U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Ruddiman Creek and Pond Remediation

All POLREP's for this site Ruddiman Creek and Pond Remediation
Muskegon, MI - EPA Region V
POLREP #5
Printer Friendly  |   PDF
 
On-Scene Coordinator - Sam Borries/ Josie Clark 10/8/2005
Pollution Report (POLREP) #5
Start Date: 8/8/2005
Pollution Report (POLREP) #5
Site Description
Refer to POLREP #1 (initial)

Current Activities
During the week of October 3, 2006 full scale dredging operations and support activities were on-going in Ruddiman Pond, and in Ruddiman Creek.  Support activities include water treatment, calciment delivery, truck loading/unloading, decontamination procedures and maintenance of roads and barriers.  As of the end of day on October 7, appromixately 9,170 cubic yards were shipped off site for disposal.  6,270 cubic yards of that material were from Area A3 of Ruddiman Pond, and the remaining 2,900 cubic yards were from Area G of Ruddiman Creek.  288,900 gallons of water have been treated and discharged into the sanitary sewer as of 10/7/05.

Three obstacles were overcome during week.  On Monday morning, Great Lakes Docks and Materials lost one of two spuds from their work barge when the support cable snapped.  The top of the 40 foot long spud was located 11 feet under the water surface and recovered.  GLDM spent two days repairing the spud, and reinforcing the winching system to prevent a reoccurance in the future.  On Wednesday, EQM's filter bags in the water treatment system were clogging within half an hour of installation.  They have solved this by dosing the water with chlorine prior to putting it through the treatment system.  For every 20,000 gallons of water, one pound of chlorine is added.  On Thursday, Jackson and Mercky encountered material that is too soft to bear the weight of the excavator in the southwest portion of Area G.  They retreated from the area to prevent the equipment from getting stuck in the mud.  J&M dug out the top four feet of soft material under the access road path, then backfilled it with sand.  This has allowed them to return on swamp mats to the southwest corner to complete excavation of Area G.


Planned Removal Actions
During the week of 10/10/05 full scale dredging operations will be ongoing in Ruddiman Pond and in Area G, H or I of Ruddiman Creek.  Transportation, Disposal and water treatment will occur simultaneously with the ongoing dredging activities.  It is anticipated that Area G will be completed during this week, and confirmation sampling of the excavation bottom will be completed by EarthTech.

Next Steps
Continue dredging operations.

Key Issues
None