U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
FMO Pesticide Site - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region III
|
Subject:
|
POLREP #30
On-going Removal Action
FMO Pesticide Site
A3PZ
Orefield, PA
Latitude: 40.6322715 Longitude: -75.6149893
|
To:
|
Gerald Heston, US EPA Region III
Jeff Bartlett, North Whitehall Township
Dennis Carney, EPA Region III
Linda Marzulli, EPA Region III
|
From:
|
Ruth Scharr, Federal On-Scene Coordinator
|
Date:
|
11/23/2011
|
Reporting Period:
|
11/11/2011 to 11/18/11
|
1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
A3PZ |
|
Contract Number: |
EP-S3-07-03 |
D.O. Number: |
|
|
Action Memo Date: |
9/1/2010 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
7/1/2010 |
|
Start Date: |
9/17/2010 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
PAN000306719 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time-Critical Removal
1.1.2 Site Description
The Site is characterized as a time-critical removal. The Site includes land that was used formerly for the commercial growing and harvesting of fruit from orchard trees and are currently zoned for residential or public use primarily in North Whitehall Township, PA. Lead arsenate pesticide was historically used for several decades at the Site until its use was banned in 1988 by EPA. Elevated levels of arsenic and lead have been detected in surface soil samples on residential parcels and in public use areas. The FMO Pesticide Action Memo was submitted by the OSC and signed on September 1, 2010 approving a Removal Action which addresses contamination at residential parcels.
1.1.2.1 Location
The site is primarily located in the Orefield/Schnecksville area of North Whitehall Township, Lehigh County, Pennsylvania.
1.1.2.2 Description of Threat
Incidental ingestion of lead and arsenic through direct contact with contaminated soil, or ingestion of contaminants from small particles that have been aerosolized from the disturbance of soil.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
2.1.2 Response Actions to Date
Currently a total of 23 properties require removal activities. Twenty-two properties have been completed to date. "Complete" refers to excavation being complete and the yard being restored with sod. Additional watering activities are conducted at a given property after being completed.
On November 14th, excavation activities were started at the 23rd property. Most of the front yard was excavated. On November 17th, backfilling activities began on the western side of the front yard. Excavation activities included hand digging around trees and driveway to avoid damage of both areas. Heavy equipment was
used in both areas to complete excavation activites. No significantly
elevated dust concentrations were identified downwind of or within the work
area during this time period. All excavation areas were covered with
impermeable plastic during evenings until backfill was installed. The entire excavated area was covered with impermeable plastic at the end of the work day on November 18th and will not be uncovered until the crew returns to work on November 29th.
Newly installed sod
was watered at each property as identified by EPA. Sod was not watered if
it rained.
A total of 131 rolloffs containing an estimated 2,096 tons of soil have
been shipped offsite for disposal as non-hazardous waste. A total of 5
rolloffs were used at property 23. During this month, 13 rolloffs were received and staged onsite; 3 were
shipped off for disposal by November 18th.
Crew was demobed on November 19th for the Thanksgiving holiday.
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
If the ground temperature holds above 40 degrees Fahrenheit, and is projected to remain so through mid-December, then sod will be installed in the front yard of the 23rd property the week of November 28th. Otherwise, seeding and erosion control matting will be installed. ERRS will continue to water sod, as needed, at properties indicated by EPA.
Post-excavation samples will be shipped to an offsite laboratory for arsenic and lead analysis. Post-excavation walk-throughs are being scheduled at residences at which inital rooting of the sod has occurred. Initial rooting of the sod can take approximately three to four weeks. EPA will prepare the closeout letter for those properties where we have completed post-excavation walkthoughs. This letter will include a map showing where EPA excavated and restored the property. Post-excavation sampling results will be provided in a separate letter due to the extended turnaround time for the receipt of the validated data.
Crew will remobe on November 28th to complete work at the last property.
2.2.1.2 Next Steps
2.2.2 Issues
None
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
2.5.1 Safety Officer
2.6 Liaison Officer
2.7 Information Officer
2.7.1 Public Information Officer
2.7.2 Community Involvement Coordinator
David Polish 215 814-3327
|
3. Participating Entities
|
|
No information available at this time.
|
4. Personnel On Site
|
|
On November 11, 2011, 1 Weston, 10 Kemron, 1 Kemron subcontractor and 1 EPA personnel were onsite.
On November 12, 2011, 4 Kemron subcontractor, 2 Kemron personnel were onsite.
On November 13, 2011, no personnel were onsite.
On November 14, 2011, 1 Weston, 10 Kemron, 5 Kemron subcontractor and 1 EPA personnel were onsite.
On November 15, 2011, 1 Weston, 10 Kemron, 5 Kemron subcontractor and 1 EPA personnel were onsite.
On November 16, 2011, 1 Weston, 10 Kemron, 2 Kemron subcontractor and 1 EPA personnel were onsite.
On November 17, 2011, 1 Weston, 10 Kemron and 1 EPA personnel were onsite.
On November 18, 2011, 1 Weston, 10 Kemron and 1 EPA personnel were onsite.
|
5. Definition of Terms
|
|
No information available at this time.
|
6. Additional sources of information
|
|
No information available at this time.
|
7. Situational Reference Materials
|
|
No information available at this time.
|
|
|