2.1.1 Narrative
Responsible Parties initiated the cleanup on 11/16/2015. EPA OSC and EPA START oversaw the cleanup onsite at all times. The overall goal of the removal action is to remove the threat of lead exposure to surrounding residents and workers from surface soil through: 1) removal of soil contaminated with high levels of lead above the EPA RML, and 2) placement of permanent covers at the Site.
2.1.2 Response Actions to Date
(Response actions from 11/16 to 11/20/2015.)
BNSF (Railroad PRP) and its contractors mobilized to the site and completed removal of about 1150 feet of rail and about 575 wooden railroad ties in Site Areas: 1,2,4,5,6,8,&10 (see photo attached to POLREP). The railroad ties were transported off-site to a BNSF staging area (near the Site) for disposition (at an energy recovery facility) at later date. The rails were staged in a gated empty lot next to the Site (after getting owner permission) for recycling at a later date. At all phases of the cleanup water was discharged on to the ground in the work areas to ensure dust control. In addition, sidewalks were also cleaned to make sure that dirt tracked in and out by vehicles was removed (swept back to the Site). (Work to remove the rails and ties was completed on 11/19/2015).
GHD (H.Kramer and & Co. contractors) coordinated the cleanup crews onsite and conducted particulate monitoring (upwind and downwind). BNSF conducted its own worker personal protection air monitoring (under OSHA). The personal protection air monitoring results were below the criteria to the extent that the workers were able to go to a PPE modified level D on 11/17 after being in Level C on 11/16.
EPA OSC and START contractors observed the cleanup to ensure compliance with the work plan and conducted air monitoring in coordination with GHD.
GHD and EPA conduct air monitoring using DataRAM
4 and DustTraks for dust in air. EPA utilized a
Gilian to monitor START personnel exposure, sampling for arsenic, cadmium, chromium,
and lead particulates in air.
EPA START reported that the average DataRAM 4 downwind dust particulate reading for
this week was 0.0140 mg/m3. The average pDR dust particulate
reading for this week was 0.0094 mg/m3. (The action levels
START developed for the site are 0.812 mg/m3 for Areas 8 and 9, 1.19
mg/m3 for Areas 4, 5, 6, 7, and 10, and 3.19 mg/m3 for
Areas 1 and 2.) GHD has a single action level of 0.480 mg/m3. The off-site dust particulate action level is any sustained downwind reading of
0.150 mg/m3 above background or the upwind reading. No action
levels (for dust) were exceeded.
EPA OSC and GHD met with the principal (Benito Juarez Academy, High School adjacent to Areas 1 and 2) to coordinate work schedule and addressed all health and safety concerns from the high school. Controls such as maintaining safe distance and air monitoring carried out by EPA START and OSC (plus BNSF and GHD personnel) were in place to ensure protection of students and teachers.
EPA OSC met with representatives of the Community Group PERRO on 11/16 in the morning. They were concerned about the dust issues and the OSC briefed them on the work and dust controls in place.
EPA OSC coordinating with the Alderman's (Solis) Office to help address homeless trespassers at the Site and an abandoned van and dumpster (blocking work in Area 8). The Van was removed by the City on 11/20/2015.
2.1.3 Enforcement Activities, Identity of Potentially Responsible Parties (PRPs)
On 9/29/2015 EPA signed an Settlement Agreement and Order on Consent For Removal Action with the PRPs for the Site: H.Kramer and Company, City of Chicago, and BNSF Railway Company.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal |
Railroad ties (wood) |
|
575 feet |
|
|
disposal thru energy recovery |
Rails (steel) |
|
1150 |
|
|
to be recycled. |
|
|
|
|
|
|
|