For site description and previous actions, please refer to previous POLREPs.
During April, May, and June 2007, EPA and the Tennessee Department of Environment & Conservation (TDEC) continued to monitor the cleanup activities at the Site.
Intitial actions completed by Helena's contractor, USES, resulted in the generation of 32-20 cubic yard rolloffs of pesticide contaminated soil and 12,000 gallons of contaminated wastewater. Also, an arsenic contaminted waste pile, primarily consisting of seed, was stockpiled and covered on the building slab.
Samples from these wastestreams were collected by Helenas contractor, and the waste remained on-site pending lab results.
The Site was bermed to prevent runoff, and USES has continued to collect potentially contaminated runoff from the berm areas while disposal plans are finalized.
Complications regarding waste characterization delayed the shipment of the rolloff waste; however, the waste was containerized or covered to prevent migration until shipment.
Eventually, disposal arrangements were finalized and the following wastes were transported offsite for disposal:
32 Rolloffs of non-haz, pesticide contaminated soil (18-20 tons/rolloff) 24 trucks (360 tons est.) of non-haz, pesticide contaminated soil 100,000 gallons rainwater to local POTW 10,000 gallons of hazardous wastewater 250 tons of hazardous seed/debris
Removal of the rolloff waste and stockpile allowed Helena's contractor room to complete the remaining actions EPA & TDEC deemed to be priority. These actions included the decontamination of the building concrete slab and excavation of the remaining visually inpacted soils along the northern portion of the building.
Helena's contractor has collected confirmation samples in the excavation areas. The data has been provided to TDEC for remediation consideration.
As of the date of this polrep, Helena has the following planned actions remaining at the Site:
Shipment of the remaining 2000 gallons of hazardous wastewater; complete excavation & disposal of soils contaminated with atrazene.
Remaining excavation is scheduled for 7/9/07
The TDEC continues to take the lead on remaining Site cleanup activities. Helena's contractor continues to maintain the berm and collect wastewater as necessary. Helena will make a final decision regarding site restoration after excavation is completed; however, it is anticipated they will backfill excavation areas and establish cover.
|
32 Rolloffs (600 tons est.) of pesticide (2,4 D) contaminated soils shipped to BFI-Tunica, MS Landfill
360 tons est. of pesticide (2,4 D) contaminated soils shipped via truck to BFI Tunica, MS Landfill
100,000 gallons of rainwater discharged to Humbolt, TN POTW
12,000 Gallons RCRA hazardous pesticide wastewater shipped to Clean Harbors, El Dorado, Ark.
250 tons RCRA hazardous waste (arsenic) seed/debris to Waste Mang., Emelle, AL.
|