U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Ohio Cast Products

All POLREP's for this site Ohio Cast Products
Canton, OH - EPA Region V
POLREP #8
Printer Friendly  |   PDF
 
On-Scene Coordinator - Stephen Wolfe\James Justice 6/15/2009
Time-Critical - Removal Action Pollution Report (POLREP) #8
Start Date: 3/16/2009
Pollution Report (POLREP) #8
Site Description
See initial POLREP.

Current Activities
June 1, 2009 (Monday)

•  ERRS began the clean-up of the PCB-contaminated (150,000 ppm PCB) floor debris and foundry sand inside the building of Area #6.
•  ERRS began and completed an exploratory excavation for a suspected (anecdotal information and site blueprints) underground storage tank.  No underground storage tank was located.
•  ERRS began the removal of residual asbestos pipe insulation and asbestos-contaminated waste material from the floor in Building #4.
•  ERRS completed the clean-up of ACWM from Areas #1 and #2.

June 2, 2009 (Tuesday)

•  ERRS continued the clean-up of the PCB-contaminated (150,000 ppm PCB) floor debris and foundry sand inside the building of Area #6.
•  ERRS completed the removal of residual asbestos pipe insulation and asbestos-contaminated waste material from the floor in Building #4.
•  START conducted a visual inspection of Areas #1 and #2 as part of the final clearance requirements for the removal of asbestos contaminated materials. START collected final clearance micro-vacuum samples and surface soil samples for asbestos.
•  Former Ohio Cast Products employees indicated thst drums were buried on the property; therefore, test pits were excavated by ERRS to search for buried drums or containers. No drums/containers were observed in the three pits excavated.

June 3, 2009, (Wednesday)

•  Nine additional test pits were excavated by ERRS in the southeast portion of the Site.  No drums/containers were observed.
•  ERRS began consolidation of waste materials from drums, totes and containers into 55-gallon drums and shippable containers and segregated the waste streams.
•  ERRS continued the clean-up of the PCB-contaminated (150,000 ppm PCB) floor debris and foundry sand inside the building of Area #6. ERRS continued the floor clean-up of ACWM from Building #4.

June 4, 2009, (Thursday)

•  Two (2) roll-off boxes of ACWM transported off site for disposal.
•  Approximately 30 feet of the western portion of Building #4 was removed for site safety. This portion of the building was heavily damaged from the fire.
•  The third transformer was removed from the substation area and relocated to the transformer staging area.
•  ERRS continued consolidation of waste materials from drums, totes and containers into 55-gallon drums and shippable containers.

June 5, 2009, (Friday)

•  ERRS began the clean-up of floor debris from Area #3 (courtyard area) of mixed PCB and asbestos waste.
•  ERRS continued consolidation of waste materials from drums, totes and containers into 55-gallon drums and shippable containers.
•  ERRS continued the clean-up of the PCB-contaminated (150,000 ppm PCB) floor debris and foundry sand inside the building of Area #6.
•  ERRS/START began investigation for the presence/ extent of contamination of PCBs in the vicinity of the electrical substation.

June 8, 2009 (Monday)

•  ERRS/START continued investigation for the presence/extent of contamination of PCBs in the vicinity of the electrical substation.
•  ERRS continued the transfer and consolidation of waste streams into transportable drums and totes.
•  ERRS completed the clean-up of the heavily PCB contaminated sand in Building #6 (8 cubic yard boxes) and applied less than 10 solution to the cleaned floor.

June 9, 2009 (Tuesday)

•  ERRS/START continued the investigation for the presence/extent of contamination of PCBs in the vicinity of the electrical substation.
•  ERRS continued the transfer and consolidation of waste streams into transportable drums and totes.
•  ERRS continued the removal of asbestos and PCB contaminated debris from Building #3 (courtyard). Waste was placed in lined, 20-yard roll-off boxes for off site disposal.
•  ERRS continued applying less than 10 solution to the concrete floor in Building #6.

June 10, 2009, (Wednesday)

•  ERRS/START completed the investigation for the presence/extent of contamination of PCBs in the vicinity of the electrical substation.  Analytical results for samples collected are pending.
•  ERRS completed the transfer and consolidation of waste streams into transportable drums and totes.
•  ERRS began installation of the wastewater treatment system for the removal and filtration of PCB contaminated water from the trench system in Building 6.

June 11, 2009, (Thursday)

•  ERRS continued installation of the wastewater treatment system for the removal and filtration of PCB contaminated water from the trench system in Building 6.
•  Representatives from the City of Canton sewer division were on site to discuss the discharge requirements and laboratory analytical parameters for the treated wastewater.
•  ERRS began backfilling the basement area and some of the office area of Building #1 with on-site materials.

June 12, 2009, (Friday)

•  ERRS completed the clean-up of floor debris from Area #3 (courtyard area) of mixed PCB and asbestos waste.
•  Site walk conducted by US EPA, ERRS and START to qualify and quantify the remaining scope of work activities.
•  START collected five (5) wipe samples from floor in Building #6, for PCB’s, after the “Less than 10” solution applied to the floor.
•  START collected five (5) micro-vacuum samples from Building #4 and one (1) micro-vacuum sample from the southwest portion on Building #2 for asbestos final clearance.


Planned Removal Actions
- Complete final cleaning of buildings affected by ACWM.

- Perform extent of contamination investigation of PCB contaminated soil from leaking transformers (Analytical results penidng).

- Initiate removal of PCB contaminated soil (total estimated 3,000 tons).

- Consolidate, sample, perform hazardous categorization and off-site disposal of all drums and containers on the site (estimated 100 drums, 100 totes and misc small containers).

- Remove and dispose of PCB contaminated water from the pits associated with the building.

- Remove transformers containing PCB oil.

- Remove and dispose of silica quartz dust/sand, as necessary.


Key Issues
- Residents are located directly across the street from the site.  As such, daily perimeter air samples for asbestos will be collected during all asbestos related work.


 
Disposition Of Wastes
A total of 3,119 tons of ACWM debris went to Minerva Landfill, Waynseburg, Ohio for disposal.

A total of 911 tons of ACWM debris went to American Landfill, Waynesburg, Ohio for disposal


Waste Stream Quantity Manifest # Disposal Facility
ACWM Debris 15 tons 215209 American Landfill, Waynesburg, Ohio
ACWM Debris 15 215208 Minerva Landfill, Waynesburg, Ohio