This Polrep covers Site work performed from Sunday 11/1/09 through Friday 11/6/09.
Sunday 11/1/09 – no site work.
Monday 11/2/09 On-site today: 6 ERRS. Safety Meeting at 7:30am. Work ended at 5pm * Started grading site with Low Ground Pressure D6 Dozer for better surface water drainage. * Continued to fill sand bags to hold visqueen on stockpile of contaminated soil. * Continued to demobilize water treatment system tanks. * Demobilized 20 foot storage container.
Tuesday 11/3/09 On-site today: 6 ERRS. Safety Meeting at 7:30am. Work ended at 5pm * Continued grading site with Low Ground Pressure D6 Dozer for better surface water drainage. * Loaded two EQM trucks with small office equipment and demobilized. * Continued to demobilize water treatment system tanks. * Received 200’ by 204’, reinforced, 6-mil, one-piece liner to cover stockpiled contaminated soil.
Wednesday 11/4/09 On-site today: 6 ERRS. Safety Meeting at 7:30am. Work ended at 5pm * Continued grading site with Low Ground Pressure D6 Dozer for better surface water drainage. * Covered stockpiled contaminated soil with 200’ by 204’, reinforced, 6-mil, one-piece liner and secured perimeter of liner with berm of clean soil and roped sand bags. * Continued to demobilize water treatment system tanks.
Thursday 11/5/09 On-site today: 7 ERRS. Safety Meeting at 7:30am. Work ended at noon. * Finished grading site with Low Ground Pressure D6 Dozer for better surface water drainage. * Deconned and demobed 460 Excavator. * Prepared tank #1 to be pumped with vacuum truck.
Friday 11/6/09 On-site today: 4 ERRS. Safety Meeting at 7:30am. Work ended at 5pm * Loaded two additional trucks with small office equipment and demobilized. * Deconned and demobed L90 Loader, D6 LGP Dozer, 2000 gallon Water Truck, remaining portable toilets and handwash station. * Cleaned permanent officer trailer and storage container. * Pumped 11,500 gallons of sediment water from tank #1 using three vacuum trucks and sent the waste to Arlington landfill for processing and disposal.
1. Demobilize remaining tank and equipment. 2. Cover stockpiled contaminated soil until it can be transported to appropriate landfill. 3. Grade and seed bare areas.
|