See initial PolRep. 
         
    
 
    
	
         
        Continued the on-site treatment of contaminated soils by using quick lime, in order to reduce the TCLP levels of lead.  Approximately 300 cubic yards of materials were treated.
  Began removing the contents of the excavated drums.
  Continued the air monitoring of both the perimeter and the work area.
  Collected one composite sample from the treated soils for analysis by an outside lab. Analytical test results indicated that the soil treatment was successful.
  Transported and disposed off approximately 75 tons of PCB-contaminated soils. 
         
    
 
    
	
         
        Remove and Sample Drums & Containers
  Sample soil stockpiles & generate waste profiles
  Perform Hazard Categorization
  Overpack/Repack Drums & Containers
  Excavate/Treat Impacted Soils, as necessary
  Transport/Dispose Drums & Impacted Soils
  Backfill & Grade Excavated Areas
  Restore Site, as necessary 
         
    
 
    
	
         
        Continue the on-site treatment of contaminated soils.
  Sample the treated material and arrange for disposal.
  On-site treatment of the materials that were removed from the excavated drums.
  Transportation and disposal of the treated PCB contaminated soils. 
         
    
 
    
	
         
        Secure funding for the continuation and completion of the project.
  
         
    
 
    
     |