U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Blair WaterwayTBT

All POL/SITREP's for this site Blair WaterwayTBT
Tacoma, WA - EPA Region X
POLREP #2
Progress
Printer Friendly  |   PDF
 
U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Blair WaterwayTBT - Removal Polrep

EPA Emergency Response

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region X

Subject: POLREP #2
Progress
Blair WaterwayTBT
10MY
Tacoma, WA
Latitude: 47.2734526 Longitude: -122.4079141


To:
From: Kathy Parker, OSC
Date: 9/28/2015
Reporting Period: 9/15/2015 to 9/28/2015

1. Introduction
  1.1 Background
   
Site Number: 10MY    Contract Number:  
D.O. Number:      Action Memo Date: 1/27/2015
Response Authority: CERCLA    Response Type: Time-Critical
Response Lead: PRP    Incident Category: Removal Action
NPL Status: Non NPL    Operable Unit:
Mobilization Date: 4/13/2015    Start Date: 4/13/2015
Demob Date:      Completion Date:  
CERCLIS ID: WAD980726368    RCRIS ID:
ERNS No.:    State Notification:
FPN#:    Reimbursable Account #:

1.1.1 Incident Category
Time Critical Removal Action

1.1.2 Site Description

Tributyl tin-contaminated sediments under Pier 4 in Tacoma, Washington.

1.1.2.1 Location

1 Sitkum Way, Tacoma, WA

1.1.2.2 Description of Threat

Tributyltin at levels exceeding 50,000 ug/kg were found in the sediments under Pier 4 during a predredge sampling performd by the Port of Tacoma in 2013. Tributyltin is an environmental toxin affecting mollusks and was banned in the 1990s.

1.1.3 Preliminary Removal Assessment/Removal Site Inspection Results

The Port of Tacoma collected and analyzed samples of sediment under Pier 4 in July 2014 to determine the extent and depth of contamination. Results indicated a removal action was necessary to dredge and remove approximately 50,000 cubic yards of sediment.

 

2. Current Activities
  2.1 Operations Section
   

2.1.1 Narrative

2.1.2 Response Actions to Date
The Port of Tacoma began work in April 2015 to mobilize equipment to Pier 4 and start disconnecting utilities. Work then proceeded with removal of the pier deck. On June 15, 2015, OMI (contractor to the Port of Tacoma) began pulling the pilings holding up the pier deck using a vibratory hammer. On August 17, 2015 OMI began removing clean sediment upslope from the contaminated sediment and dumping it at an open-water disposal site managed by the Department of Natural Resources. Removal of clean sediments was completed on September 14, 2015.

On September 15, 2015, OMI began dredging TBT-contaminated sediments, barging it to the APM terminal (contiguous to Pier 4), transloading the sediments to trucks, and hauling the material to the LRI waste disposal facility. Water dredged with the sediment was pumped to a holding pond, treated to remove TBT, and discharged to Puget Sound. Water quality testing results indicate the treatment system was effective at removing TBT and particulates and that the dredging was not mobilizing particulates or TBT off-site above levels of concern.

2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)

The Port of Tacoma is the PRP performing the removal action. research is being conducted to identify additional PRPs.

2.1.4 Progress Metrics

Waste Stream Medium Quantity Manifest # Treatment Disposal
           
           
           


  2.2 Planning Section
   

2.2.1 Anticipated Activities
A news release was issued by EPA on September 25, 2015 that contaminated dredging had begun.

2.2.1.1 Planned Response Activities

Contaminated dredging and operation of the transload and water treatment site at APM terminal is expected to continue into December 2015.

2.2.1.2 Next Steps

2.2.2 Issues

  2.3 Logistics Section
    No information available at this time.

  2.4 Finance Section
    No information available at this time.

  2.5 Other Command Staff
    No information available at this time.

3. Participating Entities
  No information available at this time.

4. Personnel On Site
 

EPA

The Port of Tacoma

Orion Marine Contractors (OMI)

Subcontractors to OMI

 

5. Definition of Terms
  No information available at this time.

6. Additional sources of information
  No information available at this time.

7. Situational Reference Materials
  No information available at this time.