2.1.1 Narrative
Responsible Parties initiated
the cleanup at the Site on 11/16/2015. EPA OSC and EPA START oversaw the cleanup
onsite at all times. The overall goal of the removal action is to remove
the threat of lead exposure to surrounding residents and workers from surface
soil through: 1) removal of soil contaminated with high levels of lead above
the EPA RML, and 2) placement of permanent covers at the Site.
2.1.2 Response Actions
to Date
The following are response actions
from 11/30 to 12/4/2015. EPA, START, and H. Kramer contractors [GHD (prime), RW Collins (soil excavation),& Hygieneering (H&S, Monday only)] are onsite. Response actions from 11/16 to 11/25 are documented in the previous POLREPS #1 and #2.
The overall goals for the week was to: 1) remove vegetation, garbage and other solid waste from Areas 1 and 2 ; 2) Excavate Area 1 to appropriate depth to meet cleanup levels; 3) Conduct additional treatment of soil as needed. These goals were achieved as described in the following day to day work:
Monday 11/30 to Tuesday 12/1:
- RW Collins conducted and completed solid waste (garbage, and vegetation)
removal activities in western portion of Area 1. The waste was stockpiled in the vacant lot north of western Area 1. There is a large amount of garbage from this area which was used as an encampment for homeless in the area. In addition, there were three large abandoned power poles, and rail ties mixed into the solid waste.
Wednesday 12/2 :
-
Chicago Streets and Sanitation arrived on-site to assist in the removal of garbage and vegetation in Areas 1(eastern portion) and 2. In addition, they transported all of the solid waste off-site to the Shred-all solid waste transfer station (43rd and Racine) in Chicago. EPA OSC had previously called the Alderman's Office for assistance to help dispose of the large amounts of garbage in Areas 1 and 2.
-
GHD's TLCP lead results came back and the results were below the TCLP criteria for lead in Area 4 and the eastern portion of Area 8. However, TCLP lead results for the Area 8 were still above the Haz criteria and so H. Kramer contractor RW Collins conducted additional treatment in the western 50’ of soil in Area 8. After treatment samples were collected (EPA collected split samples) for lab analysis.
-
RW Collins begins soil excavation of western portion of Area
1. The excavation started on the west end. The first 50 feet on the west end was already at the lead cleanup level (below 800mg.kg) and 3 inches (bgs) of soil was removed in this area to make room for the gravel cover. There after excavation was conducted to 6 inches bgs as described in the work plan.
-
To confirm that the cleanup goal is being met, EPA OSC and START began collecting and screening soil samples with
the XRF as RW Collins progressed with the excavation in western portion of Area 1.
Thursday, 12/3:
- Excavation of the western portion of Area 1 at 6
inch bgs continued. EPA OSC and START collected surface
soil samples at about 40-50 foot horizontal intervals and evaluated using the XRF to confirm
that cleanup levels are being met. Excavated soil was stockpiled over plastic sheets in the open
parking area north of Area 1. EPA soil samples were sent to the START lab for analyses (total lead).
Friday, 12/4
- Excavation in the western portion Area 1 was completed. The final 54 feet was excavated down to 2 feet because the XRF lead concentration results were consistently above 1500 mg/kg. EPA and GHD determined this was a low drainage point in the area and it was decided to excavated down to the 2 feet bgs to meet the goals specified in the EPA Action memo.
- GHD and RW Collins initiated grading work in Area 2 and Eastern portion of Area 1 to prepare the ground for the gravel/asphalt cover.
- 17 truck loads of gravel arrived and were staged at the parking lot north of Area 1 for use in grading and cover in (366.6 tons) Area 1 and Area 2.
- Soil piles in the vacant parking lot and in Area 4 were covered and secured for the weekend.
-The EPA TCLP lead results for the 2 split samples from the Area
4 piles were 0.23 mg/L and 0.8 mg/l. The TCLP lead results for the 2
split samples from Area 8 were 0.029 mg/L and 2.4 mg/L.
Throughout the reporting period GHD and EPA
continued to conduct air monitoring with DataRAM 4 and DustTraks for dust in
air. EPA monitored downwind with GHD. GHD had an additional
monitoring location upwind with a DustTrak. EPA conducted additional air
monitoring with a PDR for dust in air the PDR held by START personnel collected dust data for
continuous monitoring near work areas.
The average PDR reading for the week is 0.0157 mg/m3
and average DataRAM 4 reading for the week is 0.0313 mg/m3.
No action levels (for dust) were exceeded.
Note: The action levels EPA START developed for the
site are 0.812 mg/m3 for Areas 8 and 9, 1.19 mg/m3 for
Areas 4, 5, 6, 7, and 10, and 3.19 mg/m3 for Areas 1 and 2.)
GHD has a single action level of 0.480 mg/m3. The
off-site dust particulate action level is any sustained downwind reading of
0.150 mg/m3 above background or the upwind reading.
2.1.3 Enforcement Activities, Identity of Potentially
Responsible Parties (PRPs)
On
9/29/2015 EPA signed an Settlement Agreement and Order on Consent For Removal
Action with the PRPs for the Site: H.Kramer and Company, City of Chicago, and
BNSF Railway Company.
2.1.4 Progress Metrics
Waste Stream |
Medium |
Quantity |
Manifest # |
Treatment |
Disposal
|
Railroad ties (wood) |
|
575 feet |
|
|
disposal thru energy recovery |
Rails (steel) |
|
1150 feet |
|
|
to be recycled. |
Lead contaminated Soil(> TCLP Lead )
-------------------------------
Garbage and vegetation
|
|
105 cubic yards excavated and treated
------------------
38.8 tons
|
|
|
Soil excavated and treated on-site (estimate)
------------------------
Shred-Al solid waste transfer station (Chicago)
|
|