POLREP #2 - Continuation of Cleanup
Printer Friendly  |   PDF
 
On-Scene Coordinator - Craig Thomas 2/1/2008
Time-Critical - Removal Action Pollution Report (POLREP) #2
Start Date: 11/8/2007
Pollution Report (POLREP) #2
Site Description
The Asarco Taylor Springs Site consists of two parts: a 673-acre industrial property located on the southwest side of Taylor Springs, Montgomery County, Illinois 62089 and an unknown number of residential properties surrounding the industrial property.

The coordinates for the main Site are latitude 38° 39'06.9" north by longitude 90° 05'35.8" west. Of the 673 acres occupied by the main Site, 303 acres are wooded, 189 acres are used for agriculture, and the remaining 181 acres comprise the former and current Site operations area.  These 181 acres have been listed on the National Priorities List (NPL)

The Site is bordered to the northwest by cultivated farmland and woodlands, to the northeast by residential areas, to the east by the Taylor Springs waste water treatment plant and cultivated farmland, and to the south and west by cultivated farmland and woodlands. These Pollution Reports (POLREPs), focus on the residential areas surrounding the main industrial site.

The objective of this time critical removal action is to remove metals contamination above health based levels (primarily lead) associated with smelter wastes which were used on residential properties as fill material, as well as collect data which will be used to support the Remedial Investigation for the main site.

U.S. EPA's Emergency Response branch conducted a site assessment of soil lead concentrations in residential and public areas in the Village of Taylor Springs.  Access was obtained at approximately half of the residential properties in Taylor Springs, and sampling was conducted in June, 2006.  Results of this sampling found that approximately 20 residential or public areas exceeded U.S. EPA's time critical removal action level of 1,200 parts per million (ppm) lead, and an additional 67 properties exceeded the U.S. EPA Region IX Preliminary Remedial Goal for lead of 400 ppm.

This removal action should address the approximately 20 properties, and any previously unsampled residential properties or public use areas with lead concentrations exceeding 1200 ppm.


Current Activities
On January 2, 2008, the PRP contractors re-mobilized to the site to continue excavation activities and characterization sampling.  

On January 28, 2008, the PRP contractors had three excavation crews working on three separate properties, but will go back down to two excavation crews once they have analytical results back to begin backfilling activities.

To date, properties #14, #25, #29, #33, #61, #67, #78, #81, #89, #90, #96, #100, #118, and #120 have been excavated. PRP contractors are currently on properties #58 and #64.  An X-ray fluorescence analyzer(XRF)is being used to guide the excavation depths and width.  Approximately 2007.5 cubic yards have been removed to date.


Planned Removal Actions
Continue on excavation of properties under the TCRA.  Awaiting analytical results so that the PRP contractors can begin to backfill excavated properties.

Next Steps
PRP contractors will continue to backfill excavated properties.

Key Issues
None.