U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

LWD, Inc.

All POLREP's for this site LWD, Inc.
Calvert City, KY - EPA Region IV
POLREP #7
Printer Friendly  |   PDF
 
On-Scene Coordinator - Steve Spurlin 8/24/2006
Time-Critical - Removal Action Pollution Report (POLREP) #7
Start Date: 3/2/2006
Pollution Report (POLREP) #7
Site Description
Please refer to previous POLREPs for site description and previous actions taken.

Current Activities
The following activities took place during the reporting period:

Operation of the wastewater treatment system (WWT) was continued until August 22, 2006 at which time the system was temporarily shutdown to change out the carbon in the filter system.  Approximately 450,000 gallons have been treated by the WWT system.  Treated water is being used for decontamination operations and/or being land applied.  Approximately 22,000 gallons of hazardous liquids from 4 tanks in the North Tank Farm (NTF) were shipped to Veolia ES Technical Solutions incinerator facility in Port Arthur, Texas for incineration and disposal.  Mechanical demolition of piping, valves, and pumps within the containment area of the NTF is being continued.  Piping is being cut into manageable pieces; pumps and valves are being disassembled; and all components are being decontaminated prior to being placed in a trailer for recycling at a scrap facility.  Samples from storage tanks continue to be taken as needed for characterization purposes.



Planned Removal Actions
The following activities are planned during the next reporting period:

Carbon change out will be completed and the WWT operations of treatable wastewater will be continued.  Mechanical demolition of piping, valves, and pumps will be continued.  Transportation and disposal of on-site hazardous waste will continue.  There are approximately 300 drums and containers that remain onsite, both inside the incinerator building and the drum storage warehouse.  To prevent spill migration, all drums will continue to be checked daily for leaks and bulges and will be over-packed as necessary.


Next Steps
The following have been identified as next steps in the stabilization phase of this removal action:

Preperations will continue so that the NTF can be completely dismantled along with the two caustic towers.  The south sump area, in the rolloff staging area, will be bermed and will become the location for cutting and cleaning of the rolloff boxes. This process will begin once the NTF is in the stage where the tanks can be removed.


Key Issues
Weather continues to pose problems at the Site.  Electrical storms in close proximaty causes delays or suspension of work.  Also, higher temperatures can cause heat stress, therefore the heat has been limiting the amount of time crews can work in personal protective equipment (PPE).