SEE POLREP #1
Soil sampling based on the air deposition model and visual inspections has been completed. ERT collected a total of 97 soil samples for laboratory analysis. Of those 97 soil samples collected; • 3 samples were collected on site for confirmation, • 3 samples were collected off site from commercial properties, • 91 samples were collected off site from residential properties. Sample results are expected by May 9.
On-site excavation, transportation, and disposal have been completed. Asbestos is an inhalation threat; material 18-24in below ground surface was not removed. Geotextile fabric was placed on the excavation floor. Backfilling and restoration is underway.
1. Site restoration including backfilling and reseeding of Area 2 and Area 3; 2. Repave east parking areas; 3. Work with CSX Transportation, Inc on cleanup of railroad property
|