeter dust monitoring. No dust issues or exceedences were noted.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slab 63, XRF results were above regulatory guidelines for 2 of the 5 grab locations for arsenic.
• Shaw collected samples from crush material for lead analysis. Analytical results are all below regulatory guidelines.
• JD Galloway excavated the PAH hot spot locations at building 75 and 106. Shaw collected samples from the excavated areas which included the east wall of 75 and all
four walls of the hotspot at 106.
• Shaw collected groundwater samples from MW 11 for volatile organics at the request of the EPA. MW 11 is in close proximity to the building 27 vault impacted soil. Results were ND.
• Shaw collected samples from the wooden block floor from the machine shop (building 31) for volatiles and PCB’s.
• Shaw collected transducer data from the monitoring wells in the caustic area.
• Shaw performed daily monitoring of building 89 soil stockpiles. The highest PID readings were 23 ppm for the week.
• Shaw continued to complete the Draft Rifle Range report, the Draft Olin Area report, and the Technical meme for on-site arsenic soil management for NCDENR Brownfields.
• Shaw continued cost evaluations of on-site water treatment options.
*TN continue oversite duties for EPA.


Demolition and Remedial Progress Report for 3/23 to 3/27/09 4/2/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw continued the building clearance process. Towers 10,45,60,61 and stack 62 were cleared for demolition.
• DH Griffin shipped 42 loads of scrap metal weighing 640 tons to DH Griffins Greensboro office for recycling.
• DH Griffin continued shipping non hazardous materials (fly ash & carbon) to Republic Landfill, 44 loads weighing 795 tons were shipped. Carbon loadout complete.
• DH Griffin continued shipping lead impacted brick to Republic landfill, 21 loads weighing 350 tons were shipped.
• DH Griffin continued demolition of buildings 15,31,51,62.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of building slabs 73.
• DH Griffin continued perimeter dust monitoring. No dust issues or exceedences were noted.
• JD Galloway shipped starch from AST’s 295 and 296 to Republic Landfill, 9 loads weighing approximately 142 tons were shipped.
• Mountain Environmental removed residual black liquor from tower 61 cone.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slab 73, XRF results were below regulatory guidelines.
• Shaw collected samples from crush material for lead analysis. Analytical results are all below regulatory guidelines.
• Shaw collected 26 samples from the perimeter of the buffer zone in building 56 and the control room on the south end of building 58. Samples were from several different matrices including pipe insulation, paint chip, wood, brick and concrete. Samples were analyzed for total mercury and analytical results are pending.
• Shaw performed daily monitoring of building 89 soil stockpiles. Elevated PID readings were recorded above the bldg 27 stockpile on warmer days.


Demolition and Remedial Progress Report for 3/16 to 3/20/09 3/26/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw continued the building clearance process. Buildings 19 and 49 were cleared for demolition.
• DH Griffin shipped 43 loads of scrap metal weighing 680 tons to DH Griffins Greensboro office for recycling.
• DH Griffin continued demolition of buildings 15,31,51,62.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of building slabs 60,73,87.
• DH Griffin continued perimeter dust monitoring. No dust issues or exceedences were noted.
• DH Griffin completed removing carbon from building 15 using a vacuum truck. Carbon is staged for disposal behind building 15.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slab 60.
• Shaw collected samples from crush material for lead analysis. Analytical results are all below regulatory guidelines.
• Shaw collected and analyzed samples from the mercury spill at bldg 15. Samples failed on site XRF analysis. Impacted soil was excavated ( ½ cu/yd) and post excavation
samples were collected. Post excavation samples passed regulatory guidelines.
• Shaw excavated hot spot soil from buildings slabs 27, 75 and 106. Samples were sent for laboratory analysis for PAH’s in slabs 75 and 106. Slab 106 also had a lead hot spot which passed XRF analysis for lead. The concrete vault and impacted soil immediately surrounding it at slab 27 was removed. Approximately 238 gallons of vault liquids were also removed and disposed. Seven test pits were excavated around the vault to try to delineate impacted soil. Additional investigation will be required to determine impacted soil quantities.





Demolition and Remedial Progress Report for 3/9 to 3/13/09 3/23/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw’s structural engineer performed a survey of the EC building to aide demolition planning.
• Shaw continued the building clearance process. Building 31 site clearance walk was completed and clearance requirements were identified.
• DH Griffin shipped 37 loads of scrap metal weighing 559 tons to DH Griffins Greensboro office for recycling.
• DH Griffin shipped 12 loads of construction debris weighing 214 tons to WCA Landfill for disposal.
• DH Griffin continued demolition of buildings 51, 60, 62. Lead brick is being stripped and separated from the ground floor.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of building slabs 16, 60, 87.
• DH Griffin continued perimeter dust monitoring. No dust issues or exceedences were noted.
• DH Griffin began removing carbon from building 15 using a vacuum truck. Carbon is staged for disposal behind building 15.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slabs 75, 87.
• Shaw collected samples from crush material for lead analysis. Analytical results are all below regulatory guidelines.
• Shaw collected samples from soil adjacent to the mercury spill at building 15.
• Mountain Environmental cleaned up the mercury spill in the SW corner of the second floor of building 15. Approximately 5 oz was collected, <1 oz noted in spill area the remaining mercury was recovered from a flow switch.


Demolition and Remedial Progress Report for 3/2 to 3/6/09 3/12/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw performed a field survey of the coal yard to determine capacity for cellophane soil placement.
• DH Griffin shipped 32 loads of scrap metal weighing 565 tons to DH Griffins Greensboro office for recycling.
• DH Griffin began shipping lead impacted brick to Republic landfill, 2 loads weighing 35 tons were shipped.
• DH Griffin continued demolition of buildings 60,62.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of building slabs 16,20,87,88.
• DH Griffin continued removing utilities behind building 62.
• DH Griffin continued perimeter dust monitoring. No dust issues or exceedences were noted.
• Mountain Environmental completed removing weak liquor from building 56 chests and transferring to the clarifier. A total of 28 loads have been removed and placed into the
clarifier. Approximately 84,000 gallons of weak liquor were transferred.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slabs 75,87.
• Shaw collected samples from crush material for lead analysis. Analytical results are all
below regulatory guidelines.
• Shaw completed slug testing and the step drawdown test in the caustic area.


Demolition and Remedial Progress Report for 2/23 to 2/28/09 3/12/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw continued the building clearance process. Building 11 was cleared for demolition.
• DH Griffin shipped 42 loads of scrap metal weighing 662 tons to DH Griffins Greensboro office for recycling.
• DH Griffin continued shipping lead impacted brick to Republic landfill, 17 loads weighing 280 tons were shipped.
• DH Griffin continued demolition of buildings 11,62.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of building slabs 38,87.
• DH Griffin continued removing utilities behind building 62.
• DH Griffin continued perimeter dust monitoring. No dust issues or exceedences were noted.
• Kessel Engineer continued oversight of the geotechnical operations for fill being placed in reservoirs 47 and 54.
• Kessel Engineering completed collecting geotechnical boring samples.
• Mountain Environmental continued removing weak liquor from building 56 chests and transferring to the clarifier. Approximately 24 loads have been removed totaling 72,000
gallons of weak liquor. Approximately 18,000 gallons remain.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slabs 68,88.
• Shaw finished collecting environmental samples from Kessel Engineering geotechnical borings. Four boring locations had arsenic levels above RG’s. Three borings also had PID readings above 5ppm. Samples from these three locations were sent to the laboratory VOC and PAH analysis.
• Shaw collected samples from crush material for lead analysis. Analytical results are all below RG’s.
• DH Griffin alerted Shaw to a an area below reservoir 38 with strong organic odors. PID readings were noted in excess of 50 ppm. Samples were collected and sent to the
laboratory for VOC’s and PAH’s. Results indicated that soil in the area of concern is below RG’s.







Demolition and Remedial Progress Report for 2/16 to 2/21/09 2/26/2009
• Shaw continued sampling crushed concrete/brick debris. Results from last weeks
sampling showed no elevated lead impacts in the debris stream.
• Shaw continued the building clearance process. Building 43 was cleared for demolition.
• DH Griffin (DARI) shipped 2 truckload of asbestos to Charlotte Motor Speedway
Landfill totaling 20.5 tons.
• DH Griffin shipped 42 loads of scrap metal weighing 659 tons to DH Griffins
Greensboro office for recycling.
• DH Griffin shipped 32 loads of construction debris weighing 613 tons to WCA Landfill
for disposal.
• DH Griffin began shipping lead impacted brick from buildings 15 and 33 to Republic
landfill, 23 loads weighing 366 tons were shipped.
• DH Griffin continued demolition of buildings 15,62,73.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of building slabs 68,87,88.
• DH Griffin continued removing utilities between building 87 and 88.
• DH Griffin continued perimeter dust monitoring. No dust issues were noted for the
week.
• Kessel Engineer continued oversight of the geotechnical operations for fill being placed
in reservoir 54.
• Kessel Engineering began collecting geotechnical boring samples. Shaw will provide
oversight and locate each of the twelve borings with a GPS.
• Mountain Environmental continued removing weak liquor from building 56 chests and
transferring to the clarifier. Approximately 20 loads have been transferred to the clarifier
totaling 50-60,000 gallons. The task appears 50% completed.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slabs 68,88.
• Shaw completed collecting sediment samples in the EC building trenches
• Shaw collected environmental samples while overseeing the Kessel Engineering
geotechnical borings (6,7,9,10,11,12). When ample volume is available samples are
analyzed for metals using XRF analysis. Three samples from GT-10 exceeded RG’s for
arsenic (25,37,46 ppm). Boring locations 10 and 12 had PID readings in excess of 5ppm
and were sent for laboratory analysis (VOC’s and PAH’s).
• Shaw collected two samples from crush material for lead analysis.
• Shaw completed preparations’ (driller, Frac tank, pumps) to conduct the additional
drilling activities at the Caustic area next week. Frac tank didn’t arrive till Monday other
preparations were just scheduling?






Demolition and Remedial Progress Report for 2/9 to 2/14/09 2/20/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw continued the building clearance process. Cleared buildings 11,15 front section,73,109 for demolition.
• DH Griffin (DARI) shipped 1 truckload of asbestos to Charlotte Motor Speedway Landfill totaling 9.22 tons.
• DH Griffin shipped 39 loads of scrap metal weighing 628 tons to DH Griffins Greensboro office for recycling.
• DH Griffin shipped 3 loads of lime as product for reuse weighing 30.7242 tons, the lime loadout is complete.
• DH Griffin shipped 6 loads of non-hazardous (calcium carbonate) waste weighing 48.2 tons to WCA Landfill for disposal.
• DH Griffin continued asbestos and OHM abatement in building 15,52,73.
• DH Griffin continued demolition of buildings 30,37,62,63,87.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of building slabs 68,88.
• DH Griffin continued perimeter dust monitoring.
• Kessel Geotechnical began oversight of the geotechnical operations for fill placement at reservoir 54.
• Mountain Environmental continued removing weak liquor from building 56 chests and transferring to the clarifier.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slabs 68,88.
• Shaw completed ditch center sampling in the south and east ditches. XRF analysis continued on the deepest samples that had sufficient recoveries.
• Shaw’s surveying subcontractor completed a round of monitoring well and piezometer elevations.
• Shaw completed the camera survey of the EC building trenches.
• Shaw installed transducers in monitoring wells 16 A/B/C
• Shaw collected samples from crush material for lead analysis.


Demolition and Remedial Progress Report for 2/2 to 2/7/09 2/13/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw continued the building clearance process. Cleared buildings 30,37,60,62,63 for demolition.
• DH Griffin (DARI) shipped 2 truckloads of asbestos to Charlotte Motor Speedway Landfill totaling 14.2 tons.
• DH Griffin shipped 35 loads of scrap metal weighing 503 tons to DH Griffins Greensboro office for recycling.
• DH Griffin shipped 19 loads of lime as product for reuse weighing 242 tons.
• DARI started asbestos abatement in building 52.
• DH Griffin continued demolition of buildings 30,37,62,63,87.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of slabs 15,23,29,55 on the east side of the site.
• DH Griffin continued perimeter dust monitoring.
• Mountain Environmental removing weak liquor from building 56 chests and transferring to the clarifier.
• DRV continued discharging from the north clarifier into the ASB.
Shaw continued slab assessment activities in building slabs 15,23,27,29 and 55.
• Shaw completed ditch sidewall sampling in the south ditch and began ditch center sampling in the south ditch. XRF analysis continued on the deepest samples that had
sufficient recoveries. Began locating sample points for GPS mapping.
• Shaw completed a round of ground water level monitoring from all monitoring wells and piezometers which will be used to generate a updated site-wide groundwater elevation
map.
• Completed core drilling of 32 locations through the slab and into the subsurface trenches
in the EC Building floor to allow camera survey access.
• The Pump Test Plan for the Caustic area is in production.


Demolition and Remedial Progress Report for 1/26 to 1/31/09 2/6/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw continued the building clearance process. Building 62 transformers (10) were drained and 12,000 gallons on non PCB oil were recovered.
• DH Griffin (DARI) shipped 7 truckloads of asbestos to Charlotte Motor Speedway Landfill totaling 55 tons.
• DH Griffin shipped 37 loads of scrap metal weighing 568 tons to DH Griffins Greensboro office for recycling.
• DH Griffin shipped 12 loads of lime as product for reuse weighing 163 tons.
• DARI continued asbestos abatement in pipelines on the east side of the site and building 109 sheds.
• DH Griffin continued demolition of buildings 75,87.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of slabs 15,27,29,55 on the east side of the site.
• DH Griffin continued perimeter dust monitoring.
• Pike Electrical removed the last remaining structure, a transformer, from building 39 area.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slabs 27,28,29,75 and 90. Building 75 slab exceeded field PID guidelines and was sent for laboratory analysis.
• Shaw collected samples from the vault excavation adjacent to building 75 and from the building 27 footer excavation. The vault excavation appeared to contain residual black
liquor and the building 27 footer excavation had high levels of volatiles (1300 ppm PID). Samples from both locations were sent for laboratory analysis.
• Shaw continued ditch side sampling in the east ditch and began ditch side sampling in the south ditch. XRF analysis continued on the deepest samples from each side sample
location. 433 samples have been collected through 1/31/09.
• Shaw completed the finish grade, seed and straw of the rifle range excavation area.


Demolition and Remedial Progress Report for 1/19 to 1/24/09 2/5/2009
• Shaw continued sampling crushed concrete/brick debris.
• Shaw continued the building clearance process; buildings 62 walkthrough identified ten large transformers requiring oil drain confirmation. All are labeled non PCB.
• Shaw continued the building clearance process of building on the east side of the site.
Building 62 walkthrough identified ten transformers requiring oil drain confirmation. All are identified as non PCB oils.
• DH Griffin (DARI) shipped 5 truckloads of asbestos to Charlotte Motor Speedway Landfill totaling 43 tons.
• DH Griffin shipped 36 loads of scrap metal weighing 454 tons to DH Griffins Greensboro office for recycling.
• DARI continued asbestos abatement in pipelines on the east side of the site.
• DH Griffin continued demolition of buildings 41,75,87.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued demolition of slabs 15,21,27,28,29 on the east side of the site.
• DH Griffin continued perimeter dust monitoring.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slabs 14. The building 14 composite indicated elevated arsenic levels and additional sampling concluded that RG’s
from arsenic were exceeded at three locations.
• Based on regulator review, Shaw finalized the Tech Memo discussing elevated arsenic background levels used as fill material in the cellophane area.
• Shaw placed clean fill and grading areas disturbed by excavation and load-out activities at the rifle range.
• Shaw installed 6 new monitoring wells and completed 12 direct push soil borings around the caustic building slab. Four additional hand auger samples were collected within the footprint of the caustic building down to the groundwater interface. pH readings varied from 12.56 to 13.58.
• Shaw cleared and grubbed the south and east ditch transects and marked transects sample locations. Ditch side sampling began in the north end of the east ditch and center deep samples were collected in the east and south ditches. 98 samples were collected from side sampling and 20 from ditch centers. Three deep samples were not
collected due to numerous refusals from 1 ½ to 2 feet. Remaining deep samples will be collected using a 2 foot core to insure adequate volume and a more representative matrix. Two of the18-24” samples have exceeded RG’s for mercury, 12 have been analyzed.
• Mountain Environmental continued to remediate OHM, weak liquor was removed from a sump in building 75 and placed in the clarifier.


Demolition and Remedial Progress Report for 1/12 to 1/17/09 1/26/2009
• Shaw continued sampling crushed concrete/brick debris and collected and analyzed (metals) vault liquids near buildings 53/59.
• Shaw continued the building clearance process; buildings 41, 75 and 90 were cleared for demolition.
• Shaw continued the building clearance process of building on the east side of the site.
• DH Griffin (DARI) shipped 6 truckloads of asbestos to Charlotte Motor Speedway Landfill totaling 45.9 tons.
• DH Griffin shipped 13 loads of scrap metal weighing 206 tons to DH Griffins Greensboro office for recycling.
• DH Griffin shipped 28 loads of construction debris weighing 444 tons to WCA Landfill for disposal.
• DARI continued asbestos abatement in pipelines on the east side of the site.
• DH Griffin continued demolition of buildings 15,21,27,28,29,41,55,73.
• DH Griffin continued crushing operations in the north end of the site.
• DH Griffin continued slab removal operations on the east side of the site.
• DH Griffin continued perimeter dust monitoring.
• Mountain Environmental continued to remediate OHM.
• DRV continued discharging from the north clarifier into the ASB.
• Shaw continued slab assessment activities in building slabs 14,21,38,40 and 47. The building 14 composite indicated elevated arsenic levels and requires additional analytical.
• Based on regulator review, Shaw finalized the Tech Memo discussing elevated arsenic background levels used as fill material in the cellophane area.
• Shaw completed load-out of the stabilized lead containing soils from the Rifle Range to the Republic Services landfill in Enoree, SC. A total of 57 loads weighing 1175 tons have been shipped to the facility.
• Shaw developed two new wells in the Olin area and collected GW samples from wells for mercury analysis. These wells were requested by the regulators to provide final delineation of the mercury detection in well MW-26
• Shaw completed the remaining (PAH) hot spot excavation at SB-04. Four sidewalls and one floor sample were sent for lab analysis. Approximately 16 cubic yards were
excavated and placed in Building 89 with the remaining Olin area soils.
• Shaw completed hotspot removals at four cellophane areas: B101, B106, B94, B95, and B82. Approximately 200 cubic yards, mostly for B-82, of soil were generated from the removals and all soil was transported and staged in secure Building 89.
• Shaw received final acceptance of the TCRA Work plan from EPA with the finalization of the Ditches investigation strategy.


Demolition and Remedial Progress Report for 1/5-1/10/09 1/22/2009
• Shaw continued slab and basement assessment activities in the cellophane area and bldg 12.
• Shaw continued sampling crushed concrete/brick debris and collected and analyzed vault
liquids near buildings 53/59.
• Shaw continued the building clearance process of building on the east side of the site.
• Shaw and state/federal regulators continue to investigate the arsenic background levels
for fill material in the cellophane area.
• DH Griffin (DARI) shipped 6 truckloads of asbestos to Charlotte Motor Speedway
Landfill totaling 51 tons.
• DH Griffin shipped 9 loads of scrap metal weighing 143 tons to DH Griffins Greensboro
office for recycling.
• DH Griffin shipped 19 loads of construction debris weighing 339 tons to WCA Landfill
for disposal.
• DH Griffin shipped 1 loads of non-hazardous material debris weighing 5.25 tons to WCA
Landfill for disposal.
• DARI continued asbestos abatement in building 62 and pipelines on the east side of the
site.
• DH Griffin continued demolition of buildings 21,27,28,29,40,47.
• DH Griffin installed additional erosion control measures in the sedimentation basin
drainage and excavated utilities adjacent to the south ditch.
• DH Griffin continued crushing operations in the cellophane area and the north end of the
site.
• DH Griffin started slab removal operations on building 12.
• DH Griffin continued perimeter dust monitoring.
• Mountain Environmental continued to remediate OHM.
• DRV continued discharging from the north clarifier into the ASB.


Demolition and Remedial Progress Report for 12/15/08-12/31/08 1/14/2009
Shaw continued slab and basement assessment activities in the cellophane area.
• Shaw continued sampling crushed concrete/brick debris and collected and analyzed vault
liquids near buildings 53/59, vault contains approximately 28k gallons.
• Shaw and subcontractor ARM installed monitoring wells and collected soil borings in the
caustic area. Soil borings also collected in the cellophane area to determine fill depths.
• Shaw tested pH of caustic building slab concrete on drum pad, 10.6.
• Shaw delineated VOC impacted area under building 94 slab, approximately 60 cu/yds.
• Shaw and NCDNR continue to investigate the arsenic background levels for fill material
in the cellophane area.
• DH Griffin (DARI) shipped 13 truckloads of asbestos to Charlotte Motor Speedway
Landfill totaling 113.2 tons.
• DH Griffin shipped 27 loads of scrap metal weighing 373.1 tons to DH Griffins
Greensboro office for recycling.
• DH Griffin shipped 95 loads of construction debris weighing 1743 tons to WCA Landfill
for disposal.
• DH Griffin shipped 12 loads of non-hazardous material debris weighing 128 tons to
WCA Landfill for disposal.
• DARI continued asbestos abatement in buildings 15,62,73.
• DH Griffin continued demolition of buildings 14,15,50,53,59,87.
• DH Griffin continued crushing operations in the cellophane area and the north end of the
site.
• DH Griffin continued slab removal operations on building 5.
• DH Griffin continued perimeter dust, lead and arsenic monitoring.
• Mountain Environmental continued to containerize, stage and loadout OHM.
• DRV continued discharging from the north clarifier into the ASB.


Demolition and Remedial Progress Report for 12/8-12/13/08 12/19/2008
• Shaw continued slab and basement assessment activities in the cellophane area.
• Shaw continued sampling crushed concrete/brick debris, slab soils and from borrow
source soils used in the cellophane area.
• Shaw performed elevation surveys in the east and south ditches.
• DH Griffin (DARI) shipped five truckloads of asbestos to Charlotte Motor Speedway
Landfill totaling 39.9 tons.
• DH Griffin shipped 12 loads of scrap metal weighing 168 tons to DH Griffins
Greensboro office for recycling.
• DH Griffin shipped 27 loads of construction debris weighing 454 tons to WCA Landfill
for disposal.
• DH Griffin shipped two loads of non-hazardous material debris weighing 28 tons to
WCA Landfill for disposal.
• DARI continued asbestos abatement in buildings 43,55,62.
• DH Griffin continued demolition of buildings 35,50,53,59,70,87,88.
• DH Griffin continued crushing operations in the cellophane area and the north end of the
site.
• DH Griffin continued slab removal operations on buildings 5,70.
• DH Griffin continued perimeter dust, lead and arsenic monitoring.
• Mountain Environmental continued to containerize, stage and loadout OHM.
• DRV continued discharging from the north clarifier into the ASB.


Demolition and Remedial Progress Report for 12/1-12/6/08 12/11/2008
• Shaw continued slab and basement assessment activities in the cellophane area.
• Shaw continued excavating hotspots in the Olin area. Excavated soil is being staged in
building 89.
• Shaw began backfill and grading operations at the rifle range and Olin area hot spots.
• Shaw continued sampling crushed concrete and brick materials in the cellophane area.
• DH Griffin (DARI) shipped three truckloads of asbestos to Charlotte Motor Speedway
Landfill totaling 35 tons.
• DH Griffin shipped seven loads of scrap metal weighing 107 tons to DH Griffins
Greensboro office for recycling.
• DH Griffin shipped 22 loads of construction debris weighing 410 tons to WCA Landfill
for disposal.
• DH Griffin shipped two loads of non-hazardous material debris weighing 17.7 tons to
WCA Landfill for disposal.
• DARI continued asbestos abatement in buildings 43,62.
• DH Griffin continued demolition of buildings 34,35,50,53,59,70.
• DH Griffin continued crushing operations in the cellophane area.
• DH Griffin continued slab removal operations in the cellophane area and began bldg 70.
• DH Griffin continued perimeter dust and began lead and arsenic monitoring.
• DH Griffin continued installing sedimentation basin #2 drainage piping.
• Mountain Environmental continued to drain process lines, bulk oil and remove remaining
chemical containers.
• DRV continued discharging from the north clarifier into the ASB.


Demolition and Remedial Progress Report for 11/17-11/26/08 12/4/2008
• Shaw continued slab and basement assessment activities in the cellophane area.
• Shaw received the final shipment of portland cement and completed the stabilization
process at the rifle range.
• Shaw began and completed a round of well sampling in the EC building, Olin area and
along the ditches. Twenty wells were sampled including existing and new wells.
• Shaw continued excavating hotspots in the Olin area. Excavated soil is being staged in
building 89.
• Shaw cleared bldg 88 for demolition.
• Shaw continued lead based paint sampling. A paint sample was also collected in building
55 for PCB’s.
• Shaw began sampling crushed concrete and brick materials in the cellophane area.
• DH Griffin (DARI) shipped four truckloads of asbestos to Charlotte Motor Speedway
Landfill totaling 35 tons.
• DH Griffin shipped 23 loads of scrap metal weighing 333 tons to DH Griffins
Greensboro office for recycling.
• DH Griffin sent off one load of hazardous materials(24.1 tons) and 3 loads of nonhazardous
materials (25.5tons).
• DARI continued asbestos abatement in buildings 43,62.
• DH Griffin continued demolition of buildings 34,35,46,48,50,53,56.
• DH Griffin continued crushing operations in the cellophane area.
• DH Griffin continued slab removal operations in the cellophane area.
• DH Griffin continued perimeter dust monitoring.
• DH Griffin began installing sedimentation basin #2 drainage piping.
• Mountain Environmental continued to drain process lines, bulk oil and remove remaining
chemical containers.
• DRV began discharging from the north clarifier into the ASB.