U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Hudson Falls Powerhouse and Allen Mill Site

 
Site Contact:
David Rosoff
On-Scene Coordinator

(Rosoff.David@epa.gov)

Site Location:
Village of Hudson Falls, NY 12839
response.epa.gov/HudsonFalls

The Hudson Falls Powerhouse and Allen Mill Site is located along the east bank of the Hudson River in the village of Hudson Falls, Washington County, New York. The Allen Mill is a former textile mill that was constructed in the mid-1800s and borders the former General Electric (GE) Hudson Falls Facility. The Powerhouse, which is immediately downstream from the Allen Mill, was constructed in 1907 and supplied hydroelectric power to the Mill through a system of raceways and tunnels that were excavated into the bedrock. 

During a 30-year period ending in 1977, polychlorinated biphenyls (PCBs) were discharged into the Hudson River from GE’s capacitor manufacturing plant located in Hudson Falls. PCB releases from the plant caused significant surface and below-ground contamination. The former GE Hudson Falls plant site is being addressed under New York State’s Superfund program. GE performed dredging in the upper Hudson River to remove PCB-contaminated sediment, under EPA oversight, between 2009-2015. However, PCB contamination remains in the bedrock at the GE Hudson Falls Facility, and potentially in the soil near the Allen Mill and Powerhouse structures themselves.

In July 2022, the U.S. Environmental Protection Agency (EPA) reached an agreement with Niagara Mohawk Power Corporation (NMPC), which is owned by National Grid, and General Electric Company (GE) to dismantle the Powerhouse and Allen Mill. The owner of the property, NMPC, is taking down the buildings due to their deteriorated condition. Because these activities have the potential to cause a release of PCBs into the Hudson River, they will be carefully dismantled.  

Under the terms of the legal agreement, NMPC and GE are required to submit detailed plans to the Agency outlining how the structures will be taken down safely, with measures in place to reduce the potential for a release of hazardous substances into the river. The monitoring of air, surface water and groundwater will be required during the work.

The Powerhouse building was carefully dismantled from fall 2022 into spring 2023. Extensive environmental monitoring was performed during the work and the data indicates that a release to the river was successfully prevented. Long-term plans are needed for the remaining building features, including a comprehensive plan for the concrete floor slab and trench.

Pre-design investigation work for the Allen Mill began in fall 2023 and is ongoing. This work is needed to better understand environmental conditions in and around the building where access has been restricted for many years. The pre-design work includes sampling of building materials and debris, as well as sampling of water, air and groundwater to understand baseline conditions. The dismantling of the Allen Mill is scheduled to begin in fall 2025 following the completion of the pre-design investigation and design work. 

More information about the work is available in the Powerhouse and Allen Mill Presentation to the Hudson River Community Advisory Group (09/25/24).