See polrep number 1.
January 1 through 9, 2005: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 192 gallons of material recovered to date in the 1,000 gallon tank.
January 10 through 16, 2005: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 192 gallons of material recovered to date in the 1,000 gallon tank.
January 17 through 23, 2005: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 192 gallons of material recovered to date in the 1,000 gallon tank.
January 24 through 31: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 192 gallons of material recovered to date in the 1,000 gallon tank.
February 1 through 6th, 2005: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 193 gallons of material recovered to date in the 1,000 gallon tank.
February 7 through 13th, 2005: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 200 gallons of material recovered to date in the 1,000 gallon tank.
**** Monday, February 14th, 2005. (OSC - 1, ERRS-4, START-1) ERRS, START, and OSC mobilized to the Ashton site. ERRS conducted some snow removal, set up site trailer, and loaded work conex box with tools and equipment. City of Ashton workers located the sewer line. START received shipment of equipment. ERRS prepared site for work on Tuesday.
**** Tuesday, February 15th, 2005. (OSC-1, ERRS-4, START-1) ERRS continued snow removal and worked to open up the vault covers housing the wells and oil removal pumps. Electricians conducted job walk and review of power requirements. The electricians determined that current power run to the utility box associated with the product pumps would not support the additional load for the groundwater depression system - need to run another line to temporary utility pole. Utilities Location service on site to survey site for buried electrical and water lines.
**** Wednesday, February 16th, 2005 (OSC-1, ERRS-4, START-1) ERRS installed temporary chain-link fencing around the site. EPA and ERRS worked with Idaho Transportation Department to obtain permit to excavate from site to sewer line on their right-of-way. ERRS met with City of Ashton Water and Sewer workers to discuss hook up requirements to the sewer line. Approximately 175 gallons of gasoline/diesel was removed from the 1,000 gallon storage tank and transported off site for recycling. ERRS ran pull lines through conduit leading from MW-15 and MW-10 to MW-9. EPA made field decision to relocate groundwater treatment system near MW-9 instead of MW-10. ERRS received the treatment system components that were preassembled on two metal skids. EPA attended the City Counsel meeting and provided a status update on site conditions and requested that the City waive the $1,000 sewer hook-up fee. The City voted to waive the $1,000 hook-up fee and requested EPA pay for their workers time and materials to assist with the sewer line hook-up. EPA agreed with the request as billable work. START conducted groundwater and product level measurements on all on-site wells. The off-site wells are covered by snow - workers will uncover them tomorrow. ERT hydrogeologist mobilized to the site.
**** Thursday, February 16th, 2005 (OSC-1, ERRS-4, START-1, ERT-1) ERRS received verbal authorization from Idaho Transportation Department to begin excavation on their right-of-way. ERRS excavated trench to the sewer line. Utah Power on site to determine requirements to install line to the temporary pole to be set by the electrician. ERRS configured all pumps, however, could not install because plumbing parts have not arrived on site. ERRS and START removed snow from on top of the off site wells. Temporary shed parts arrived on site along with plumbing parts. START collected another round of groundwater and product level measurements.
**** Friday, February 18, 2005. (OSC-1, ERRS-4, START-1, ERT-1, IDEQ-1, ERRS subcontractor DAL enterprises-1, City of Ashton -2) ERRS installed the three groundwater depression pumps into each well and ran the communication cables through the underground conduit. DAL and City of Ashton installed the connection to the sewer line. Electricians installed temporary utility pole. START and ERT collected groundwater and product level measurements from off-site and on-site wells. IDEQ hydrologist visited site and discussed system with ERT hydrogeologist.
-Operate groundwater depression and oil recovery systems.
* Plan to install and connect all electrical connecitons except the overhead power line. * Install overhead powerline. * Power up and test system. * Collect water quality samples of the effluent. * Initiate operation and maintenance plan for the product and groundwater systems.
EPA will operate these systems for another 6 months and then re-evaluate.
The Operator indicated that he may have to close his business this weekend.
|