1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
109H |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
10/11/2007 |
Response Authority: |
CERCLA |
|
Response Type: |
Non-Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
7/5/2010 |
|
Start Date: |
7/6/2010 |
Demob Date: |
9/21/2010 |
|
Completion Date: |
9/21/2010 |
CERCLIS ID: |
WAN001002309 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Refer to Initial POLREP.
1.1.2 Site Description
Refer to Initial POLREP.
1.1.2.1 Location
Refer to Initial POLREP.
1.1.2.2 Description of Threat
Refer to Initial POLREP.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
Refer to Initial POLREP.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
Refer to Initial POLREP.
.
2.1.2 Response Actions to Date
Approximately 41,000 cubic yards of mine waste contaminated materials and petroleum contaminated soils were excavated from the vicinity of milling structures, and these materials were transported to and consolidated at the nearby impoundment. The 43 acre impoundment was reduced in size by approximately 3 acres. The 3-acre impoundment pond was drained, obliterated, and filled in with clean material. Several mill structures such as conveyors were demolished to enable excavation of contaminated materials.
A borrow source was developed to provide clean cover material for the protective barrier constructed on the impoundment. Soil was also excavated from a nearby pasture area to provide additional cover material and to create a substitute wetland for the obliterated impoundment pond. More than 172,000 cubic yards of course-grained soil seeded with 1875 pounds of a dryland pasture grass mix was placed over the impoundment. A 1-mile metal T-post and barbed wire fence was erected around the perimeter of the barrier to control access.
Disturbed areas were graded and stabilized for surface water and sediment control.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
Refer to Initial POLREP.
2.1.4 Progress Metrics
Refer to Initial and Intermediate POLREP.
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
None; the removal action is complete.
2.2.1.1 Planned Response Activities
None; the removal action is complete.
2.2.1.2 Next Steps
None; the removal action is complete.
2.2.2 Issues
None.
|
|
2.3 Logistics Section
|
|
|
N/A
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
2.5.1 Safety Officer
Refer to Initial POLREP.
2.6 Liaison Officer
N/A
2.7 Information Officer
2.7.1 Public Information Officer
N/A
2.7.2 Community Involvement Coordinator
N/A
|
3. Participating Entities
|
|
3.1 Unified Command
N/A
3.2 Cooperating Agencies
Refer to Initial POLREP.
|
4. Personnel On Site
|
|
None; the removal action is complete.
|
5. Definition of Terms
|
|
N/A
|
6. Additional sources of information
|
|
6.1 Internet location of additional information/report
N/A
6.2 Reporting Schedule
N/A
|
7. Situational Reference Materials
|
|
N/A
|