U.S. EPA OSC Steve Faryan and Weston Solutions Inc. (WSI) START personal, Ben Maradkel continue conducting oversight, while PRP contractor installs soil vapor extraction (SVE) wells.
■ Installation of eleven soil vapor extraction (SVE) wells.
■ Reinforced haul road south of the Lockformer plant with more gravel to reduce tracking of mud on to the streets.
■ Transported and Disposed soil cuttings off-site.
■ Cut concrete inside the plant (west portion) to install SVE wells and electrodes.
■ PRP will remediate the surficial silty clay till and fill in Area 1 and 2 with Electrical Resistive Heating (ERH) technology.
■ PRP will remediate the mass waste sand and gravel in Area 1 and 2 with SVE technology.
■ Continue to install SVE wells.
■ Solve run-off problem in temporary parking lot (TBD e.g. catch basin)
■ Cut into concrete floor inside plant (former degreaser area).
■ Install equipment and process piping to the SVE wells.
■ Construct storage building.
■ Install electrodes and vapor wells for ERH.
■ Hookup vapor/air/water piping (ERH).
■ Review and Approve confirmation sampling plan.
■ Transport and Dispose soil cuttings and decontamination water off-site.
|