1. Introduction
|
|
1.1 Background
|
|
|
Site Number: |
10MC |
|
Contract Number: |
|
D.O. Number: |
|
|
Action Memo Date: |
8/28/2014 |
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
Response Lead: |
EPA |
|
Incident Category: |
Removal Action |
NPL Status: |
Non NPL |
|
Operable Unit: |
|
Mobilization Date: |
10/13/2014 |
|
Start Date: |
10/13/2014 |
Demob Date: |
|
|
Completion Date: |
|
CERCLIS ID: |
WAN001002396 |
|
RCRIS ID: |
|
ERNS No.: |
|
|
State Notification: |
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time-Critical Removal Action
1.1.2 Site Description
See initial POLREP.
1.1.2.1 Location
See initial POLREP.
1.1.2.2 Description of Threat
See initial POLREP.
1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results
See initial POLREP.
|
2. Current Activities
|
|
2.1 Operations Section
|
|
|
2.1.1 Narrative
During the seasonal work shutdown period, the RPs consultant, Resource Environmental Management Consultants (REMC) monitored site conditions, overpacked and removed the drums that had been staged prior to the seasonal work shutdown, excavated 13 test pits north of Harrier Creek Road to determine the depth of tailings, and conducted a pre-construction season site meeting.
2.1.2 Response Actions to Date
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
2.1.4 Progress Metrics
During the reporting period, the staged drums were removed from the site. The manifests are not available at this time.
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
2.2.1 Anticipated Activities
Site work is scheduled to begin May 18, 2015. The anticipated work schedule is as follows:
May 2015
- Excavate and haul surrounding soils east of Goldfield Mine Road at slough area.
- Construct Wedge Buttress
- Confirmation sampling of Disturbed Areas south of the impoundment
June 2015
- Complete Wedge Buttress construction
- Excavate perimeter of the impoundment
- Excavate tailings north of Harrier Creek Road
- Clean up haul road
- Excavate material south of Harrier Creek Road
- Clear and grub borrow soil areas
- Stockpile topsoil
July 2015
- Complete excavation of materials south of Harrier Creek Road
- Confirmation sampling of disturbed areas north of the impoundment
- Grade the impoundment
- Place ecological barrier on the impoundment
August 2015
- Complete placement of ecological barrier
- Excavation and placement of cover soils
- Recontour the consolidation areas
September 2015
- Completion of recontouring of consolidation areas
- Place top soil in the mill area, impoundment perimeter, on Arrington property.
- Construction of the fence around the impoundment and adit
- Revegitation of the disturbed areas.
2.2.1.1 Planned Response Activities
2.2.1.2 Next Steps
2.2.2 Issues
|
|
2.3 Logistics Section
|
|
|
No information available at this time.
|
|
2.4 Finance Section
|
|
|
No information available at this time.
|
|
2.5 Other Command Staff
|
|
|
No information available at this time.
|
3. Participating Entities
|
|
3.1 Unified Command
3.2 Cooperating Agencies
Colville Confederated Tribes.
Washington State Department of Ecology
|
4. Personnel On Site
|
|
Personnel on-site for the pre-construction meeting:
EPA OSC - Rees
START - Nordeen
RMC - Fricke
ACI - Sullens, Chavez
Durham, Jones, & Pinegar - Randell
|
5. Definition of Terms
|
|
No information available at this time.
|
6. Additional sources of information
|
|
6.1 Internet location of additional information/report
6.2 Reporting Schedule
RMC is providing monthly reports. Once construction season begins, RMC will provide weekly reports.
|