POLREP #39
Progress
ESI-PRP Removal
B5YS
Indianapolis, IN
Latitude: 39.9128600 Longitude: -86.2423680
|
|
To:
|
Sue Michael, City of Indianapolis
Tom White, Citizens Energy Group
Harry Atkinson, IDEM
Ryan Groves, IDEM
Megan Nagle, IDEM
George Ritchotte, IDEM
Jason Doerflein, Marion County Health Department
Sam Bruner, Pike Fire Department
John Maritote, U.S. EPA Region V
Janet Pope, U.S. EPA Region V
Kim Cussen, United Water
Stan Rigney, IDEM
Randy Braun, IDEM
Maupin Natalie, IDEM
Eric Kaufman, Marion County Health Department
Jason Ravenscroft, Marion County Health Department
Dan Sparks, USFWS
Ed Karecki, USFWS
Bob Masbaum, Citizens Energy Group
Kristen Heitman, Providence Wildlife
Michael Massonne, City of Indianapolis
Cheryl Carlson, Citizens Energy Group
Emily Mack, City of Indianapolis
Thomas Marks, U.S. EPA
Rex Osborn, IDEM
Gabriele Hauer, IDEM
Max Michael, IDEM
Deirdre Wyatt, IDEM
Jennifer Schick, City of Indianapolis
|
|
From:
|
Verrneta Simon, On-Scene Coordinator
|
|
Date:
|
1/17/2012
|
|
Reporting Period:
|
1/9/2012-1/13/2012
|
|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
B5YS |
|
Contract Number: |
|
|
D.O. Number: |
|
|
Action Memo Date: |
9/30/2010 |
|
Response Authority: |
CERCLA |
|
Response Type: |
PRP Oversight |
|
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
|
NPL Status: |
Non NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
4/6/2011 |
|
Start Date: |
4/6/2011 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
INN0051050501 |
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
|
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Bankrupt Commercial Used Oils Facility
1.1.2 Site Description
See POLREP 1
1.1.2.1 Location
4910 West 86th Street, Indianapolis, Indiana 46268
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
See POLREP 1
2.1.2 Response Actions to Date
On January 9, 2012, Midwest hauled off 2 loads (12,400 gal) of oily water from the control structure to United Waste Water Inc.’s facility in Cincinnati, OH.
- Midwest continued cleaning the control structure.
- Midwest pumped approximately 24,000 gallons of water from the east million gallon bunker to the west million gallon bunker so that they can start scraping the bottom of the east bunker tank.
- EQ continued pumping Tank 51 liquid contents into a solidification box and mixing it with paper pulp and TerraBond solidification media.
- EQ hauled off (6) 20 cyd roll-off boxes of solidified sludge to Southside Landfill in Indianapolis, IN.
- EQ received (2) 50,000 pound load of wood pulp solidification media from Appleton Papers, Inc. in Dayton, OH.
- Trihydro was unable to treat water due to frozen lines.
- Trihydro had a representative from McAllister Machinery on site to evaluate machinery and safety equipment for work in the bunker tanks.
On January 10, 2012, Midwest hauled off 1 load (6,200 gal) of oily water from the control structure to United Waste Water Inc.’s facility in Cincinnati, OH.
- Midwest received (2) 50,000 pound loads of wood pulp solidification media from Appleton Papers, Inc. in Dayton, OH.
- Midwest scraped the bottom east corner of the east bunker tank with a long reach excavator so that there would be no solidified sludge under the selected fill material. A photo taken from the southeast corner of the east bunker tank is attached to this POLREP.
- Midwest continued cleaning the control structure.
- Midwest solidified control structure sludge in the solidification pits.
- EQ continued pumping Tank 51 liquid contents into a solidification box and mixing it with paper pulp and lime solidification media.
- EQ hauled off (6) 20 cyd roll-off boxes of solidified sludge to Southside Landfill in Indianapolis, IN.
- EQ received (3) 50,000 pound loads of wood pulp solidification media from Appleton Papers, Inc. in Dayton, OH.
- Trihydro representative Ken Gollon, AVS (subcontractor to Trihydro) and START Rauh visited two potential "cement cleanout" fill sources for recon.
- Trihydro believes that this material will ease EPA’s concerns since it comes from a single source (cement mixing facility) and the small size will minimize potential void space problems.
- Trihydro collected samples of the material for laboratory analysis.
On January 11, 2012, Midwest hauled off 6 loads (35,932 gal) of oily water from the control structure, the Tank 51 frac tank, and the primary separator to United Waste Water Inc.’s facility in Cincinnati, OH.
- 0.4” of rain fell overnight and during the day.
- Midwest hauled off 5 totes (1,375 gal) of flocculent, 500 pounds of soda ash, and 500 pounds of citric acid United Waste Water Inc.’s facility in Cincinnati, OH for recycling.
- Midwest continued cleaning the control structure.
- Midwest solidified control structure sludge in the solidification pits.
- EQ continued pumping Tank 51 liquid contents into solidification boxes and mixing it with paper pulp and lime solidification media.
- EQ hauled off (9) 20 cyd roll-off boxes of solidified sludge to Southside Landfill in Indianapolis, IN.
- EQ received (3) 50,000 pound loads of wood pulp solidification media from Appleton Papers, Inc. in Dayton, OH.
- Roger Ward Engineering was on site continuing survey work to help them prepare their long term stormwater management plan.
- Trihydro representative Ken Gollon, AVS (subcontractor to Trihydro) and START Rauh visited a third potential bunker tank fill source.
- Trihydro collected samples of the material for laboratory analysis.
On January 12, 2012, Midwest hauled off 5 loads (28,200 gal) of oily water from the control structure and frac tank 11 to United Waste Water Inc.’s facility in Cincinnati, OH.
- 0.3” of rain and snow fell overnight and during the day.
- Midwest continued cleaning the control structure.
- Midwest solidified control structure sludge in the solidification pits.
- EQ continued pumping Tank 51 liquid contents into solidification boxes and mixing it with paper pulp and lime solidification media.
- EQ hauled off (5) 20 cyd roll-off boxes of solidified sludge to Southside Landfill in Indianapolis, IN.
- EQ received (3) 50,000 pound loads of wood pulp solidification media from Appleton Papers, Inc. in Dayton, OH.
On January 13, 2012, Midwest continued cleaning in the chemical building.
- 0.1” of snow (melted for measurement) fell overnight and during the day.
- Midwest worked on maintaining equipment.
- EQ continued pumping Tank 51 liquid contents into solidification boxes and mixing it with paper pulp and lime solidification media.
- EQ hauled off (2) 20 cyd roll-off boxes of solidified sludge to Southside Landfill in Indianapolis, IN.
- EQ received (3) 50,000 pound loads of wood pulp solidification media from Appleton Papers, Inc. in Dayton, OH.
- EQ mobilized a larger sludge pump.
- AVS was on site to begin evaluating bunker tank access.
The wood pulp and sawdust solidification materials are
reclaimed/recycled products. As of January 6, 2012, approximately
12,650,000 pounds of wood pulp solidification media, 1,800 tons of
sawdust solidification media have been used to solidify sludge.
Additionally, 880 tons of lime solidification media and 45 tons of
TerraBond solidification media had been used to solidify waste sludge.
2.1.3 Enforcement Activities, Identity of Potentially
Responsible Parties (PRPs)
N/A
2.1.4 Progress Metrics
| Waste Stream |
Medium |
Quantity |
Discharge |
Treatment |
Disposal |
| Oily Water |
Liquid |
4,320,616 gallons |
|
X |
|
| Stormwater |
Liquid |
437,356 gallons |
|
X |
|
| Tank 51 Containment |
Liquid |
452,051 gallons |
|
X |
|
| Totes and Drums |
Liquid |
13,310 gallons |
|
X |
|
| Solidified Sludge |
Solid |
24,940 cyd |
|
|
X |
| Unsolidified Sludge |
Liquid |
200 cyd |
|
X |
|
| Treated Stormwater |
Liquid |
723,665 gallons |
X |
|
|
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
- Increase the number of contractors on site to expedite site cleanup.
2.2.1.1 Planned Response Activities
None
2.2.1.2 Next Steps
U.S. EPA will provide oversight of PRP Group removal activities.
2.2.2 Issues
None
|
|
|
2.3 Logistics Section
|
|
|
|
Not applicable.
|
|
|
2.4 Finance Section
|
|
|
|
No information available at this time.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer
Not applicable.
2.6 Liaison Officer
Not applicable.
2.7 Information Officer
2.7.1 Public Information Officer
2.7.2 Community Involvement Coordinator
A date has not been selected for the next community meeting.
|
|
3. Participating Entities
|
|
|
3.1 Unified Command
Indiana Department of Environmental Management
Indianapolis Department of Public Works
Pike Township Fire Department
City of Indianapolis
3.2 Cooperating Agencies
Marion County Health Department
|
|
4. Personnel On Site
|
|
|
START Contractor
Trihydro
Midwest (subcontractor to Trihydro)
EQ (subcontractor to Trihydro)
Roger Ward Engineering (subcontractor to Trihydro)
AVS (subcontractor to Trihydro)
|
|
5. Definition of Terms
|
|
|
ASAOC – Administrative Settlement Agreement on Consent
ERRS – Emergency and Rapid Response Services
IDEM – Indiana Department of Environmental Management
OSC – On-Scene Coordinator
POLREP – Pollution Report
PRP - Potentially Responsible Party
RCRA – Resource Conservation and Recovery Act
START – Superfund Technical Assessment and Response Team
U.S. EPA – United States Environmental Protection Agency
|
|
6. Additional sources of information
|
|
|
6.1 Internet location of additional information/report
For additional information, please refer to the US EPA lead removal action website at www.epaosc.org/esi
6.2 Reporting Schedule
The next POLREP will be submitted at a date to be determined.
|
|
7. Situational Reference Materials
|
|
|
For additional information, please refer to the documents section at www.epaosc.org/esi
|
|
|