U.S. ENVIRONMENTAL PROTECTION AGENCY
POLLUTION/SITUATION REPORT
Town of Pines Groundwater Plume - OU2 - Removal Polrep

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
Region V
|
|
Subject:
|
POLREP #3
Progress
Town of Pines Groundwater Plume - OU2
B5V9
Town of Pines, IN
Latitude: 41.6887279 Longitude: -86.9440403
|
|
To:
|
Mark Johnson, ATSDR
Valencia Darby, U.S. DOI
Mark Durno, U.S. EPA
HQ EOC, U.S. EPA
John Glover, U.S. EPA
Matt Mankowski, U.S. EPA
Mike Ribordy, U.S. EPA
Joe Ferry, NIPSCO
Doug Petroff, Project Coordinator
Dan Sullivan, NIPSCO
Bill Haswell, Haley & Aldrich
Erik Hardin, USEPA
Motria Caudill, ATSDR
Shelly Lam, USEPA
Jeff Lippert, U.S. EPA
Greg Gehrig, USEPA
Jennifer Elkins, USEPA
Susan Lingenfelser, DOI
Rachel Linduska, EPA
Allison Lippert, EPA
Tamara Carnovsky, EPA
Jamie Stoik, U.S. EPA
Steve Ridenour, U.S. EPA
Mick Hans, US EPA
Luke Jones, U.S. EPA
|
|
From:
|
Jacob Hassan, On-Scene Coordinator
|
|
Date:
|
9/23/2016
|
|
Reporting Period:
|
8/11/2016 - 9/9/2016
|
|
1. Introduction
|
|
|
1.1 Background
|
|
|
|
|
Site Number: |
B5V9 |
|
Contract Number: |
|
|
D.O. Number: |
|
|
Action Memo Date: |
10/15/2015 |
|
Response Authority: |
CERCLA |
|
Response Type: |
Time-Critical |
|
Response Lead: |
PRP |
|
Incident Category: |
Removal Action |
|
NPL Status: |
NPL |
|
Operable Unit: |
|
|
Mobilization Date: |
6/6/2016 |
|
Start Date: |
6/7/2016 |
|
Demob Date: |
|
|
Completion Date: |
|
|
CERCLIS ID: |
INN000505593 |
|
RCRIS ID: |
|
|
ERNS No.: |
|
|
State Notification: |
|
|
FPN#: |
|
|
Reimbursable Account #: |
|
1.1.1 Incident Category
Time Critical Removal
1.1.2 Site Description
See PolRep # 1
|
|
2. Current Activities
|
|
|
2.1 Operations Section
|
|
|
|
2.1.1 Narrative
Site operational hours are Monday - Friday 7 am to 5 pm
EPA and START continue to provide technical oversight of all removal activities on site. START is collecting a subset of split samples for comparison and validation of NIPSCO confirmation samples. Air monitoring and off-site borrow source activities are ongoing.
2.1.2 Response Actions to Date
Below is a status summary of each of the properties and where they are at in the removal process.
GS042
Sod placement begins and landscape restoration work continues.
-
Obtain property owner approval for pre-design survey work -
COMPLETED
-
Conduct subsurface utility survey-
COMPLETED
-
Conduct site topographic and
property boundary survey- COMPLETED
-
Conduct landscape inventory-
COMPLETED
-
Complete Design Drawings and obtain
USEPA approval- COMPLETED
-
Obtain property owner approval for
removal work- COMPLETED
-
Photo document pre-excavation
conditions- COMPLETED
-
Conduct building condition survey,
if applicable- COMPLETED
-
Mobilize for construction-
COMPLETED
-
Install site security and access
controls- COMPLETED
-
Install erosion and sedimentation
controls- COMPLETED
-
Establish construction controls and
facilities- COMPLETED
-
Establish decontamination
facilities for personnel and equipment- COMPLETED
-
Clear and grub - COMPLETED
-
Conduct excavation activities -
COMPLETED
-
Conduct confirmation sampling -
COMPLETED
-
Place a marker barrier in
excavations where target materials remain in place - COMPLETED
-
Backfill excavation – COMPLETED
-
Complete landscape restoration – ON-GOING
-
Demobilize – NOT STARTED
GS037
-
Obtain property owner approval for pre-design survey work -
COMPLETED
-
Conduct subsurface utility survey-
COMPLETED
-
Conduct site topographic and
property boundary survey- COMPLETED
-
Conduct landscape inventory-
COMPLETED
-
Complete Design Drawings and obtain
USEPA approval- COMPLETED
-
Obtain property owner approval for
removal work- COMPLETED
-
Photo document pre-excavation
conditions- COMPLETED
-
Conduct building condition survey,
if applicable- COMPLETED
-
Mobilize for construction-
COMPLETED
-
Install site security and access
controls- COMPLETED
-
Install erosion and sedimentation
controls- COMPLETED
-
Establish construction controls and
facilities- COMPLETED
-
Establish decontamination
facilities for personnel and equipment- COMPLETED
-
Clear and grub - COMPLETED
-
Conduct excavation activities -
COMPLETED
-
Conduct confirmation sampling -
COMPLETED
-
Place a marker barrier in
excavations where target materials remain in place - COMPLETED
-
Backfill excavation – COMPLETED
-
Complete landscape restoration –
NOT STARTED
-
Demobilize – NOT STARTED
GS089
-
Obtain property owner approval for pre-design survey work -
COMPLETED
-
Conduct subsurface utility survey-
COMPLETED
-
Conduct site topographic and
property boundary survey- COMPLETED
-
Conduct landscape inventory-
COMPLETED
-
Complete Design Drawings and obtain
USEPA approval- COMPLETED
-
Obtain property owner approval for
removal work- COMPLETED
-
Photo document pre-excavation
conditions- COMPLETED
-
Conduct building condition survey,
if applicable- COMPLETED
-
Mobilize for construction-
COMPLETED
-
Install site security and access
controls- COMPLETED
-
Install erosion and sedimentation
controls- COMPLETED
-
Establish construction controls and
facilities- COMPLETED
-
Establish decontamination
facilities for personnel and equipment- COMPLETED
-
Clear and grub - COMPLETED
-
Conduct excavation activities -
COMPLETED
-
Conduct confirmation sampling -
COMPLETED
-
Place a marker barrier in
excavations where target materials remain in place - COMPLETED
-
Backfill excavation – COMPLETED
-
Complete landscape restoration –
NOT STARTED
-
Demobilize – NOT STARTED
GS014
Grading of topsoil and gravel in driveway area complete.
-
Obtain property owner approval for pre-design survey work -
COMPLETED
-
Conduct subsurface utility survey-
COMPLETED
-
Conduct site topographic and
property boundary survey- COMPLETED
-
Conduct landscape inventory-
COMPLETED
-
Complete Design Drawings and obtain
USEPA approval- COMPLETED
-
Obtain property owner approval for
removal work- COMPLETED
-
Photo document pre-excavation
conditions- COMPLETED
-
Conduct building condition survey,
if applicable- COMPLETED
-
Mobilize for construction-
COMPLETED
-
Install site security and access
controls- COMPLETED
-
Install erosion and sedimentation
controls- COMPLETED
-
Establish construction controls and
facilities- COMPLETED
-
Establish decontamination
facilities for personnel and equipment- COMPLETED
-
Clear and grub - COMPLETED
-
Conduct excavation activities -
COMPLETED
-
Conduct confirmation sampling -
COMPLETED
-
Place a marker barrier in
excavations where target materials remain in place - COMPLETED
-
Backfill excavation – COMPLETED
-
Complete landscape restoration –
NOT STARTED
-
Demobilize – NOT STARTED
GS012/GS054
Backfilling and backfill grading work on-going. Additional marker barrier will be placed on
south side of property prior to backfilling once ponding in area dries.
-
Obtain property owner approval for pre-design survey work -
COMPLETED
-
Conduct subsurface utility survey-
COMPLETED
-
Conduct site topographic and
property boundary survey- COMPLETED
-
Conduct landscape inventory-
COMPLETED
-
Complete Design Drawings and obtain
USEPA approval- COMPLETED
-
Obtain property owner approval for
removal work- COMPLETED
-
Photo document pre-excavation
conditions- COMPLETED
-
Conduct building condition survey,
if applicable- COMPLETED
-
Mobilize for construction-
COMPLETED
-
Install site security and access
controls- COMPLETED
-
Install erosion and sedimentation
controls- COMPLETED
-
Establish construction controls and
facilities- COMPLETED
-
Establish decontamination
facilities for personnel and equipment- COMPLETED
-
Clear and grub - COMPLETED
-
Conduct excavation activities -
COMPLETED
-
Conduct confirmation sampling -
COMPLETED
-
Place a marker barrier in
excavations where target materials remain in place - ONGOING
-
Backfill excavation – ON-GOING
-
Complete landscape restoration –
NOT STARTED
-
Demobilize – NOT STARTED
GS052
ENTACT begins backfilling and
backfill grading on the north side of the property. Final excavation survey information indicated
that the south center area of the excavation at GS052 was not at 3’ bgs. Haley and Aldrich collected a confirmation
sample from the area to determine if additional excavation work will be
necessary. START collected a split of
the confirmation sample.
-
Obtain property owner approval for pre-design survey work -
COMPLETED
-
Conduct subsurface utility survey-
COMPLETED
-
Conduct site topographic and
property boundary survey- COMPLETED
-
Conduct landscape inventory- COMPLETED
-
Complete Design Drawings and obtain
USEPA approval- COMPLETED
-
Obtain property owner approval for
removal work- COMPLETED
-
Photo document pre-excavation
conditions- COMPLETED
-
Conduct building condition survey,
if applicable- COMPLETED
-
Mobilize for construction-
COMPLETED
-
Install site security and access
controls- COMPLETED
-
Install erosion and sedimentation
controls- COMPLETED
-
Establish construction controls and
facilities- COMPLETED
-
Establish decontamination
facilities for personnel and equipment- COMPLETED
-
Clear and grub – COMPLETED
-
Conduct excavation activities – ON-GOING
-
Conduct confirmation sampling – ON-GOING
-
Place a marker barrier in
excavations where target materials remain in place – ON-GOING
-
Backfill excavation – ON-GOING
-
Complete landscape restoration –
NOT STARTED
-
Demobilize – NOT STARTED
GS081
ENTACT continues conducting excavation work on the east side
of the property. Excavation area to
extend south of current extent based upon XRF screening conducted by Haley and
Aldrich.
-
Obtain property owner approval for pre-design survey work -
COMPLETED
-
Conduct subsurface utility survey-
COMPLETED
-
Conduct site topographic and
property boundary survey- COMPLETED
-
Conduct landscape inventory-
COMPLETED
-
Complete Design Drawings and obtain
USEPA approval- COMPLETED
-
Obtain property owner approval for
removal work- COMPLETED
-
Photo document pre-excavation
conditions- COMPLETED
-
Conduct building condition survey,
if applicable- COMPLETED
-
Mobilize for construction- COMPLETED
-
Install site security and access
controls- COMPLETED
-
Install erosion and sedimentation
controls- COMPLETED
-
Establish construction controls and
facilities- COMPLETED
-
Establish decontamination
facilities for personnel and equipment- COMPLETED
-
Clear and grub – COMPLETED
-
Conduct excavation activities – ON-GOING
-
Conduct confirmation sampling – NOT
STARTED
-
Place a marker barrier in
excavations where target materials remain in place - NOT STARTED
-
Backfill excavation – NOT STARTED
-
Complete landscape restoration –
NOT STARTED
-
Demobilize – NOT STARTED
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
NIPSCO is the identified PRP
2.1.4 Progress Metrics
Metrics are reported through 8/31/2016
| ITEM |
UNIT |
CUMULATIVE |
| Clean Fill Delivered |
CY |
26,064 |
| Solid Waste
Reused On-Site |
TON |
0 |
| Water Used
On-Site |
GAL |
497,801 |
| Fuel Used
On-Site (Diesel) |
GAL |
5,983 |
| Electricity
Used On-Site |
kWh |
2,751 |
1,764 loads of soil have been hauled off-site
|
Waste Stream
|
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
|
Soil
|
|
45,549 tons |
|
Disposal |
Forest Lawn Landfill - Three Oaks, MI
|
| Debris |
|
169 tons |
|
Disposal |
Forest Lawn Landfill - Three Oaks, MI |
| |
|
|
|
|
|
|
|
|
2.2 Planning Section
|
|
|
|
2.2.1 Anticipated Activities
- Continue regularly project call.
- NIPSCO and their contractor, Haley & Aldrich, continue to investigate properties for elevated levels of arsenic, lead and thallium.
- NIPSCO continues to negotiate access with some properties that are identified as needing a removal action.
2.2.1.1 Planned Response Activities
Sequencing of Events for Each Removal Action.
2.2.1.2 Next Steps
Continue to gain access to identified properties.
2.2.2 Issues
|
|
|
2.3 Logistics Section
|
|
|
|
No information available at this time.
|
|
|
2.4 Finance Section
|
|
|
|
2.4.1 Narrative
Funding for the this removal action is from the special account established for the Town of Pines Groundwater Plume Site.
|
|
|
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| TAT/START |
$220,000.00 |
$177,321.79 |
$42,678.21 |
19.40% |
|
Intramural Costs
|
| |
| Total Site Costs |
$220,000.00 |
$177,321.79 |
$42,678.21 |
19.40% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
|
|
|
2.5 Other Command Staff
|
|
|
|
2.5.1 Safety Officer
Entact - Jerry Overton
2.5.2 Liaison Officer
USEPA - Eileen Deamer
2.5.3 Information Officer
USEPA - Sue Pastor and Rachel Bassler
NIPSCO - Nick Meyer and Angie Nelson
|
|
3. Participating Entities
|
|
|
3.1 Unified Command
3.2 Cooperating Agencies
- IDEM
- Town of Pines
- National Park Service
- US Fish and Wildlife
- NIPSCO
- Haley & Aldrich
- Entact
|
|
4. Personnel On Site
|
|
|
Onsite Staff:
- EPA - 1
- START - 2
- NIPSCO - 3
- Haley & Aldrich - 6
- Entact - 30
|
|
5. Definition of Terms
|
|
|
EPA - United Stated Environmental Protection Agency
START - Superfund Technical Assistance and Response Team
RML - Removal Management Level
AOC - Administrative Order on Consent
mg/kg - milligrams per kilogram
RI/FS - Remedial Investigation/ Feasibility Study
|
|
6. Additional sources of information
|
|
|
6.1 Internet location of additional information/report
http://www.epa.gov/superfund/town-pines-groundwater
6.2 Reporting Schedule
As needed
|
|
7. Situational Reference Materials
|
|
|
No information available at this time.
|
|
POLREP #3 Last Updated 9/23/2016
|
|
|