U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Ecusta Mill

All POLREP's for this site Ecusta Mill
Pisgah Forest, NC - EPA Region IV
POLREP #8 - On going Removal Activities for 1/26 to 1/31/09
Printer Friendly  |   PDF
 
On-Scene Coordinator - Jennifer Wendel 2/6/2009
Time-Critical - Removal Action Pollution Report (POLREP) #8
Start Date: 9/22/2008
Pollution Report (POLREP) #8
Site Description
The Ecusta Mill is a former flax pulping and paper manufacturing facility that was built in 1939 and was operational until 2002.  Cellophane production also occurred at the facility for approximately 30 years.  In addition, the following activities have occurred at the Site:  chlorine production operations using Sorenson mercury cells (electro-chemical building); caustic storage; water and wastewater treatment; and printing.  EPA's Removal Program and the North Carolina Department of Environment and Natural Resources (NC DENR) first responded when the plant was closed down in 2002.  Of primary concern were potential releases from an interruption of power to the basement sumps under the production buildings.  The EPA Environmental Response Team conducted sampling of the concrete floor, the sub-floor, and soils under the electro-chemical building and sediments in on-site ditches.  This sampling confirmed the presence of mercury in the sub-floor structures to 16 feet below ground surface (580 mg/kg) and the floor drains (260 mg/kg) of the electro-chemical building, in the indoor air and in the overland drainage ditches which had received historic discharge from the building.

    An Expanded Site Inspection (ESI) was conducted by EPA Region 4, Science and Ecosystem Support Division and the State in March, 2004.  The ESI focused on two main areas of concern, the electro-chemical building and the Aeration and Sedimentation Basin (ASB) area.  Mercury was detected in soils adjacent to the electro-chemical building, in sediments in the on-site drainage ditches and in sediments of the Davison River immediately adjacent to the manufacturing area. The ESI also confirmed soils and sediments in other areas of the site are contaminated with mercury and dioxin.   Groundwater sampling has confirmed low-levels of mercury in groundwater near the electro-chemical building, low levels of carbon disulfide and 1,1-Dichloroethane near the cellophane plant, and a high pH reading (pH 12.17) in the area of a previous caustic spill.

    The total Site is approximately 527 acres in a mixed-use residential/industrial area.  The manufacturing facility is approximately 213 acres. The ASB has a surface area of approximately 75 acres and was used for wastewater treatment.  The ASB also receives storm water from approximately one-third of the site, including those areas historically most actively involved in paper production.  The following industrial solid waste landfills are located at the Site:  the Island landfill, the new ash landfill; the old ash and sludge landfills which are unlined industrial landfills which do not have permit numbers issued.  The previous site owner is in the process of closing all landfills in compliance with State permit requirements.

    A small arms firing range has been historically operated on the Site south of the main manufacturing operations on a largely undeveloped parcel of land near the confluence of the Davidson and French Broad Rivers.  Lead impacted soil has been document from the historic firing range.

    Renova Partners, a Brownfields redevelopment company purchased the property in January 2008.  Renova formed a subsidiary company Davidson River Village, LLC (DRV) who is conducting complete demolition of all on-site structures prior to site redevelopment.  D.H. Griffin was retained by DRV to conduct the demolitiion.  

  DRV is conducting the Removal Activities at the site under an AOC with EPA.  They have hired Shaw Environmental as the lead environmental contractor. Removal Activities include a Time Critical Removal Action and 2 Non-Time Critical Removal Actions.  



Current Activities
Shaw continuing sampling crushed concrete/brick debris.

Shaw continuing the building clearance process. Building 62 transformers (10) were drained and 12,000 gallons on non PCB oil were recovered.

DH Griffin (DARI) shipping truckloads of asbestos to Charlotte Motor Speedway Landfill.

DH Griffin shipping loads of scrap metal weighing 568 tons to DH Griffins Greensboro office for recycling.

DH Griffin shipping loads of lime as product for reuse.

DARI continuing asbestos abatement in pipelines on the east side of the site and building
109 sheds.

DH Griffin excavating impacted soil associated with the vault excavation adjacent to building 75.

DH Griffin continuing demolition of buildings 75,87.

DH Griffin continingd crushing operations in the north end of the site.

DH Griffin continuing demolition of slabs 15,27,29,55 on the east side of the site.

DH Griffin continuing perimeter dust monitoring.

Pike Electrical removing the last remaining structure, a transformer, from building 39
area.

DRV continuing discharging from the north clarifier into the ASB.

Shaw continuing slab assessment activities in building slabs 27,28,29,75 and 90. Building
75 slab exceeded field PID guidelines and was sent for laboratory analysis.

Shaw collecting samples from the vault excavation adjacent to building 75 and from the building 27 footer excavation. The vault excavation appeared to contain residual black liquor and the building 27 footer excavation had high levels of volatiles (1300 ppm PID). Samples from both locations were sent for laboratory analysis.

Shaw continuing ditch side sampling in the east ditch and began ditch side sampling in the
south ditch. XRF analysis continued on the deepest samples from each side sample
location. 433 samples have been collected through 1/31/09.

Shaw completing grading, seeding and strawing of the rifle range excavation area.


Planned Removal Actions
Shaw and DH Griffin will continue the building clearance process.

DH Griffin ACM abatement crews will start asbestos abatement in building 52 and
continue OHM abatement in building 60.

DH Griffin demolition activities will continue in buildings cleared.

DH Griffin recycling contractors will continue removing recyclable supplies and
equipment.

DH Griffin/ Shaw will continue slab removal and investigation process.

DH Griffin and Mountain Environmental will continue to remove OHM materials.

Shaw will collect samples for crushed debris.

Shaw will continue ditch sampling of side samples and begin ditch center sampling. Two
foot deep ditch center samples and will be collected using a two foot core sampler. Side
sampling will continue using a hand auger. The bottom 6” of each sample location will
continue to be analyzed on site using and XRF in addition to laboratory analysis for all
depths.

Shaw will continue sub slab analysis and documentation.

State/federal regulators will continue to investigate arsenic soil background levels.

Shaw will prepare for the EC building camera survey by core drilling access points in the
sub-slab trenches.

Shaw will survey monitoring well elevations and collect a round of groundwater levels.


 
Disposition Of Wastes
DH Griffin (DARI) shipped 7 truckloads of asbestos to Charlotte Motor Speedway Landfill totaling 55 tons.

DH Griffin shipped 37 loads of scrap metal weighing 568 tons to DH Griffins Greensboro office for recycling.

DH Griffin shipped 12 loads of lime as product for reuse weighing 163 tons.