U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
San Jacinto River Waste Pits TCRA - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region VI
|
Subject:
|
POLREP #3
Site preparation resumes
San Jacinto River Waste Pits TCRA
06ZQ
Channelview, TX
Latitude: 29.7944000 Longitude: -95.0625000
|
To:
|
|
From:
|
Valmichael Leos, RPM
|
Date:
|
2/16/2011
|
Reporting Period:
|
01/01/11 - 02/14/11
|
1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
06ZQ |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
4/2/2010 |
Response Authority: |
CERCLA |
|
Response Type: |
PRP Oversight |
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
NPL Status: |
NPL |
|
Operable Unit: |
|
Mobilization Date: |
12/8/2010 |
|
Start Date: |
12/8/2010 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
TXN000606611 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
RP lead CERCLA time critical removal action
1.1.2 Site Description
The site encompasses approximately 25 acres. The removal action is to stabilize the site by designing and constructing a physical protective barrier surrounding waste ponds 1 and 2 that temporarily abates the release of polychlorinated dibenzo-p-dioxins and polychlorinated dibenzofurans (and possibly PCBs) into the San Jacinto River, until the site is flllly characterized and a remedy is selected.
1.1.2.1 Location
The Site is in Harris County in the State of Texas. The Site itself
has no specific street address. The Site is comprised of two waste ponds
with three surface impoundments built in the 1960's. The ponds and
impoundments are situated on a partially submerged 20-acre parcel of
real property. The Site is located on the western bank of the San
Jacinto River, in Harris County, Texas, immediately north of the
Interstate Highway 10 (1-10) bridge over the San Jacinto River.
Available information indicates the two waste ponds were built during
1965 by constructing berms within the estuarine area just north of what
was then Texas State Highway 73 and is now 1-10, west of the main river
channel, east of the City of Houston, between two unincorporated areas
known as Channelview and Highlands.
1.1.2.2 Description of Threat
The waste paper sludge was placed in the two ponds on the Site. Waste
pond 1 is located on the western portion of the Site totaling 132,386
square feet. Waste pond 2 which consists of two surface impoundments are
on the eastern portion of the Site totaling 46,182 square feet and
188,641 square feet respectively. Currently, the Site is inactive and
approximately half of the Site's surface area, including the abandoned
waste disposal ponds, is now submerged below the adjacent San Jacinto
River's water surface. Waste pond I with one impoundment is partially
submerged and waste pond 2 with the two impoundments is completely
submerged in the San Jacinto River.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
The primary hazardous substances documented at the Site are
polychlorinated dibenzo-pdioxins and polychlorinated dibenzofurans. At
the time of the signing of the Action Memo, dioxin concentrations as high
as 41,300 parts per trillion have been found in sediment samples
collected from the Site's disposal pond areas and hom river sediments
near the Site. Sediments contaminated with high levels of dioxin have
been found in the San Jacinto River both upstream and downstream from
the Site due to tidal influences. Additional sediment samples were
collected in compliance with the Action Memo, dioxin concentrations as
high as 360,000 parts per trillion have been found in sediment
samples collected from the submerged portion of the waste disposal ponds
as well as dioxin concentrations as high as 3,660 parts per trillion
action level in sediment sanlples collected outside the original 1966
berm placement for the two waste ponds indicating the release of dioxin
from the original location of the waste ponds.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1
Narrative
In accordance with the statement of work (SOW), in the EPA Administrative Order
on Consent (AOC), the respondents International Paper Company Inc. (IP) and
McGinnes Industrial Maintenance Corporation (MIMC) have 30 calendar days to
begin construction for the time critical removal action. On November 8,
2010 the EPA finalized a work plan that details the construction of a temporary
cap that will stabilize the release or threat of release of hazardous
substances into the San Jacinto River.
2.1.2 Response Actions to Date
On January 5, 2011, EPA remedial project manager (RPM) Leos conducted a site
inspection and documented that all on site field activities at the site have
stopped. The Respondents have resumed some on site field activities on
February 1, 2011 in preparation for implementing the time critical removal
action.
To date, the respondents have began conducting access road improvements along
the Texas Department of Transportation (TxDOT) Right-of-Way (ROW) adjacent to
the waste pits, mobilized office trailers for on site project management, and
have received a limited amount of cover material which is being stockpiled for
use on top of the waste pits.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties
(PRPs)
Currently, EPA is working with International Paper Company Inc. and McGinnes
Industrial Maintenance Corporation under an EPA issued Administrative Order on
Consent.
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated / Completed Activities
• The Respondents, Anchor QEA, and USA Environment, completed work on the following tasks:
• Engaged in construction activities at the Administration Site that included the following:
o Completed installation of electrical connections to the office trailers at the Administration Site. Activation of electrical service will occur after inspection by the utility company, planned for next week.
o Began installation of plumbing connections to the office trailers at the Administration Site.
o Began fence repairs around the perimeter of the Administration Site.
o Received and stored 10 rolls (15’x360’) of Skaps GT142 geotextile at the Administration Site.
o Added barbed wire atop perimeter fence at the Administration Site.
o Administration Site signs approved by EPA were ordered on February 11, 2011.
• Engaged in construction activities at the LaBarge Site that included the following:
o Received Armor Cap D rock at LaBarge Site and managed Armor Cap D stockpile.
o Continued assembly of transport barge and barge-mounted equipment.
• Engaged in construction activities on the TxDOT right-of-way (ROW) that included the following:
o Installed silt fence along north side of TxDOT ROW in area between main access gate and west cell of the waste pits.
o Graded TxDOT ROW haul road to promote drying of soil.
o Mobilized roller to TxDOT ROW.
o Raised height of main access gate approximately 12 inches in preparation for haul road construction.
o Transported 4 rolls (15’ x 360’) of geotextile to TxDOT ROW in preparation for haul road construction.
• Contacted fencing company on February 10, 2011, to repair breach in Big Star fencing. Repairs scheduled to be completed by February 15, 2011.
2.2.1.1 Planned Response Activities
• Continue site preparation of lay down area and access road for mobilization of equipment and resources.
• Continued analytical laboratory testing of processed concrete and aggregate samples.
• USA Environment continued to develop remaining contractor draft work plans described
in the approved Removal Action Work Plan.
• Continued developing on-site security plan to be used during active TCRA construction.
• Finalize remaining contractor work plans referenced in Section 4.4 of the approved
TCRA Removal Action Work Plan.
• Ship next train load of natural stone aggregate (Armor Cap C) from the quarry to Texas
City. This material will be stored in Texas City until space becomes available at the
LaBarge Site, or within Laydown and Stockpile Area to be constructed in the TxDOT
ROW.
• Take additional steps to address Site security.
• Continue to prepare the Administration Site including:
o Have electrical hookup inspected and activated.
o Finish communication and sewer hookups for the job-site trailers.
o Procure and install identification signs for the Administration Site.
o Develop plan for managing Site visitors, including Plans for providing safety briefing and maintaining a visitor log.
• Continue to prepare the LaBarge Site including:
o Complete barge preparation and loading of material for placement of armor cap.
o Continue to supplement stockpile of aggregate as space becomes available.
• On the TxDOT ROW, continue construction of the road and related improvements
described in the approved RAWP, and construct additional improvements in the ROW as
permitted by the access agreement with TxDOT.
• On the waste pits:
o Perform pre-construction bathymetric survey.
o Move buoys.
o Install silt curtain.
o Clearing and grubbing of the western cell.
o Commence installation of armor cap, provided weather delays do not significantly impact ongoing construction activities.
2.2.2 Issues
• No work as been completed on top of the waste pits as of February 16, 2001, and the Respondents are estimated to be a minimum two months behind schedule according to the current EPA approved work schedule.
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
No information available at this time.
|
3. Participating Entities
|
|
No information available at this time.
|
4. Personnel On Site
|
|
No information available at this time.
|
5. Definition of Terms
|
|
No information available at this time.
|
6. Additional sources of information
|
|
No information available at this time.
|
7. Situational Reference Materials
|
|
No information available at this time.
|
|
|