See polrep number 1.
December 1 through 7, 2003: ERRS subcontractor (1) ERRS subcontractor conducted operations and maintenance activities. A total of 93 gallons of material recovered in the 1,000 gallon tank. December 8 through 14, 2003: ERRS Subcontractor (1) ERRS Subcontractor conducted operations and maintenance activities. A total of 100 gallons of material recovered in the 1,000 gallon tank.
December 15 through 21, 2003: ERRS Subcontractor (1) ERRS Subcontractor conducted operations and maintenance activities, including cleaning the fuel extraction pumps. A total of 102 gallons of material recovered in the 1,000 gallon tank.
December 22 through 31, 2003: ERRS Subcontracotr (1) ERRS Subcontractor conducted operations and maintenance activities, including cleaning the fuel extraction pumps. A total of 103 gallons of material recovered in the 1,000 gallon tank.
-Operate system for 6 month period and re-evaluate.
-Transportation and Disposal of recovered product as needed. -EPA will re-evaluate the need to operate the system after 6-months.
IDEQ purchased treatment system and will provide collection services under an amended pollution removal funding authorization (PRFA).
Note: Adjusted EPA's costs based upon new estimates.
|